| Item | Quantity | R1Bog Construction INC | R2Jet Excavating Company | R3Eclipse CO LLC | R4Northstar Contracting INC | % of bid |
|---|---|---|---|---|---|---|
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $31,000 | $28,000 | $5,580 | $50,000 | 11% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 270 SY | $95.00 | $99.00 | $115 | $75.00 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $26,280 | $95,000 | 7% |
| 441E50701 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (25 CY | $750 | $800 | $846 | $350 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 33 CY | $500 | $500 | $520 | $150 | 6% |
| 203E20000 EMBANKMENT | 645 CY | $25.00 | $30.00 | $14.00 | $25.00 |
| Item | Quantity | R1Bog Construction INC | R2Jet Excavating Company | R3Eclipse CO LLC | R4Northstar Contracting INC |
|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 2 EACH | $500 | $250 | $362 | $750 |
| 202E23000 PAVEMENT REMOVED | 98 SY | $42.00 | $35.00 | $95.00 | $15.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 76 FT | $30.00 | $55.00 | $19.00 | $20.00 |
| 202E38000 GUARDRAIL REMOVED | 153 FT | $3.00 | $4.00 | $2.00 | $10.00 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 2 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 6% |
| 203E10000 EXCAVATION | 628 CY | $24.00 | $25.00 | $18.00 | $20.00 | 6% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $15,000 | $22,000 | $8,035 | $85,000 | 6% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,300 | $2,100 | $2,148 | $3,500 | 5% |
| 606E15050 GUARDRAIL, TYPE MGS | 525 FT | $25.00 | $27.00 | $28.00 | $50.00 | 5% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 680 FT | $15.00 | $20.00 | $36.00 | $72.00 | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $10,000 | $20,000 | $78,385 | $90,000 | 4% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $10,000 | $15,000 | $11,675 | $15,000 | 4% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 11 CY | $900 | $1,100 | $1,008 | $180 | 4% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350) | 3 EACH | $3,200 | $3,275 | $3,231 | $4,000 | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,500 | $10,000 | $0.01 | $7,900 | 3% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 7.13 CY | $1,100 | $1,850 | $2,261 | $1,500 | 3% |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 6 MNTH | $1,200 | $750 | $1,674 | $1,500 | 3% |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 1,325 SY | $5.00 | $2.00 | $4.00 | $2.50 | 2% |
| 659E00300 TOPSOIL | 172 CY | $35.00 | $40.00 | $74.00 | $45.00 | 2% |
| $300 |
| $200 |
| $112 |
| $175 |
| 202E75000 FENCE REMOVED | 69 FT | $10.00 | $8.00 | $6.00 | $5.00 |
| 204E10000 SUBGRADE COMPACTION | 141 SY | $5.00 | $3.00 | $10.00 | $2.50 |
| 204E45000 PROOF ROLLING | 1 HOUR | $60.00 | $50.00 | $244 | $250 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,500 | $1,700 | $1,540 | $4,000 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 5 SY | $200 | $125 | $106 | $250 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 5.56 CY | $150 | $250 | $203 | $300 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $50.00 | $28.00 | $300 |
| 659E00530 SEEDING AND MULCHING, CLASS 3B | 224 SY | $5.00 | $3.00 | $4.00 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 78 SY | $1.00 | $1.00 | $4.00 | $1.75 |
| 659E15000 INTER-SEEDING | 78 SY | $1.00 | $1.00 | $0.28 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.22 TON | $1,000 | $750 | $279 | $750 |
| 659E31000 LIME | 0.33 ACRE | $100 | $250 | $28.00 | $500 |
| 659E35000 WATER | 9 MGAL | $1.00 | $1.00 | $1.00 | $200 |
| 670E00700 DITCH EROSION PROTECTION | 259 SY | $4.00 | $2.00 | $2.00 | $5.00 |
| 832E30000 EROSION CONTROL | 2,480 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 137 SY | $9.00 | $4.00 | $5.00 | $5.00 |
