CUY-IR 90-07.58/13.72 Paint
CUY County · est $10M
Bid dateThursday, October 28—
CUY County · est $10M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 3.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 28 more items below.
| Item | Quantity | R1Industrial Painting & Rigging INC | R2Corrosion Resistance LTD | R3Vimas Painting Company INC | R4360 Construction Company INC | R5Corcon INC | R6Panther Industrial Painting LLC | R7Elite Contractors INC | R8Liberty Maintenance INC | R9Titan Industrial Services INC | R10Euro Paint LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 342,700 SF | $6.00 | $6.70 | $9.00 | $9.00 | $3.90 | $11.00 | $7.00 | $8.81 | $10.15 | $8.30 | 36% |
| Item | Quantity | R1Industrial Painting & Rigging INC | R2Corrosion Resistance LTD | R3Vimas Painting Company INC | R4360 Construction Company INC | R5Corcon INC | R6Panther Industrial Painting LLC | R7Elite Contractors INC | R8Liberty Maintenance INC | R9Titan Industrial Services INC | R10Euro Paint LLC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $1,000 | $8,700 | $4,000 | $10,000 | $20,000 | $1,000 | $10,000 | $2,500 | $5,000 | $5,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 210,500 SF | $6.00 | $8.00 | $9.00 | $8.00 | $5.00 | $11.00 | $7.00 | $8.81 | $10.10 | $8.19 | 22% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 342,700 SF | $1.00 | $1.50 | $1.00 | $2.00 | $2.90 | $1.00 | $2.25 | $1.95 | $1.50 | $2.50 | 6% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 342,700 SF | $1.00 | $1.40 | $1.00 | $1.00 | $1.50 | $1.00 | $2.25 | $1.95 | $1.50 | $2.50 | 6% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 342,700 SF | $1.00 | $1.65 | $1.00 | $1.00 | $1.50 | $1.00 | $2.25 | $1.95 | $1.50 | $2.50 | 6% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 211,000 SF | $1.00 | $1.85 | $1.00 | $1.00 | $1.90 | $1.00 | $2.25 | $1.95 | $1.50 | $2.50 | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 211,000 SF | $1.00 | $2.10 | $1.00 | $1.00 | $1.90 | $1.00 | $2.25 | $1.95 | $1.50 | $2.50 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 210,500 SF | $1.00 | $2.00 | $1.00 | $2.00 | $3.70 | $1.00 | $2.25 | $1.95 | $1.50 | $2.50 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $150,000 | $168,000 | $650,000 | $60,000 | $800,000 | $200,000 | $500,000 | $200,000 | $250,000 | $114,500 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $116,000 | $40,000 | $140,000 | $75,000 | $80,000 | $150,000 | $200,000 | $74,000 | $90,000 | $140,000 | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 3,540 FT | $20.00 | $5.00 | $0.10 | $26.50 | $26.50 | $20.00 | $26.50 | $29.73 | $28.00 | $26.50 | 1% |
| 614E23410 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 740.06, | 20,607 FT | $3.25 | $3.25 | $0.10 | $3.25 | $3.25 | $1.00 | $3.25 | $3.65 | $3.25 | $3.25 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $60,000 | $145,000 | $200,000 | $70,000 | $600,000 | $250,000 | $200,000 | $60,823 | $100,000 | $54,315 | 1% |
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 105 CY | $500 | $555 | $1.00 | $965 | $1,150 | $300 | $2.25 | $1,083 | $965 | $965 | 1% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, DEPTH = 1 1/2" | 2,540 SY | $15.00 | $18.00 | $0.10 | $28.00 | $2.60 | $10.00 | $3.50 | $31.42 | $28.00 | $28.00 | 1% |
| 513E21501 REPLACEMENT OF DETERIORATED END CROSSFRAMES, AS PE | 3,000 LB | $12.00 | $10.90 | $15.00 | $12.00 | $12.00 | $10.00 | $9.00 | $10.10 | $17.25 | $9.00 | 1% |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 6,640 FT | $4.00 | $1.46 | $0.10 | $3.50 | $1.75 | $3.50 | $3.00 | $5.00 | $1.73 | $3.52 | 0% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 24 SNMT | $1,050 | $695 | $1.00 | $1,050 | $1,050 | $500 | $1,050 | $1,178 | $1,050 | $1,050 | 0% |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 2.6 MILE | $8,700 | $8,700 | $1.00 | $8,700 | $8,700 | $7,000 | $8,700 | $9,761 | $8,700 | $8,700 | 0% |
| 644E00104 EDGE LINE, 6" | 2.6 MILE | $8,625 | $8,625 | $1.00 | $8,625 | $8,625 | $3,000 | $8,625 | $9,677 | $8,625 | $8,625 | 0% |
| 607E98000 FENCE, MISC.: CONSTRUCTION FENCE | 3,000 FT | $5.00 | $2.35 | $1.00 | $7.80 | $7.80 | $1.00 | $10.00 | $10.00 | $2.00 | $7.80 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 407E10000 TACK COAT | 215 GAL | $5.00 | $2.25 | $1.00 | $4.00 | $3.00 | $10.00 | $5.00 | $4.49 | $4.00 | $4.00 |
