MAH-/POR-US 62/VAR-19.04/VAR
MAH County · est $1.6M
Bid dateThursday, June 17—
MAH County · est $1.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 72 more items below.
| Item | Quantity | R1Marucci & Gaffney Excavating CO | R2Karvo Companies INC | R3Shelly & Sands INC | R4Perk Company INC | % of bid |
|---|---|---|---|---|---|---|
| 255E10010 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 2,500 SY | $135 | $150 | $198 | $260 | 38% |
| 258E10000 RETROFIT DOWEL BAR | 1,000 EACH | $157 | $75.00 | $65.00 | $185 | 18% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,000 | $90,000 | $80,000 | $71,150 | 11% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 2,454 SF | $18.50 | $19.50 | $19.00 | $18.00 | 5% |
| Item | Quantity | R1Marucci & Gaffney Excavating CO | R2Karvo Companies INC | R3Shelly & Sands INC | R4Perk Company INC |
|---|---|---|---|---|---|
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 420 CY | $10.00 | $35.00 | $75.00 | $1.00 |
| 616E10001 WATER, AS PER PLAN | 50 MGAL | $1.00 | $4.00 | $265 | $145 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E05200 4" UNCLASSIFIED PIPE UNDERDRAINS | 250 FT | $8.00 | $35.00 | $3.80 | $5.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 255E20000 FULL DEPTH PAVEMENT SAWING | 11,250 FT | $3.00 | $2.80 | $3.60 | $3.50 | 4% |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 420 CY | $75.00 | $75.00 | $42.00 | $20.00 | 4% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 150 SF | $150 | $135 | $135 | $125 | 3% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 41 EACH | $525 | $565 | $555 | $575 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $72,000 | $60,000 | $64,000 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 200 HOUR | $85.00 | $75.00 | $65.00 | $75.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $10,000 | $6,000 | $12,500 | 2% |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 1,702 SY | $8.50 | $11.00 | $11.65 | $16.50 | 2% |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 1,633 SY | $8.50 | $11.00 | $11.65 | $16.50 | 2% |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 12 SNMT | $900 | $900 | $1,000 | $1,100 | 1% |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 1,250 SY | $8.50 | $11.00 | $11.65 | $16.50 | 1% |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 1,243 SY | $8.50 | $11.00 | $11.65 | $16.50 | 1% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 250 FT | $35.00 | $37.00 | $3.80 | $6.00 | 1% |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 922 SY | $8.50 | $11.00 | $11.65 | $16.50 | 1% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $7,500 | $3,000 | $3,200 | $5,100 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $1,200 | $2,000 | $2,500 | $1,750 | 1% |
| 150 FT |
| $8.00 |
| $50.00 |
| $3.80 |
| $5.00 |
| 605E13301 6" UNCLASSIFIED PIPE UNDERDRAINS, AS PER PLAN | 150 FT | $35.00 | $52.00 | $3.80 | $6.00 |
| 605E98300 UNDERDRAINS, MISC.: UNDERDRAIN CLEANOUT | 24 EACH | $200 | $575 | $23.00 | $50.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 50 FT | $25.00 | $50.00 | $4.85 | $6.00 |
| 621E00100 RPM | 10 EACH | $450 | $785 | $325 | $785 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 10 EACH | $100 | $12.00 | $8.75 | $100 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 80 FT | $29.50 | $33.50 | $31.00 | $24.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 4 EACH | $395 | $375 | $410 | $450 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 30 SF | $22.50 | $22.20 | $23.00 | $16.00 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 4 EACH | $945 | $1,120 | $1,000 | $850 |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 1 EACH | $125 | $110 | $130 | $400 |
| 630E85600 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND REERECTIO | 2 EACH | $230 | $320 | $240 | $600 |
| 630E86205 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 6 EACH | $285 | $315 | $300 | $150 |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 11 EACH | $245 | $275 | $255 | $350 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 1 MILE | $2,000 | $2,000 | $2,100 | $8,500 |
| 642E00204 LANE LINE, 6", TYPE 1 | 1 MILE | $2,000 | $2,000 | $2,100 | $3,500 |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 100 FT | $2.00 | $2.00 | $2.00 | $3.00 |
| 614E12460 WORK ZONE MARKING SIGN (ALL PHASES) | 20 EACH | $85.00 | $100 | $90.00 | $100 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $50.00 | $100 | $360 | $250 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $5,000 | $3,000 | $3,200 | $5,100 |
| 203E40000 BORROW | 5 CY | $35.00 | $100 | $105 | $150 |
