ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 62 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Complete General Construction Company | R3Catts Construction INC | R4Kokosing Construction Company INC | % of bid |
|---|---|---|---|---|---|---|
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 274 CY | $445 | $445 | $545 | $445 | 10% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 1,247 SY | $90.00 | $80.00 | $85.00 | $134 | 9% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 1,241 SY | $90.00 | $75.00 | $85.00 | $134 | 9% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 1,729 SY | $61.50 | $80.00 | $82.00 | $61.50 | 9% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,239 SY | $55.00 | $83.00 | $78.50 | $65.00 | 5% |
| 606E35120 BRIDGE TERMINAL ASSEMBLY, TYPE 3 | 18 EACH |
| Item | Quantity | R1Shelly & Sands INC | R2Complete General Construction Company | R3Catts Construction INC | R4Kokosing Construction Company INC |
|---|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 1,012.5 FT | $2.80 | $2.00 | $2.40 | $5.00 |
| 606E13000 GUARDRAIL, TYPE 5 | 1,012.5 FT | $21.00 | $21.60 | $25.00 | $29.00 |
| 606E32500 BRIDGE TERMINAL ASSEMBLY, TYPE F | 2 EACH | $2,200 | $1,785 | $2,130 | $5,850 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $3,750 |
| $3,265 |
| $3,894 |
| $5,475 |
| 5% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,245 SY | $53.00 | $93.00 | $37.00 | $65.00 | 5% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 651 SY | $86.00 | $85.00 | $135 | $134 | 4% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $55,000 | $30,000 | $7,500 | $35,000 | 4% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $55,000 | $35,000 | $20,850 | $35,000 | 4% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 609 SY | $90.00 | $90.00 | $85.00 | $134 | 4% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 528 SY | $98.00 | $85.00 | $90.00 | $134 | 4% |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 513 FT | $90.00 | $103 | $110 | $125 | 4% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $45,000 | $45,000 | $7,750 | $55,300 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $42,000 | $120,000 | $80,000 | $89,000 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $100,000 | $63,500 | $100,000 | 3% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 651 SY | $61.00 | $82.00 | $37.00 | $65.00 | 3% |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 428 FT | $90.00 | $103 | $110 | $125 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (0.5" THICK) | 3,835 SY | $9.50 | $9.50 | $5.00 | $9.50 | 3% |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 393 FT | $90.00 | $103 | $110 | $125 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" THICK) | 2,717 SY | $10.60 | $10.60 | $5.00 | $10.60 |
| 407E20000 NON-TRACKING TACK COAT | 590 GAL | $4.00 | $4.00 | $4.00 | $4.00 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 3,054 FT | $2.20 | $2.00 | $8.00 | $2.05 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 34 EACH | $8.00 | $40.00 | $29.00 | $100 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 2.13 MILE | $1,625 | $1,625 | $19,346 | $1,625 |
| 642E00204 LANE LINE, 6", TYPE 1 | 1.23 MILE | $1,075 | $1,075 | $1,282 | $1,075 |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 370 FT | $4.25 | $4.25 | $5.00 | $4.25 |
| 642E01510 DOTTED LINE, 6", TYPE 1 | 212 FT | $2.00 | $2.00 | $2.00 | $2.00 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,000 | $2,440 | $2,909 | $4,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE WAY) | 80 EACH | $8.00 | $28.00 | $34.00 | $6.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 80 EACH | $18.00 | $38.00 | $45.00 | $17.00 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 2.11 MILE | $3,050 | $3,050 | $3,636 | $3,050 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 1,800 FT | $1.50 | $1.50 | $2.00 | $1.50 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,870 FT | $13.00 | $20.00 | $25.00 | $15.00 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 50 LB | $2.14 | $5.00 | $4.00 | $4.25 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 4 CY | $2,465 | $4,000 | $1,200 | $1,800 |
| 516E11800 VERTICAL EXTENSION OF STRUCTURAL EXPANSION JOINT | 170 FT | $115 | $208 | $256 | $190 |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 342 FT | $90.00 | $103 | $104 | $160 |
