COL-ODNR Highlandtown Culvert
COL County · est $0.2M
Bid dateThursday, July 15—
COL County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 5 more items below.
| Item | Quantity | R1Stanley Miller Construction Company | R2Rudzik Excavating INC | R3S E T INC | R4Turn-key Tunneling INC | % of bid |
|---|---|---|---|---|---|---|
| 203E20000 EMBANKMENT | 2,248 CY | $24.00 | $29.00 | $20.00 | $42.00 | 29% |
| 611E96600 CONDUIT, BORED OR JACKED: 36" TYPE A, 748.06 | 107 FT | $427 | $620 | $896 | $505 | 24% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $17,167 | $12,930 | $17,000 | $7,875 | 9% |
| 203E10000 EXCAVATION | 1,097 CY | $10.00 | $20.00 | $26.00 | $15.75 | 6% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,889 | $2,000 | $10,000 | $6,300 | 5% |
| 659E10000 SEEDING AND MULCHING | 1,533 SY | $5.75 | $3.00 | $3.25 | $5.25 |
| Item | Quantity | R1Stanley Miller Construction Company | R2Rudzik Excavating INC | R3S E T INC | R4Turn-key Tunneling INC |
|---|---|---|---|---|---|
| 659E14000 REPAIR SEEDING AND MULCHING | 77 SY | $1.00 | $1.00 | $1.10 | $0.21 |
| 659E20000 COMMERCIAL FERTILIZER | 0.21 TON | $600 | $25.00 | $660 | $1,260 |
| 659E31000 LIME | 0.32 ACRE | $250 | $20.00 | $27.50 | $840 |
| 659E35000 WATER | 10 MGAL | $1.00 | $0.01 | $1.10 | $0.26 |
| 616E10000 WATER | 35 MGAL |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 5% |
| 606E16001 GUARDRAIL REBUILT, AS PER PLAN | 300 FT | $23.00 | $15.00 | $18.04 | $21.00 | 4% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 659E00300 TOPSOIL | 170 CY | $28.00 | $21.00 | $67.25 | $47.25 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $4,390 | $9,450 | $22,800 | $45,000 | 2% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 12" | 76 FT | $55.00 | $50.00 | $10.16 | $80.00 | 2% |
| 304E20000 AGGREGATE BASE | 30 CY | $132 | $98.00 | $64.10 | $158 | 2% |
| 601E11000 RIPRAP, TYPE D | 4 SY | $756 | $460 | $153 | $289 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,667 | $2,600 | $3,600 | $6,400 | 1% |
| 602E20000 CONCRETE MASONRY | 1.5 CY | $1,610 | $2,920 | $3,083 | $2,100 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 54 GAL | $32.00 | $30.00 | $50.00 | $36.75 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,667 | $2,250 | $4,000 | $15,750 | 1% |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 6 CY | $236 | $260 | $94.10 | $289 | 1% |
| 202E38201 GUARDRAIL REMOVED FOR REUSE, AS PER PLAN | 300 FT | $2.00 | $5.00 | $1.98 | $5.25 | 0% |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $100 | $50.00 | $300 | $52.50 | 0% |
| $1.00 |
| $0.01 |
| $51.25 |
| $0.26 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E20000 EMBANKMENT | 2,248 CY | $24 | $54k | 29% |
| 611E96600 CONDUIT, BORED OR JACKED: 36" TYPE A, 748.06 | 107 FT | $427 | $46k | 24% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $17,167 | $17k | 9% |
| 203E10000 EXCAVATION | 1,097 CY | $10 | $11k | 6% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,889 | $9k | 5% |
| 659E10000 SEEDING AND MULCHING | 1,533 SY | $5.75 | $9k | 5% |
| 606E16001 GUARDRAIL REBUILT, AS PER PLAN | 300 FT | $23 | $7k | 4% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1 | $5k | 3% |
| 659E00300 TOPSOIL | 170 CY | $28 | $5k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $4,390 | $4k | 2% |