| 601E26000 DUMPED ROCK FILL, TYPE B | 5 CY | $100 | $175 | $185 | $500 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $11.00 | $10.00 | $11.50 | $9.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 46 FT | $12.00 | $12.00 | $12.70 | $11.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $22.50 | $15.00 | $24.00 | $25.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 12 SF | $20.00 | $15.00 | $21.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 6 EACH | $10.00 | $25.00 | $10.50 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $15.00 | $25.00 | $15.00 | $30.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $5,000 | $3,000 | $3,200 | $5,100 |
| 203E40000 BORROW | 20 CY | $35.00 | $100 | $105 | $150 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 17 SY | $65.00 | $60.00 | $63.00 | $110 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 17 SY | $60.00 | $50.00 | $52.00 | $60.00 |
| 601E26000 DUMPED ROCK FILL, TYPE B | 20 CY | $90.00 | $175 | $185 | $250 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $11.00 | $10.00 | $11.65 | $9.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $22.50 | $12.00 | $24.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $10.00 | $25.00 | $10.00 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $15.00 | $25.00 | $15.00 | $30.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $5,000 | $3,000 | $3,200 | $5,100 |
| 203E40000 BORROW | 10 CY | $50.00 | $100 | $105 | $150 |
| 601E27000 DUMPED ROCK FILL, TYPE C | 10 CY | $90.00 | $175 | $185 | $500 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $11.00 | $10.00 | $11.65 | $9.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 46 FT | $12.00 | $12.00 | $12.75 | $11.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $22.50 | $15.00 | $24.00 | $25.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 12 SF | $20.00 | $15.00 | $21.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 6 EACH | $10.00 | $25.00 | $10.00 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $15.00 | $25.00 | $15.00 | $30.00 |
| 518E12500 SCUPPER, MISC.: CLEANOUT | 3 EACH | $500 | $250 | $265 | $1,500 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $11.00 | $10.00 | $11.65 | $9.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $22.50 | $15.00 | $23.00 | $25.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $5,000 | $3,000 | $3,200 | $5,100 |
| 202E38000 GUARDRAIL REMOVED | 50 FT | $2.40 | $2.80 | $2.50 | $2.80 |
| 203E40000 BORROW | 2.5 CY | $168 | $100 | $105 | $150 |
| 606E13000 GUARDRAIL, TYPE 5 | 50 FT | $72.50 | $79.00 | $75.00 | $79.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $11.00 | $10.00 | $11.65 | $9.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 46 FT | $12.00 | $12.00 | $12.00 | $11.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $22.50 | $15.00 | $23.00 | $25.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 12 SF | $20.00 | $15.00 | $21.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4 EACH | $10.00 | $25.00 | $10.00 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $15.00 | $25.00 | $15.00 | $30.00 |
| 659E10000 SEEDING AND MULCHING | 20 SY | $20.00 | $49.50 | $37.00 | $49.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.01 TON | $400 | $1,200 | $1,000 | $1,200 |
| 659E31000 LIME | 0.01 ACRE | $50.00 | $250 | $1,000 | $250 |
| 659E35000 WATER | 0.1 MGAL | $1.00 | $5.00 | $1,000 | $5.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $6,000 | $6,000 | $3,200 | $5,100 |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 766 SY | $8.50 | $11.00 | $11.65 | $16.50 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $11.00 | $10.00 | $11.65 | $20.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $22.50 | $15.00 | $23.00 | $25.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,000 | $2,500 | $5,000 | $7,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 255E10010 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 2,500 SY | $135 | $338k | 34% |
| 258E10000 RETROFIT DOWEL BAR | 1,000 EACH | $157 | $157k | 16% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,000 | $100k | 10% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 2,454 SF | $18.5 | $45k | 5% |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 11,250 FT | $3 | $34k | 3% |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 420 CY | $75 | $32k | 3% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 150 SF | $150 | $23k | 2% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 41 EACH | $525 | $22k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 200 HOUR | $85 | $17k | 2% |