| 605E05200 4" UNCLASSIFIED PIPE UNDERDRAINS | 40 FT | $20.00 | $10.00 | $14.00 | $15.00 |
| 605E06000 4" BASE PIPE UNDERDRAINS | 80 FT | $10.00 | $22.00 | $13.00 | $15.00 |
| 605E31100 AGGREGATE DRAINS | 40 FT | $20.00 | $12.00 | $11.00 | $15.00 |
| 611E00200 4" CONDUIT, TYPE C, 707.31 | 80 FT | $15.00 | $20.00 | $39.00 | $25.00 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 57 FT | $12.00 | $24.00 | $27.00 | $25.00 |
| 611E04600 12" CONDUIT, TYPE C | 27 FT | $50.00 | $85.00 | $70.00 | $75.00 |
| 611E05900 15" CONDUIT, TYPE B | 46 FT | $125 | $200 | $114 | $100 |
| 611E06100 15" CONDUIT, TYPE C | 10 FT | $75.00 | $195 | $77.00 | $100 |
| 611E06101 15" CONDUIT, TYPE C, AS PER PLAN | 20 FT | $115 | $265 | $130 | $75.00 |
| 611E06700 15" CONDUIT, TYPE F | 55 FT | $75.00 | $215 | $141 | $100 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $3,500 | $4,750 | $5,525 | $3,500 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $2,500 | $2,200 | $3,105 | $3,000 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 3 EACH | $350 | $250 | $445 | $750 |
| 304E20000 AGGREGATE BASE | 39 CY | $110 | $125 | $101 | $50.00 |
| 407E10000 TACK COAT | 14 GAL | $30.00 | $25.00 | $33.00 | $2.50 |
| 609E10000 ASPHALT CONCRETE CURB, TYPE 1 | 60 FT | $75.00 | $68.00 | $85.00 | $25.00 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 4 EACH | $100 | $80.00 | $114 | $50.00 |
| 621E00100 RPM | 5 EACH | $600 | $675 | $543 | $50.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 5 EACH | $50.00 | $10.00 | $18.00 | $75.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 BIDIRECTIONAL | 8 EACH | $15.00 | $10.00 | $9.00 | $50.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 28 FT | $30.00 | $23.50 | $17.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $150 | $65.00 | $95.00 | $300 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $150 | $25.00 | $39.00 | $150 |
| 646E10010 EDGE LINE, 6" | 0.14 MILE | $32,000 | $20,000 | $20,642 | $14,000 |
| 646E10200 CENTER LINE | 0.11 MILE | $35,000 | $30,000 | $24,292 | $28,000 |
| 646E10400 STOP LINE | 37 FT | $25.00 | $10.00 | $17.00 | $30.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $50.00 | $45.00 | $90.00 | $75.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 400 FT | $3.00 | $3.00 | $3.00 | $3.00 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $5,000 | $3,000 | $28,234 | $3,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 BIDIRECTIONAL | 15 EACH | $10.00 | $15.00 | $7.00 | $25.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 15 EACH | $20.00 | $15.00 | $18.00 | $35.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $950 | $800 | $1,172 | $1,500 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.08 MILE | $10,000 | $6,500 | $11,849 | $18,000 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.47 MILE | $5,000 | $6,500 | $7,321 | $14,000 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 52 FT | $20.00 | $5.00 | $29.00 | $3.00 |
| 616E10000 WATER | 20 MGAL | $1.00 | $1.00 | $69.00 | $200 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,500 | $10,000 | $29,524 | $85,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,500 | $4,500 | $8,063 | $25,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $31,000 | $31k | 8% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 270 SY | $95 | $26k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 5% |
| 441E50701 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (25 CY | $750 | $19k | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 33 CY | $500 | $17k | 4% |
| 203E20000 EMBANKMENT | 645 CY | $25 | $16k | 4% |
| 203E10000 EXCAVATION | 628 CY | $24 | $15k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $15,000 | $15k | 4% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,300 | $14k | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 525 FT | $25 | $13k | 4% |