ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 75 more items below.
| Item | Quantity | R1Axis Civil Construction LLC | R2Rietschlin Construction INC | R3Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 819 CY | $128 | $139 | $130 | 13% |
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (594 CY | $132 | $143 | $142 | 10% |
| 611E30000 96" CONDUIT, TYPE A, 706.02, 707.02 WITH CFP (0.18 | 84 FT | $880 | $1,270 | $850 | 9% |
| 602E20000 CONCRETE MASONRY | 85.4 CY | $780 | $880 | $1,550 | 8% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 454 CY | $145 | $157 | $167 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $30,000 | $55,592 | 6% |
| 304E20000 AGGREGATE BASE | 852 CY | $58.00 |
| Item | Quantity | R1Axis Civil Construction LLC | R2Rietschlin Construction INC | R3Eclipse CO LLC |
|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 862 SY | $12.00 | $13.00 | $13.00 |
| 202E30200 STEPS REMOVED | 8 FT | $12.00 | $71.00 | $65.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 220 FT | $12.00 | $20.00 | $18.50 |
| 202E38000 GUARDRAIL REMOVED | 592 FT | $3.00 | $3.00 | $3.00 |
| 202E75000 FENCE REMOVED | 39 FT | $3.00 | $16.00 | $8.00 |
| 203E35120 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $74.00 |
| $51.00 |
| 6% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 264 CY | $170 | $184 | $221 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $50,000 | $40,000 | 5% |
| 203E10000 EXCAVATION | 1,944 CY | $18.00 | $11.00 | $15.00 | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 8,996 SY | $3.25 | $3.50 | $1.50 | 4% |
| 203E20000 EMBANKMENT | 1,557 CY | $18.00 | $15.00 | $10.00 | 3% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 673 SY | $38.00 | $72.00 | $96.00 | 3% |
| 832E30000 EROSION CONTROL | 25,000 EACH | $1.00 | $1.00 | $1.00 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $20,000 | $9,500 | $24,000 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $19,000 | $19,000 | $15,000 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $15,000 | $46,000 | $21,000 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 4,657 GAL | $3.00 | $3.25 | $3.25 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $13,500 | $15,000 | $18,500 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 15 MNTH | $900 | $1,050 | $1,400 | 2% |
| 36 CY |
| $75.00 |
| $82.00 |
| $71.00 |
| 204E10000 SUBGRADE COMPACTION | 4,284 SY | $3.00 | $1.75 | $1.50 |
| 204E45000 PROOF ROLLING | 4 HOUR | $250 | $162 | $214 |
| 606E14000 GUARDRAIL, TYPE 8 | 50 FT | $68.00 | $32.50 | $32.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 440 FT | $24.35 | $22.00 | $21.50 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 1 EACH | $2,235 | $1,998 | $1,967 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP350 OR MASH 2016 | 2 EACH | $2,720 | $2,592 | $2,552 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,000 | $1,188 | $1,170 |
| 608E40000 CONCRETE STEPS, TYPE A | 8 FT | $200 | $521 | $249 |
| 609E23000 COMBINATION CURB AND GUTTER, TYPE 4 | 140 FT | $44.00 | $40.00 | $181 |
| 690E50000 SPECIAL - MAILBOX SUPPORT | 8 EACH | $150 | $162 | $176 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 8 EACH | $125 | $280 | $197 |
| 601E11000 RIPRAP, TYPE D | 23 SY | $225 | $182 | $73.50 |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 120 CY | $78.00 | $83.00 | $93.50 |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 2 CY | $78.00 | $650 | $95.00 |
| 659E00300 TOPSOIL | 610 CY | $20.00 | $25.50 | $41.00 |
| 659E10000 SEEDING AND MULCHING | 5,276 SY | $1.35 | $0.80 | $1.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 265 SY | $1.00 | $0.74 | $1.00 |
| 659E15000 INTER-SEEDING | 265 SY | $0.01 | $0.74 | $0.01 |
| 659E20000 COMMERCIAL FERTILIZER | 0.74 TON | $500 | $800 | $532 |
| 659E31000 LIME | 1.09 ACRE | $200 | $170 | $213 |
| 659E35000 WATER | 29 MGAL | $1.00 | $1.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 216 SY | $2.35 | $2.00 | $2.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,695 | $1,620 | $2,339 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $3,400 | $3,780 | $5,581 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $8,025 | $14,040 | $13,762 |
