MED-SR 94-07.66
MED County · est $0.7M
Bid dateThursday, May 27—
MED County · est $0.7M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 72 more items below.
| Item | Quantity | R1Stanley Miller Construction Company | R2Rietschlin Construction INC | R3Adena Corporation | R4Eclipse CO LLC | R5Kenmore Construction CO INC | R6Lockhart Concrete CO | R7Black Horse Bridge Construction INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 611E22901 54" CONDUIT, TYPE D, AS PER PLAN | 307 FT | $378 | $270 | $459 | $260 | $205 | $450 | $280 | 22% |
| 611E95001 10' X 5' CONDUIT, TYPE A, 706.05, AS PER PLAN | 43 FT | $1,729 | $1,900 | $2,047 | $2,100 | $2,700 | $3,000 | $1,600 | 14% |
| Item | Quantity | R1Stanley Miller Construction Company | R2Rietschlin Construction INC | R3Adena Corporation | R4Eclipse CO LLC | R5Kenmore Construction CO INC | R6Lockhart Concrete CO | R7Black Horse Bridge Construction INC |
|---|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $7,223 | $8,800 | $8,862 | $12,456 | $10,000 | $20,000 | $16,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 82 FT | $5.00 | $22.00 | $46.19 | $23.00 | $15.00 | $10.00 | $10.00 |
| 202E35200 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 82 CY |
| $408 |
| $775 |
| $317 |
| $732 |
| $620 |
| $300 |
| $600 |
| 6% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $31,800 | $5,000 | $9,705 | $11,500 | $8,500 | $19,000 | $5,000 | 6% |
| 203E10000 EXCAVATION | 1,554 CY | $20.00 | $12.50 | $12.15 | $12.00 | $22.00 | $12.00 | $20.00 | 6% |
| 203E20000 EMBANKMENT | 1,719 CY | $17.60 | $11.50 | $9.18 | $12.50 | $12.00 | $12.00 | $30.00 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $24,500 | $30,000 | $7,574 | $24,911 | $20,000 | $29,000 | $20,000 | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 158 CY | $153 | $148 | $242 | $142 | $140 | $137 | $137 | 5% |
| 606E15050 GUARDRAIL, TYPE MGS | 887.5 FT | $19.67 | $22.00 | $2.17 | $19.50 | $17.70 | $22.00 | $19.60 | 3% |
| 659E00300 TOPSOIL | 370 CY | $44.50 | $24.50 | $30.64 | $42.50 | $25.00 | $20.00 | $40.00 | 3% |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 146 CY | $107 | $127 | $182 | $115 | $100 | $126 | $100 | 3% |
| 832E30000 EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 203E98500 ROADWAY, MISC.:DE-WATERING | 1 LS | $15,000 | $8,000 | $12,316 | $15,000 | $20,000 | $2,000 | $50,500 | 3% |
| 203E35110 GRANULAR MATERIAL, TYPE B | 182 CY | $73.35 | $66.00 | $60.90 | $71.50 | $65.00 | $50.00 | $86.00 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 56 CY | $235 | $228 | $266 | $220 | $215 | $211 | $211 | 2% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $12,944 | $20,000 | $2,534 | $25,000 | $20,000 | $9,900 | $60,000 | 2% |
| 304E20000 AGGREGATE BASE | 143 CY | $90.00 | $96.00 | $76.97 | $75.00 | $65.00 | $50.00 | $85.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 581 SY | $21.15 | $24.00 | $15.16 | $23.50 | $25.00 | $12.00 | $32.00 | 2% |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 9 EACH | $1,350 | $1,070 | $1,496 | $1,348 | $1,215 | $1,000 | $985 | 2% |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 1,635 SY | $5.50 | $6.00 | $6.68 | $5.00 | $4.20 | $6.75 | $5.00 | 2% |
| 102 FT |
| $25.00 |
| $40.00 |
| $24.84 |
| $25.50 |
| $20.00 |
| $25.00 |
| $90.00 |
| 202E38000 GUARDRAIL REMOVED | 405 FT | $2.50 | $4.00 | $6.25 | $3.00 | $2.00 | $2.00 | $3.00 |
| 202E53100 MAILBOX REMOVED | 1 EACH | $100 | $150 | $640 | $61.50 | $40.00 | $50.00 | $1,000 |
| 202E98100 REMOVAL MISC.: LANDSCAPE LIGHT RETURNED TO OWNER | 2 EACH | $100 | $680 | $320 | $30.50 | $40.00 | $100 | $50.00 |
| 202E98100 REMOVAL MISC.: POST | 5 EACH | $68.00 | $170 | $128 | $12.50 | $20.00 | $50.00 | $32.00 |
