D03-BP FY2022
D03 County · est $1.4M
Bid dateThursday, November 18—
D03 County · est $1.4M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 11,917 SF |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 73 more items below.
| Item | Quantity | R1Legend Painting INC | R2Euro Paint LLC | R3Panther Industrial Painting LLC | R4Kmx Painting INC | R5Elite Contractors INC | R6360 Construction Company INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 11,917 SF | $8.00 | $15.85 | $20.00 | $15.00 | $12.00 | $10.00 | 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 11,917 SF | $8.00 | $15.85 | $20.00 | $15.00 | $12.00 | $10.00 | 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 7,000 SF | $8.00 | $21.56 | $20.00 |
| Item | Quantity | R1Legend Painting INC | R2Euro Paint LLC | R3Panther Industrial Painting LLC | R4Kmx Painting INC | R5Elite Contractors INC | R6360 Construction Company INC |
|---|---|---|---|---|---|---|---|
| 832E30000 EROSION CONTROL | 9,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 90 HOUR | $60.00 | $80.00 | $40.00 | $60.00 | $40.00 | $60.00 |
| 614E12484 WORK ZONE INCREASED PENALTIES SIGN | 16 EACH | $185 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $35.00 |
| $20.00 |
| $13.00 |
| 6% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,598 SF | $10.00 | $23.36 | $28.00 | $27.00 | $20.00 | $15.00 | 6% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 6,723 SF | $8.00 | $21.52 | $20.00 | $35.00 | $20.00 | $13.00 | 6% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,309 SF | $10.00 | $23.29 | $28.00 | $27.00 | $20.00 | $15.00 | 6% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 2,731 SF | $18.00 | $35.62 | $38.00 | $40.00 | $35.00 | $30.00 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $49,000 | $47,500 | $30,000 | $160,000 | $250,000 | $90,000 | 5% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $7,000 | $1,000 | $500 | $1,000 | $500 | $2,500 | 5% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 11,917 SF | $3.50 | $2.50 | $1.00 | $2.00 | $1.75 | $5.00 | 5% |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 11,917 SF | $3.50 | $2.50 | $1.00 | $2.00 | $1.75 | $5.00 | 5% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 11,917 SF | $3.50 | $2.50 | $1.00 | $2.00 | $1.75 | $5.00 | 5% |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 11,917 SF | $3.50 | $2.50 | $1.00 | $2.00 | $1.75 | $5.00 | 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 11,917 SF | $3.00 | $2.50 | $1.00 | $2.00 | $1.75 | $5.00 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 11,917 SF | $3.00 | $2.50 | $1.00 | $2.00 | $1.75 | $5.00 | 4% |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (G | 851 LB | $32.00 | $32.00 | $35.20 | $35.00 | $32.00 | $15.25 | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 5,598 SF | $4.50 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 | 3% |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 5,598 SF | $4.50 | $2.50 | $1.00 | $2.00 | $4.00 | $5.00 | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 7,000 SF | $3.50 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 | 3% |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 7,000 SF | $3.50 | $2.50 | $1.00 | $2.00 | $4.00 | $5.00 | 3% |
| $185 |
| $10.00 |
| $100 |
| $200 |
| $185 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $1,050 | $1,050 | $1.00 | $1,000 | $1,100 | $1,050 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 7,000 SF | $3.00 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 10 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 6 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 6,723 SF | $3.00 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 6,723 SF | $3.50 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 6,723 SF | $3.50 | $2.50 | $1.00 | $2.00 | $4.00 | $5.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 10 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 6 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 18 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 10 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 18 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 10 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 5,309 SF | $3.00 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 5,309 SF | $4.50 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 5,309 SF | $4.50 | $2.50 | $1.00 | $2.00 | $4.00 | $5.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 9 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 5 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 5,598 SF | $3.00 | $2.50 | $1.00 | $2.00 | $4.00 | $10.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 9 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 5 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (BEARIN | 1 LS | $300 | $300 | $330 | $300 | $300 | $1,450 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (BEARIN | 1 LS | $250 | $250 | $275 | $300 | $1,000 | $1,450 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (EXISTI | 1 LS | $1,650 | $1,650 | $1,815 | $1,700 | $1,650 | $1,800 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (SCUPPE | 1 LS | $400 | $400 | $440 | $400 | $400 | $540 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 84 SY | $35.00 | $60.00 | $50.00 | $40.00 | $60.00 | $40.00 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (B | 132 LB | $22.00 | $22.00 | $24.20 | $25.00 | $22.00 | $21.00 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (G | 305 LB | $22.00 | $22.00 | $24.20 | $25.00 | $22.00 | $17.75 |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 2,421 SF | $10.00 | $35.39 | $45.00 | $50.00 | $35.00 | $23.00 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 2,421 SF | $3.00 | $2.50 | $3.00 | $2.00 | $10.00 | $15.