| 202E11000 STRUCTURE REMOVED | 1 LS | $12,500 | $16,000 | $7,665 |
| 202E98100 REMOVAL MISC.: INSPECTION WELL | 1 EACH | $250 | $560 | $206 |
| 202E98200 REMOVAL MISC.: CONDUIT | 10 FT | $20.00 | $28.00 | $10.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 50 CY | $20.00 | $16.00 | $11.50 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 62 SY | $33.00 | $32.50 | $30.50 |
| 518E21100 POROUS BACKFILL | 20 CY | $120 | $150 | $64.00 |
| 605E06000 4" BASE PIPE UNDERDRAINS | 136 FT | $14.00 | $14.50 | $8.00 |
| 605E31100 AGGREGATE DRAINS | 644 FT | $14.00 | $8.00 | $11.50 |
| 611E04600 12" CONDUIT, TYPE C | 249 FT | $50.00 | $40.00 | $53.00 |
| 611E07600 18" CONDUIT, TYPE C | 134 FT | $65.00 | $50.00 | $63.00 |
| 611E07600 18" CONDUIT, TYPE C, 707.33 | 108 FT | $65.00 | $53.00 | $64.50 |
| 611E07900 18" CONDUIT, TYPE D | 156 FT | $65.00 | $41.00 | $57.50 |
| 611E97400 CONDUIT, MISC.: 10", TYPE F FOR DRAINAGE DISCHARGE | 10 FT | $10.00 | $30.00 | $14.00 |
| 611E97400 CONDUIT, MISC.: 4", TYPE B FOR DRAINAGE DISCHARGE | 10 FT | $6.00 | $35.00 | $17.50 |
| 611E97400 CONDUIT, MISC.: 6", TYPE C FOR DRAINAGE DISCHARGE | 10 FT | $8.00 | $27.00 | $19.50 |
| 611E97400 CONDUIT, MISC.: 8", TYPE E FOR DRAINAGE DISCHARGE | 10 FT | $6.00 | $32.00 | $14.00 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $2,800 | $2,700 | $2,693 |
| 611E99550 MANHOLE, NO. 1 | 1 EACH | $2,800 | $3,000 | $3,341 |
| 611E99574 MANHOLE, NO. 3 | 4 EACH | $2,800 | $2,750 | $3,341 |
| 611E99720 INSPECTION WELL | 2 EACH | $750 | $710 | $491 |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 1.38 MILE | $1,600 | $1,728 | $2,500 |
| 251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 182 SY | $53.00 | $57.25 | $35.00 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 174 CY | $77.00 | $91.00 | $57.00 |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 634 SY | $12.50 | $13.50 | $12.75 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 6 CY | $275 | $297 | $400 |
| 617E10100 COMPACTED AGGREGATE | 1 CY | $100 | $340 | $105 |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 1,544 FT | $4.00 | $4.50 | $3.75 |
| 621E00100 RPM | 68 EACH | $65.03 | $40.00 | $39.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 37 EACH | $16.88 | $24.00 | $8.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 BI-DIRECTIONAL | 25 EACH | $12.00 | $11.00 | $10.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 117 FT | $14.30 | $16.25 | $16.00 |
| 630E08600 SIGN POST REFLECTOR | 4 EACH | $60.00 | $54.00 | $53.00 |
| 630E80100 SIGN, FLAT SHEET | 57 SF | $27.00 | $23.75 | $23.50 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 7 EACH | $25.00 | $22.00 | $21.50 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $25.00 | $22.00 | $21.50 |
| 644E00104 EDGE LINE, 6" | 1.27 MILE | $4,794 | $5,100 | $5,097 |
| 644E00300 CENTER LINE | 0.9 MILE | $5,379 | $6,900 | $5,719 |
| 644E00400 CHANNELIZING LINE, 8" | 284 FT | $2.66 | $2.00 | $3.00 |
| 644E01300 LANE ARROW | 3 EACH | $156 | $125 | $166 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $85.00 | $71.00 | $69.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 15 SNMT | $450 | $650 | $638 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.37 MILE | $995 | $1,450 | $1,409 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.73 MILE | $650 | $950 | $888 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,056 | $20,000 | $22,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 819 CY | $128 | $105k | 10% |
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (594 CY | $132 | $78k | 7% |
| 611E30000 96" CONDUIT, TYPE A, 706.02, 707.02 WITH CFP (0.18 | 84 FT | $880 | $74k | 7% |
| 602E20000 CONCRETE MASONRY | 85.4 CY | $780 | $67k | 6% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 454 CY | $145 | $66k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $50k | 5% |
| 304E20000 AGGREGATE BASE | 852 CY | $58 | $49k | 5% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 264 CY | $170 | $45k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 203E10000 EXCAVATION | 1,944 CY | $18 | $35k | 3% |