| 204E10000 SUBGRADE COMPACTION | 954 SY | $1.00 | $3.25 | $4.64 | $1.50 | $2.00 | $3.00 | $5.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 108 CY | $25.25 | $21.00 | $40.59 | $12.00 | $22.00 | $12.00 | $35.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 108 CY | $50.50 | $65.00 | $60.09 | $67.00 | $65.00 | $40.00 | $70.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $100 | $162 | $246 | $228 | $100 | $100 | $250 |
| 204E50000 GEOTEXTILE FABRIC | 234 SY | $1.00 | $4.00 | $2.36 | $2.00 | $3.00 | $5.00 | $3.00 |
| 606E15051 GUARDRAIL, TYPE MGS, AS PER PLAN | 87.5 FT | $21.89 | $80.00 | $24.26 | $22.00 | $25.00 | $100 | $74.80 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 1 EACH | $2,611 | $2,117 | $2,894 | $2,607 | $2,350 | $1,950 | $1,960 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350/MASH 2016) | 1 EACH | $2,889 | $2,680 | $3,202 | $2,884 | $2,600 | $2,350 | $2,480 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 1 EACH | $2,367 | $2,320 | $2,623 | $2,363 | $2,130 | $2,200 | $2,145 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $550 | $205 | $406 | $150 | $250 | $150 | $195 |
| 601E11000 RIPRAP, TYPE D | 62 SY | $80.00 | $91.00 | $183 | $106 | $100 | $30.00 | $100 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $81.00 | $188 | $1,009 | $189 | $250 | $100 | $150 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 5 CY | $150 | $330 | $123 | $222 | $300 | $120 | $150 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $100 | $54.00 | $326 | $30.50 | $25.00 | $200 | $100 |
| 659E10000 SEEDING AND MULCHING | 3,333 SY | $0.75 | $1.00 | $1.89 | $1.50 | $1.25 | $2.00 | $0.70 |
| 659E14000 REPAIR SEEDING AND MULCHING | 167 SY | $2.23 | $0.75 | $1.00 | $1.50 | $2.00 | $1.00 | $2.00 |
| 659E15000 INTER-SEEDING | 167 SY | $1.00 | $0.75 | $1.00 | $1.00 | $1.00 | $0.10 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.46 TON | $1,112 | $725 | $1,419 | $308 | $250 | $500 | $1,000 |
| 659E31000 LIME | 0.69 ACRE | $10.00 | $170 | $303 | $30.51 | $25.00 | $200 | $200 |
| 659E35000 WATER | 18 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 659E40000 MOWING | 7 MSF | $25.00 | $108 | $11.43 | $30.50 | $1.00 | $1.00 | $1.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $917 | $1,080 | $1,964 | $867 | $1,500 | $1,600 | $1,800 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $5,222 | $2,700 | $6,158 | $6,103 | $2,000 | $3,400 | $3,600 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $7,375 | $9,720 | $11,084 | $7,947 | $7,600 | $8,000 | $8,000 |
| 602E20000 CONCRETE MASONRY | 5.9 CY | $908 | $1,190 | $1,774 | $1,894 | $2,000 | $1,000 | $1,250 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 80 FT | $12.00 | $13.00 | $49.69 | $12.00 | $15.00 | $15.00 | $16.00 |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 327 FT | $13.00 | $14.00 | $46.36 | $13.50 | $18.00 | $20.00 | $20.00 |
| 605E31100 AGGREGATE DRAINS | 100 FT | $11.40 | $14.00 | $23.98 | $16.50 | $12.00 | $16.00 | $16.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 10 FT | $10.00 | $38.00 | $34.48 | $23.00 | $7.00 | $16.00 | $26.00 |
| 611E01100 6" CONDUIT, TYPE C | 100 FT | $3.00 | $14.00 | $3.07 | $20.00 | $7.00 | $15.00 | $23.00 |
| 611E01400 6" CONDUIT, TYPE E | 100 FT | $3.00 | $14.00 | $3.07 | $14.00 | $5.00 | $16.00 | $26.00 |
| 611E10600 24" CONDUIT, TYPE C | 17 FT | $145 | $80.00 | $149 | $113 | $200 | $90.00 | $50.00 |
| 611E13600 30" CONDUIT, TYPE C | 12 FT | $165 | $113 | $230 | $92.00 | $250 | $150 | $105 |
| 611E98700 INLET, SIDE DITCH | 1 EACH | $3,190 | $1,500 | $948 | $1,277 | $2,800 | $3,500 | $3,400 |
| 611E99575 MANHOLE, NO. 3, AS PER PLAN | 1 EACH | $6,988 | $8,800 | $7,734 | $9,712 | $6,700 | $8,000 | $8,000 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $200 | $400 | $345 | $229 | $250 | $500 | $350 |
| 407E20000 NON-TRACKING TACK COAT | 112 GAL | $2.70 | $3.00 | $3.89 | $2.50 | $3.00 | $2.40 | $2.50 |
