MEG-SR 684-00.19
MEG County · est $0.3M
Bid dateThursday, March 10—
MEG County · est $0.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 40 more items below.
| Item | Quantity | R1Parker Corporation | R2D G M INC | R3Alan Stone CO INC | R4Allard Excavation LLC | R5Ohio-west Virginia Excavating CO | % of bid |
|---|---|---|---|---|---|---|---|
| 611E94801 8' X 4' CONDUIT, TYPE A, 706.05, AS PER PLAN | 46 FT | $1,349 | $1,425 | $1,600 | $1,319 | $1,303 | 23% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 86 CY | $341 | $355 | $290 | $285 | $318 | 11% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 81 CY | $320 | $335 | $280 | $375 | $309 | 10% |
| 614E11000 MAINTAINING TRAFFIC |
| Item | Quantity | R1Parker Corporation | R2D G M INC | R3Alan Stone CO INC | R4Allard Excavation LLC | R5Ohio-west Virginia Excavating CO |
|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 212 SY | $5.00 | $15.00 | $8.00 | $14.60 | $29.00 |
| 202E23500 WEARING COURSE REMOVED | 28 SY | $5.00 | $12.00 | $13.50 | $8.00 | $166 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 27 FT | $10.00 | $20.00 | $25.50 | $5.00 | $82.00 |
| 202E38000 GUARDRAIL REMOVED | 30 FT | $5.00 | $2.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $18,600 |
| $35,000 |
| $36,000 |
| $21,000 |
| $37,000 |
| 7% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 26 CY | $550 | $500 | $730 | $965 | $630 | 5% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 171 SY | $75.00 | $100 | $54.00 | $117 | $129 | 5% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,400 | $13,500 | $3,500 | $4,400 | $8,500 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $11,600 | $10,000 | $24,500 | $63,000 | $10,000 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,600 | $11,000 | $1,000 | $1,500 | $3,500 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,600 | $7,000 | $6,500 | $5,900 | $1,000 | 4% |
| 613E41300 LOW STRENGTH MORTAR BACKFILL (TYPE 2) | 84 CY | $120 | $100 | $163 | $112 | $229 | 4% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 10 CY | $650 | $1,000 | $1,700 | $2,425 | $2,962 | 2% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $6,000 | $9,000 | $12,000 | $3,600 | $14,000 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $6,000 | $13,000 | $14,000 | $5,900 | $16,000 | 2% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,500 | $2,000 | $2,400 | $1,900 | $3,237 | 2% |
| 304E20000 AGGREGATE BASE | 92 CY | $65.00 | $100 | $91.00 | $78.00 | $234 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $5,000 | $2,000 | $5,000 | $6,000 | $6,500 | 2% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 3,511 LB | $1.25 | $2.00 | $3.00 | $3.65 | $4.00 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, (T = 3") | 527 SY | $8.00 | $16.00 | $15.00 | $15.25 | $13.00 | 2% |
| 623E40500 REFERENCE MONUMENT | 8 EACH | $500 | $350 | $878 | $300 | $827 | 2% |
| $11.50 |
| $3.00 |
| $24.00 |
| 203E10000 EXCAVATION | 177 CY | $20.00 | $30.00 | $19.50 | $18.00 | $52.00 |
| 203E20000 EMBANKMENT | 82 CY | $20.00 | $30.00 | $7.50 | $8.00 | $134 |
| 204E10000 SUBGRADE COMPACTION | 558 SY | $0.50 | $8.00 | $2.00 | $3.00 | $3.00 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 3 EACH | $100 | $200 | $277 | $172 | $330 |
| 659E10000 SEEDING AND MULCHING | 826 SY | $1.00 | $4.00 | $4.00 | $1.55 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.08 TON | $3,125 | $800 | $664 | $500 | $1,000 |
| 659E31000 LIME | 0.17 ACRE | $1,471 | $100 | $934 | $500 | $100 |
| 659E35000 WATER | 5 MGAL | $0.05 | $1.00 | $0.01 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $1,000 | $1,500 | $7,400 | $4,300 | $11,000 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 1 CY | $650 | $1,500 | $3,000 | $2,589 | $5,500 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 53 SY | $12.00 | $40.00 | $42.50 | $50.00 | $102 |
| 512E33000 TYPE 2 WATERPROOFING | 55 SY | $14.00 | $25.00 | $22.50 | $30.50 | $53.00 |
| 512E33010 TYPE 3 WATERPROOFING | 58 SY | $18.00 | $45.00 | $61.00 | $40.00 | $53.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 26 SF | $5.00 | $15.00 | $3.00 | $1.71 | $4.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 8 CY | $150 | $120 | $209 | $125 | $648 |
| 611E04900 12" CONDUIT, TYPE D | 40 FT | $50.00 | $80.00 | $63.50 | $66.00 | $85.00 |
| 407E20000 NON-TRACKING TACK COAT | 154 GAL | $10.00 | $10.00 | $5.00 | $3.05 | $23.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 26 FT | $30.00 | $15.00 | $20.00 | $20.00 | $42.00 |
| 630E08600 SIGN POST REFLECTOR | 1 EACH | $50.00 | $75.00 | $50.00 | $50.00 | $70.00 |
| 630E80100 SIGN, FLAT SHEET | 16 SF | $55.00 | $15.00 | $25.00 | $25.00 | $77.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4 EACH | $20.00 | $20.00 | $25.00 | $25.00 | $175 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $50.00 | $75.00 | $100 | $100 | $1,122 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $20.00 | $20.00 | $25.00 | $25.00 | $491 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 1 EACH | $50.00 | $75.00 | $100 | $100 | $667 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.19 MILE | $4,050 | $5,000 | $4,050 | $4,050 | $5,600 |
| 642E00300 CENTER LINE, TYPE 1 | 0.29 MILE | $3,250 | $3,500 | $3,250 | $3,250 | $4,500 |
| 502E11100 STRUCTURE FOR MAINTAINING TRAFFIC | 1 LS | $2,000 | $4,500 | $6,800 | $3,540 | $9,000 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $200 | $2,000 | $3,500 | $2,200 | $2,104 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 20 EACH | $10.00 | $35.00 | $38.00 | $38.00 | $54.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 20 EACH | $10.00 | $34.00 | $34.00 | $44.00 | $48.00 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.18 MILE | $4,167 | $6,500 | $6,450 | $6,450 | $9,000 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.4 MILE | $1,875 | $3,200 | $2,950 | $2,950 | $4,100 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 20 FT | $10.00 | $15.00 | $12.00 | $12.00 | $17.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 400 FT | $10.00 | $17.50 | $21.00 | $23.40 | $56.00 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 40 FT | $10.00 | $25.00 | $70.00 | $46.00 | $40.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E94801 8' X 4' CONDUIT, TYPE A, 706.05, AS PER PLAN | 46 FT | $1,349 | $62k | 21% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 86 CY | $341 | $29k | 10% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 81 CY | $320 | $26k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $18,600 | $19k | 6% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 26 CY | $550 | $14k | 5% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 171 SY | $75 | $13k | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,400 | $12k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $11,600 | $12k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,600 | $11k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,600 | $11k | 4% |