| 848E30100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 37 CY | $550 | $500 | $1,000 | $720 |
| 848E50000 HAND CHIPPING | 188 SY | $45.00 | $40.00 | $125 | $290 |
| 848E50100 TEST SLAB | 1 LS | $3,500 | $1,000 | $250 | $1,000 |
| 848E50200 FULL-DEPTH REPAIR | 15 CY | $1,000 | $700 | $1,300 | $3,800 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 50 LB | $2.14 | $5.00 | $16.00 | $4.25 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 4 CY | $2,465 | $4,000 | $3,252 | $1,800 |
| 516E11800 VERTICAL EXTENSION OF STRUCTURAL EXPANSION JOINT | 169 FT | $115 | $208 | $250 | $190 |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 380 FT | $90.00 | $103 | $113 | $160 |
| 848E30100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 37 CY | $550 | $500 | $1,300 | $720 |
| 848E50000 HAND CHIPPING | 187 SY | $55.00 | $40.00 | $115 | $290 |
| 848E50100 TEST SLAB | 1 LS | $3,500 | $1,000 | $250 | $1,000 |
| 848E50200 FULL-DEPTH REPAIR | 15 CY | $1,000 | $700 | $1,300 | $3,800 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 50 LB | $2.14 | $5.00 | $16.00 | $4.25 |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 609 SY | $58.00 | $82.00 | $67.00 | $65.00 |
| 848E30100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 18 CY | $550 | $500 | $1,200 | $720 |
| 848E50000 HAND CHIPPING | 92 SY | $55.00 | $40.00 | $115 | $290 |
| 848E50100 TEST SLAB | 1 LS | $3,500 | $1,000 | $250 | $1,000 |
| 848E50200 FULL-DEPTH REPAIR | 8 CY | $1,000 | $700 | $1,300 | $3,800 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED (1.25" THICK) | 609 SY | $14.00 | $12.50 | $20.00 | $25.00 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $14,000 | $8,000 | $4,000 | $10,000 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 50 LB | $2.14 | $5.00 | $4.00 | $4.25 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 3 CY | $2,175 | $4,000 | $1,200 | $1,800 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 6 SF | $325 | $275 | $200 | $225 |
| 848E30100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 19 CY | $550 | $500 | $1,000 | $720 |
| 848E50000 HAND CHIPPING | 98 SY | $42.00 | $40.00 | $125 | $290 |
| 848E50100 TEST SLAB | 1 LS | $3,500 | $1,000 | $2,000 | $1,000 |
| 848E50200 FULL-DEPTH REPAIR | 8 CY | $1,000 | $700 | $1,300 | $3,800 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED (1.25" THICK) | 651 SY | $14.00 | $12.50 | $15.00 | $25.00 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $12,000 | $8,000 | $4,500 | $10,000 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 50 LB | $2.14 | $5.00 | $16.00 | $4.25 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 2 CY | $2,695 | $4,000 | $1,750 | $1,800 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 4 SF | $325 | $275 | $300 | $225 |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 528 SY | $62.00 | $82.00 | $67.00 | $65.00 |
| 848E30100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 16 CY | $550 | $500 | $1,200 | $720 |
| 848E50000 HAND CHIPPING | 80 SY | $50.00 | $40.00 | $115 | $290 |
| 848E50100 TEST SLAB | 1 LS | $3,500 | $1,000 | $250 | $1,000 |
| 848E50200 FULL-DEPTH REPAIR | 7 CY | $1,000 | $700 | $1,300 | $3,800 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED (1.25" THICK) | 528 SY | $15.00 | $12.50 | $20.00 | $25.00 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $5,300 | $4,500 | $3,000 | $3,750 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $15,000 | $16,500 | $10,457 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 274 CY | $445 | $122k | 7% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 1,247 SY | $90 | $112k | 6% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 1,241 SY | $90 | $112k | 6% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 1,729 SY | $61.5 | $106k | 6% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,239 SY | $55 | $68k | 4% |
| 606E35120 BRIDGE TERMINAL ASSEMBLY, TYPE 3 | 18 EACH | $3,750 | $68k | 4% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,245 SY | $53 | $66k | 4% |
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 651 SY | $86 | $56k | 3% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $55,000 | $55k | 3% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $55,000 | $55k | 3% |