| 441E50400 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | — | $235 | $228 | $616 | $218 | $1,000 | $211 | $211 |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 150 SY | $48.50 | $46.00 | $79.62 | $80.50 | $90.00 | $60.00 | $70.00 |
| 202E75610 VALVE BOX REMOVED | 3 EACH | $50.00 | $330 | $94.42 | $475 | $50.00 | $100 | $150 |
| 638E20834 SPECIAL - INSTALL 1" POLYETHYLENE WATER SERVICE CO | 239 FT | $8.25 | $50.00 | $27.31 | $75.00 | $60.00 | $38.00 | $60.00 |
| 611E99900 DRAINAGE STRUCTURE, MISC.:CLEANOUT RELOCATED | 1 EACH | $722 | $1,770 | $1,897 | $1,162 | $2,000 | $500 | $2,000 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED, TYPE D | 1 EACH | $83.00 | $103 | $92.37 | $158 | $75.00 | $62.00 | $75.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 15 EACH | $8.34 | $8.50 | $9.23 | $8.50 | $7.50 | $10.00 | $8.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 23 FT | $11.00 | $20.00 | $12.31 | $22.50 | $10.00 | $18.50 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 43.5 FT | $12.00 | $24.00 | $12.31 | $27.50 | $10.00 | $20.00 | $10.00 |
| 630E80100 SIGN, FLAT SHEET | 25.8 SF | $19.45 | $33.00 | $21.55 | $23.50 | $18.00 | $30.00 | $18.00 |
| 630E85000 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE | 5 EACH | $39.00 | $11.00 | $43.10 | $40.00 | $35.00 | $60.00 | $35.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $56.00 | $71.00 | $61.58 | $89.50 | $50.00 | $75.00 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $16.70 | $22.00 | $18.47 | $47.50 | $15.00 | $20.00 | $15.00 |
| 644E00100 EDGE LINE, 4" | 0.2 MILE | $6,667 | $6,500 | $7,390 | $10,637 | $6,000 | $6,000 | $6,000 |
| 644E00300 CENTER LINE | 0.01 MILE | $61,112 | $59,400 | $67,738 | $21,268 | $55,000 | $55,000 | $55,000 |
| 410E11000 TRAFFIC COMPACTED SURFACE, TYPE B | 15 CY | $50.00 | $92.00 | $294 | $89.50 | $100 | $60.00 | $425 |
| 614E12420 DETOUR SIGNING | 1 LS | $8,889 | $8,700 | $9,853 | $7,960 | $7,500 | $15,000 | $9,000 |
| 616E10000 WATER | 1 MGAL | $1.00 | $20.00 | $1.00 | $64.50 | $10.00 | $50.00 | $100 |
| 202E11000 STRUCTURE REMOVED | 1 LS | $8,752 | $22,000 | $14,472 | $5,583 | $20,000 | $27,117 | $16,800 |
| 203E10001 EXCAVATION, AS PER PLAN | 182 CY | $27.25 | $21.00 | $10.55 | $22.00 | $40.00 | $20.00 | $54.00 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 4,323 LB | $1.35 | $1.75 | $1.51 | $1.50 | $2.20 | $1.00 | $3.00 |
| 512E10000 SEALING OF CONCRETE SURFACES | 78 SY | $26.25 | $28.00 | $12.15 | $25.00 | $50.00 | $20.00 | $28.00 |
| 512E33001 TYPE 2 WATERPROOFING, AS PER PLAN | 130 SY | $17.35 | $17.00 | $24.25 | $21.00 | $25.00 | $22.00 | $24.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 56 SF | $1.67 | $6.00 | $13.74 | $7.00 | $12.00 | $3.00 | $10.00 |
| 518E21230 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 1 LS | $5,000 | $3,350 | $2,205 | $2,263 | $15,000 | $4,000 | $2,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,445 | $8,000 | $9,853 | $14,500 | $6,000 | $19,000 | $8,100 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,850 | $14,000 | $1,232 | $48,000 | $40,000 | $29,000 | $8,000 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $800 | $1,300 | $205 | $500 | $1,500 | $500 | $500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E22901 54" CONDUIT, TYPE D, AS PER PLAN | 307 FT | $378 | $116k | 17% |
| 611E95001 10' X 5' CONDUIT, TYPE A, 706.05, AS PER PLAN | 43 FT | $1,729 | $74k | 11% |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 82 CY | $408.25 | $33k | 5% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $31,800 | $32k | 5% |
| 203E10000 EXCAVATION | 1,554 CY | $20 | $31k | 5% |
| 203E20000 EMBANKMENT | 1,719 CY | $17.6 | $30k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $24,500 | $25k | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 158 CY | $153 | $24k | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 887.5 FT | $19.67 | $17k | 3% |
| 659E00300 TOPSOIL | 370 CY | $44.5 | $16k | 2% |