TUS-Bodmer Ave Sidewalks
TUS County · est $0.2M
Bid dateThursday, January 13—
TUS County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 19items by winning bid’s extended amount.
| Item | Quantity | R1Smith Paving & Excavating INC | R2Stanley Miller Construction Company | R3D L Smith Concrete LLC | R4Rmi Cement LLC | R5Madex Construction CO | R6Tucson INC | R7Alan Stone CO INC | R8Shelly & Sands INC | R9Wolf Creek Contracting Company LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 12,575 SF | $6.35 | $5.50 | $8.10 | $5.84 | $7.91 | $6.95 | $8.00 | $7.00 | $10.10 | 56% |
| 304E20000 AGGREGATE BASE | 169 CY | $60.00 | $100 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $44.00 |
| $108 |
| $88.16 |
| $140 |
| $100 |
| $170 |
| $105 |
| 7% |
| 202E30000 WALK REMOVED | 5,014 SF | $1.80 | $1.50 | $0.50 | $2.00 | $2.21 | $2.10 | $3.00 | $2.00 | $4.45 | 6% |
| 608E52000 CURB RAMP | 640 SF | $10.00 | $16.50 | $8.00 | $20.23 | $15.03 | $41.00 | $25.00 | $41.00 | $16.16 | 5% |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 184 SF | $26.00 | $33.00 | $21.00 | $1.05 | $30.83 | $23.00 | $25.00 | $39.00 | $22.61 | 3% |
| 608E13001 6" CONCRETE WALK, AS PER PLAN | 473 SF | $10.00 | $12.00 | $12.00 | $7.56 | $12.10 | $10.00 | $15.00 | $9.20 | $9.16 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,250 | $5,000 | $12,000 | $9,600 | $7,613 | $12,575 | $7,500 | $25,000 | $2,129 | 3% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,300 | $11,611 | $6,500 | $7,722 | $6,041 | $3,300 | $5,500 | $2,200 | $7,282 | 2% |
| 654E10000 RENOVATING EXISTING SOIL | 7.6 MSF | $410 | $100 | $125 | $150 | $28.61 | $34.50 | $50.00 | $1,900 | $872 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,900 | $2,222 | $3,500 | $3,770 | $1,161 | $325 | $4,000 | $5,320 | $1,326 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $2,500 | $6,056 | $1,000 | $3,770 | $6,768 | $3,075 | $7,500 | $10,000 | $71,723 | 2% |
| 659E10000 SEEDING AND MULCHING | 1,286 SY | $1.90 | $1.68 | $4.00 | $6.39 | $4.32 | $6.00 | $5.00 | $5.50 | $5.59 | 2% |
| 204E10000 SUBGRADE COMPACTION | 1,507 SY | $1.05 | $1.00 | $1.00 | $1.07 | $1.16 | $1.90 | $3.00 | $0.95 | $2.52 | 1% |
| 651E10000 TOPSOIL STOCKPILED | 17.8 CY | $88.00 | $76.00 | $25.00 | $72.80 | $14.67 | $82.00 | $100 | $13.50 | $34.38 | 1% |
| 652E10000 PLACING STOCKPILED TOPSOIL | 17.8 CY | $88.00 | $90.00 | $25.00 | $72.80 | $16.30 | $220 | $50.00 | $13.50 | $34.38 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $1,500 | $2,026 | $2,200 | $15,944 | $5,211 | $3,275 | $3,000 | $1,270 | $3,000 | 1% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 2 EACH | $535 | $700 | $750 | $800 | $870 | $775 | $1,400 | $1,120 | $650 | 1% |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 659E20000 COMMERCIAL FERTILIZER | 0.12 TON | $1,500 | $800 | $250 | $200 | $6,570 | $3,900 | $600 | $1,065 | $70.58 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 12,575 SF | $6.35 | $80k | 56% |
| 304E20000 AGGREGATE BASE | 169 CY | $60 | $10k | 7% |
| 202E30000 WALK REMOVED | 5,014 SF | $1.8 | $9k | 6% |
| 608E52000 CURB RAMP | 640 SF | $10 | $6k | 5% |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 184 SF | $26 | $5k | 3% |
| 608E13001 6" CONCRETE WALK, AS PER PLAN | 473 SF | $10 | $5k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,250 | $4k | 3% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,300 | $3k | 2% |
| 654E10000 RENOVATING EXISTING SOIL | 7.6 MSF | $410 | $3k | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,900 | $3k | 2% |