LOR-SR 57-04.96
LOR County · est $2.3M
Bid dateThursday, December 2—
LOR County · est $2.3M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 57 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly Company | R3Chagrin Valley Paving INC | R4Karvo Companies INC | % of bid |
|---|---|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 5,476 CY | $190 | $175 | $150 | $180 | 48% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442) | 905 CY | $240 | $265 | $200 | $300 | 10% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.50") | 132,413 SY | $1.15 | $1.45 | $2.25 | $1.15 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $135,483 | $175,550 | $199,975 | $125,000 |
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly Company | R3Chagrin Valley Paving INC | R4Karvo Companies INC |
|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 579 SY | $15.50 | $15.50 | $21.00 | $20.00 |
| 202E32500 CURB AND GUTTER REMOVED | 359 FT | $9.00 | $9.00 | $15.00 | $10.00 |
| 202E38000 GUARDRAIL REMOVED | 3,312.5 FT | $2.00 | $2.00 | $2.00 | $2.00 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 5 EACH | $115 | $115 | $115 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 6% |
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 1,000 SY | $100 | $100 | $130 | $130 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $150,000 | $124,726 | 5% |
| 606E15050 GUARDRAIL, TYPE MGS | 3,325 FT | $23.20 | $23.20 | $23.20 | $23.60 | 4% |
| 452E14050 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 579 SY | $76.25 | $76.25 | $97.00 | $120 | 2% |
| 253E02000 PAVEMENT REPAIR | 90 CY | $480 | $350 | $350 | $350 | 2% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 69 CY | $450 | $255 | $500 | $300 | 1% |
| 617E10100 COMPACTED AGGREGATE | 613 CY | $50.00 | $75.00 | $60.00 | $58.00 | 1% |
| 519E12300 PATCHING CONCRETE BRIDGE DECK - TYPE B | 50 SY | $513 | $513 | $612 | $612 | 1% |
| 407E10000 TACK COAT | 10,732 GAL | $2.30 | $2.50 | $2.00 | $2.25 | 1% |
| 209E60500 LINEAR GRADING | 10.92 MILE | $2,250 | $1,485 | $750 | $1,850 | 1% |
| 611E99154 INLET RECONSTRUCTED TO GRADE | 15 EACH | $1,600 | $1,200 | $2,500 | $2,000 | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 8 EACH | $2,970 | $2,970 | $2,970 | $2,950 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 5,514 GAL | $3.75 | $3.50 | $2.00 | $4.00 | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 19 EACH | $1,050 | $950 | $950 | $1,050 | 1% |
| 621E00100 RPM | 664 EACH | $26.75 | $26.75 | $26.75 | $27.50 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 200 HOUR | $70.00 | $65.00 | $75.00 | $75.00 | 1% |
| $120 |
| 202E42206 ANCHOR ASSEMBLY REMOVED | 8 EACH | $135 | $135 | $135 | $145 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 14 EACH | $55.00 | $55.00 | $55.00 | $65.00 |
| 203E20000 EMBANKMENT | 276 CY | $50.00 | $68.50 | $28.79 | $69.50 |
| 204E10000 SUBGRADE COMPACTION | 877 SY | $1.00 | $1.00 | $1.25 | $1.50 |
| 204E13000 EXCAVATION OF SUBGRADE, 6" | 146 CY | $31.00 | $31.00 | $90.00 | $50.00 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 42 STA | $35.00 | $35.00 | $35.00 | $37.00 |
| 209E80000 GRADING MAILBOX APPROACHES | 35 EACH | $140 | $200 | $25.00 | $115 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 4 EACH | $1,340 | $1,340 | $1,340 | $1,345 |
| 606E34600 MGS BRIDGE TERMINAL ASSEMBLY, TYPE TST-2 | 8 EACH | $950 | $950 | $950 | $1,000 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 5 EACH | $2,575 | $2,575 | $2,575 | $2,640 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $525 | $525 | $525 | $500 |
| 623E39500 MONUMENT BOX ADJUSTED TO GRADE | 15 EACH | $550 | $650 | $450 | $150 |
| 654E11000 COMMERCIAL FERTILIZER | 1 TON | $100 | $1,000 | $500 | $750 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 3 EACH | $145 | $145 | $145 | $150 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 1 EACH | $265 | $265 | $265 | $250 |