| 642E00300 CENTER LINE, TYPE 1 | 0.11 MILE | $20,065 | $20,065 | $1.00 | $20,065 | $20,065 | $5,000 | $20,065 | $22,513 | $20,065 | $20,065 |
| 644E00204 LANE LINE, 6" | 3.9 MILE | $3,740 | $3,740 | $1.00 | $3,740 | $3,740 | $1,000 | $3,740 | $4,196 | $3,740 | $3,740 |
| 644E01510 DOTTED LINE, 6" | 990 FT | $2.00 | $2.00 | $1.00 | $2.00 | $2.00 | $1.00 | $2.00 | $2.24 | $2.00 | $2.00 |
| 646E10010 EDGE LINE, 6" | 1.02 MILE | $16,830 | $16,830 | $1.00 | $16,830 | $16,830 | $3,000 | $16,830 | $18,883 | $16,830 | $16,830 |
| 646E10110 LANE LINE, 6" | 1.53 MILE | $9,505 | $9,505 | $1.00 | $9,505 | $9,505 | $3,000 | $9,505 | $10,667 | $9,505 | $9,505 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $75.00 | $75.00 | $60.00 | $65.00 | $135 | $60.00 | $100 | $90.00 | $69.00 | $85.00 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $8,400 | $43,200 | $20,000 | $8,400 | $8,400 | $25,000 | $8,400 | $9,425 | $8,400 | $8,400 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,100 | $1,925 | $1.00 | $2,100 | $2,100 | $3,000 | $2,100 | $2,356 | $2,100 | $2,100 |
| 614E12800 WORK ZONE RAISED PAVEMENT MARKER | 1,681 EACH | $10.00 | $6.15 | $0.10 | $6.00 | $6.00 | $6.00 | $6.00 | $6.73 | $6.00 | $6.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE-WAY | 75 EACH | $15.00 | $4.80 | $1.00 | $15.00 | $15.00 | $10.00 | $15.00 | $16.83 | $15.00 | $15.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 75 EACH | $16.00 | $15.05 | $1.00 | $16.00 | $16.00 | $10.00 | $16.00 | $17.95 | $16.00 | $16.00 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 1.16 MILE | $7,550 | $7,550 | $1.00 | $7,550 | $7,550 | $2,500 | $7,550 | $8,471 | $7,550 | $7,550 |
| 614E23210 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 642 PAI | 8,028 FT | $0.75 | $0.75 | $0.10 | $0.75 | $0.75 | $1.00 | $0.75 | $0.84 | $0.75 | $0.75 |
| 614E24202 WORK ZONE DOTTED LINE, CLASS I, 6", 642 PAINT | 990 FT | $0.70 | $0.70 | $0.10 | $0.70 | $0.70 | $1.00 | $0.70 | $0.79 | $0.70 | $0.70 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 44 FT | $3.00 | $3.00 | $1.00 | $3.00 | $3.00 | $10.00 | $3.00 | $3.37 | $3.00 | $3.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 250 MNHR | $85.00 | $70.00 | $150 | $60.00 | $200 | $200 | $150 | $96.33 | $100 | $100 |
| 514E10000 FINAL INSPECTION REPAIR | 130 EACH | $110 | $200 | $100 | $100 | $500 | $100 | $250 | $120 | $100 | $50.00 |
| 513E95020 STRUCTURAL STEEL, MISC.: RE-WELD END CROSSFRAME ME | 1 LS | $9,000 | $5,500 | $30,000 | $26,000 | $26,000 | $20,000 | $6,000 | $21,430 | $17,250 | $19,100 |
| 513E95030 STRUCTURAL STEEL, MISC.: REPAIR OF DAMAGED MEMBERS | 2 EACH | $900 | $1,000 | $500 | $2,000 | $200 | $2,500 | $1,200 | $2,132 | $575 | $1,900 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 170 MNHR | $85.00 | $70.00 | $150 | $60.00 | $200 | $200 | $150 | $96.33 | $100 | $100 |
| 514E10000 FINAL INSPECTION REPAIR | 100 EACH | $110 | $210 | $100 | $100 | $500 | $100 | $250 | $120 | $100 | $50.00 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $10,000 | $13,000 | $20,000 | $5,000 | $15,000 | $10,000 | $50,000 | $6,172 | $10,000 | $10,000 |
| 619E16020 FIELD OFFICE, TYPE C | 6 MNTH | $300 | $2,000 | $5,000 | $3,000 | $5,000 | $500 | $2,000 | $3,000 | $4,000 | $1,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $5,120 | $5,120 | $5,000 | $5,200 | $40,000 | $5,000 | $5,000 | $5,745 | $1,100 | $5,120 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 342,700 SF | $6 | $2.06M | 35% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 210,500 SF | $6 | $1.26M | 21% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 342,700 SF | $1 | $343k | 6% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 342,700 SF | $1 | $343k | 6% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 342,700 SF | $1 | $343k | 6% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 211,000 SF | $1 | $211k | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 211,000 SF | $1 | $211k | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 210,500 SF | $1 | $211k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $150,000 | $150k | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $116,000 | $116k | 2% |