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 2,421 SF | $4.50 | $2.50 | $3.00 | $2.00 | $10.00 | $10.00 |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 2,421 SF | $4.50 | $2.50 | $3.00 | $2.00 | $10.00 | $10.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 4 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 3 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 516E31000 JOINT SEALER | 66 FT | $25.00 | $25.00 | $27.50 | $30.00 | $25.00 | $26.00 |
| 516E46201 BEARING DEVICE, ROCKER, AS PER PLAN (R100) | 2 EACH | $2,900 | $2,900 | $3,190 | $3,000 | $3,500 | $4,200 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $7,500 | $8,250 | $8,000 | $3,000 | $3,600 |
| 518E43300 6" PIPE DOWNSPOUT, INCLUDING SPECIALS | 10 FT | $400 | $400 | $440 | $450 | $400 | $308 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (BEARIN | 1 LS | $250 | $250 | $275 | $500 | $250 | $725 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (BEARIN | 1 LS | $250 | $250 | $275 | $500 | $250 | $2,900 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (CONCRE | 1 LS | $2,500 | $2,500 | $2,750 | $3,000 | $2,500 | $2,400 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (END CR | 1 LS | $1,500 | $1,500 | $1,650 | $2,000 | $1,500 | $1,450 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (EXISTI | 1 LS | $1,500 | $1,500 | $1,650 | $2,000 | $1,500 | $1,800 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (GIRDER | 1 LS | $2,000 | $2,000 | $2,200 | $2,000 | $2,000 | $725 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (INTERM | 1 LS | $250 | $250 | $275 | $500 | $250 | $725 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (SCUPPE | 1 LS | $400 | $400 | $440 | $500 | $400 | $545 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 84 SY | $35.00 | $60.00 | $50.00 | $50.00 | $60.00 | $40.00 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (B | 459 LB | $22.00 | $22.00 | $24.20 | $24.00 | $22.00 | $27.05 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (E | 227 LB | $10.00 | $10.00 | $11.00 | $15.00 | $10.00 | $12.30 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (G | 321 LB | $32.00 | $32.00 | $35.20 | $35.00 | $32.00 | $17.30 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN (I | 40 LB | $46.00 | $46.00 | $50.60 | $50.00 | $46.00 | $24.05 |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 2,421 SF | $10.00 | $35.39 | $45.00 | $50.00 | $35.00 | $23.00 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 2,421 SF | $3.00 | $2.50 | $3.00 | $2.00 | $10.00 | $15.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 2,421 SF | $4.50 | $2.50 | $3.00 | $2.00 | $10.00 | $10.00 |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 2,421 SF | $4.50 | $2.50 | $3.00 | $2.00 | $10.00 | $10.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 4 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 3 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 516E31000 JOINT SEALER | 66 FT | $25.00 | $25.00 | $27.50 | $30.00 | $25.00 | $26.00 |
| 516E46201 BEARING DEVICE, ROCKER, AS PER PLAN (R100) | 1 EACH | $2,900 | $2,900 | $3,190 | $3,000 | $2,900 | $4,200 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $12,500 | $12,500 | $13,750 | $13,000 | $12,500 | $23,550 |
| 518E43300 6" PIPE DOWNSPOUT, INCLUDING SPECIALS | 10 FT | $400 | $400 | $440 | $500 | $400 | $3,080 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 2,731 SF | $6.00 | $2.50 | $2.00 | $2.00 | $10.00 | $15.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 2,731 SF | $4.50 | $2.50 | $2.00 | $2.00 | $10.00 | $10.00 |
| 514E00067 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT, AS P | 2,731 SF | $4.50 | $2.50 | $2.00 | $2.00 | $10.00 | $10.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 5 MNHR | $60.00 | $100 | $200 | $150 | $100 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 3 EACH | $300 | $100 | $200 | $150 | $200 | $150 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $20,500 | $5,000 | $10,000 | $10,000 | $20,000 | $5,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $21,500 | $27,000 | $25,000 | $25,000 | $80,000 | $30,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,695 | $20,000 | $75,000 | $80,000 | $150,000 | $100,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $400 | $9,000 | $100 | $5,000 | $1,000 | $2,000 |
| $8 |
| $95k |
| 7% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 11,917 SF | $8 | $95k | 7% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 7,000 SF | $8 | $56k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,598 SF | $10 | $56k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 6,723 SF | $8 | $54k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,309 SF | $10 | $53k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 2,731 SF | $18 | $49k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $49,000 | $49k | 3% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $7,000 | $42k | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 11,917 SF | $3.5 | $42k | 3% |