| 832E30000 EROSION CONTROL | 2,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 2 EACH | $1,300 | $1,700 | $2,500 | $1,250 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 7 EACH | $750 | $875 | $950 | $1,100 |
| 254E01600 PATCHING PLANED SURFACE | 1,328 SY | $7.25 | $1.00 | $15.00 | $1.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 500 FT | $3.00 | $3.00 | $5.25 | $5.00 |
| 304E20000 AGGREGATE BASE, 6" | 146 CY | $85.00 | $85.00 | $55.00 | $95.00 |
| 407E13900 TACK COAT, 702.13 | 80 GAL | $2.45 | $15.00 | $2.00 | $2.25 |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 359 FT | $36.00 | $36.00 | $30.00 | $40.00 |
| 617E20000 SHOULDER PREPARATION | 13,780 SY | $0.40 | $0.40 | $0.25 | $0.55 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 1.35 MILE | $2,200 | $2,885 | $2,200 | $2,200 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 1.43 MILE | $2,200 | $2,885 | $2,200 | $2,200 |
| 690E98200 SPECIAL - MALTENE BASED LONGITUDINAL JOINT STABILI | 14,254 SF | $0.80 | $0.80 | $0.80 | $0.80 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 664 EACH | $2.00 | $5.00 | $1.00 | $1.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, 1 WAY | 40 EACH | $8.00 | $8.00 | $8.00 | $8.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 5 EACH | $8.80 | $8.80 | $8.80 | $9.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 11.21 MILE | $645 | $705 | $705 | $645 |
| 642E00204 LANE LINE, 6", TYPE 1 | 2.34 MILE | $550 | $550 | $550 | $550 |
| 642E00300 CENTER LINE, TYPE 1 | 5.66 MILE | $950 | $950 | $950 | $950 |
| 644E00400 CHANNELIZING LINE, 8" | 3,010 FT | $1.50 | $0.95 | $0.95 | $1.50 |
| 644E00500 STOP LINE | 586 FT | $6.00 | $6.00 | $6.00 | $6.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 120 FT | $6.00 | $5.50 | $5.50 | $6.00 |
| 644E00900 ISLAND MARKING | 100 SF | $6.00 | $3.00 | $3.00 | $6.00 |
| 644E01300 LANE ARROW | 30 EACH | $88.00 | $95.00 | $95.00 | $88.00 |
| 644E01510 DOTTED LINE, 6" | 200 FT | $2.00 | $3.00 | $3.00 | $2.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $2,500 | $2,500 | $2,500 | $2,500 |
| 614E12460 WORK ZONE MARKING SIGN | 68 EACH | $70.00 | $70.00 | $70.00 | $70.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $200 | $115 | $250 | $200 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $900 | $900 | $900 | $900 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 4.68 MILE | $700 | $600 | $600 | $700 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 11.32 MILE | $900 | $1,050 | $1,050 | $900 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 5.12 MILE | $595 | $700 | $700 | $595 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 6,020 FT | $0.50 | $0.85 | $0.85 | $0.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 370 FT | $3.00 | $3.50 | $3.50 | $3.00 |
| 516E31000 JOINT SEALER | 112 FT | $29.00 | $29.00 | $16.86 | $16.86 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 64 SF | $105 | $105 | $98.39 | $98.39 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $8,000 | $25,000 | $12,000 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $2,000 | $2,500 | $2,000 | $2,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $5,000 | $500 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 5,476 CY | $190 | $1.04M | 43% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442) | 905 CY | $240 | $217k | 9% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.50") | 132,413 SY | $1.15 | $152k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $135,483 | $135k | 6% |
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 1,000 SY | $100 | $100k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 3,325 FT | $23.2 | $77k | 3% |
| 452E14050 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 579 SY | $76.25 | $44k | 2% |
| 253E02000 PAVEMENT REPAIR | 90 CY | $480 | $43k | 2% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 69 CY | $450 | $31k | 1% |