CLI-SR 350-04.20
CLI County · est $0.8M
Bid dateThursday, September 15—
CLI County · est $0.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1John R Jurgensen Company | R2Barrett Paving Materials INC | % of bid |
|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 1,930 CY | $204 | $250 | 47% |
| 253E02000 PAVEMENT REPAIR | 400 CY | $392 | $390 | 19% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A, 1" | 55,583 SY | $1.35 | $2.50 | 9% |
| 644E00104 EDGE LINE, 6" | 7.42 MILE | $4,336 | $4,336 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,475 | $40,000 | 3% |
| 407E20000 NON-TRACKING TACK COAT | 5,003 GAL | $5.00 | $4.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | 2% |
| 644E00300 CENTER LINE | 3.71 MILE | $5,206 | $5,206 | 2% |
| 617E10100 COMPACTED AGGREGATE | 181 CY | $102 | $135 | 2% |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 3.71 MILE | $3,396 | $3,110 | 2% |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 19,588 FT | $0.62 | $0.40 | 1% |
| 621E00100 RPM | 245 EACH | $37.25 | $37.25 | 1% |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 7.42 MILE | $908 | $908 | 1% |
| 617E20000 SHOULDER PREPARATION | 4,353 SY | $1.53 | $0.80 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 3.71 MILE | $1,455 | $1,455 | 1% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $4,537 | $4,000 | 1% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 245 EACH | $17.74 | $15.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,987 | $4,900 | 0% |
| 897E02000 PATCHING PLANED SURFACE | 556 SY | $4.38 | $5.00 | 0% |
| 644E00400 CHANNELIZING LINE, 8" | 105 FT | $6.00 | $6.00 | 0% |
| Item | Quantity | R1John R Jurgensen Company | R2Barrett Paving Materials INC |
|---|---|---|---|
| 617E25000 WATER | 4 MGAL | $52.28 | $25.00 |
| 644E00500 STOP LINE | 15 FT | $25.00 | $25.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 15 FT | $10.00 | $10.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 1,930 CY | $203.84 | $393k | 47% |
| 253E02000 PAVEMENT REPAIR | 400 CY | $392.11 | $157k | 19% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A, 1" | 55,583 SY | $1.35 | $75k | 9% |
| 644E00104 EDGE LINE, 6" | 7.42 MILE | $4,336 | $32k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,475 | $27k | 3% |
| 407E20000 NON-TRACKING TACK COAT | 5,003 GAL | $5 | $25k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 644E00300 CENTER LINE | 3.71 MILE | $5,206 | $19k | 2% |
| 617E10100 COMPACTED AGGREGATE | 181 CY | $101.52 | $18k | 2% |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 3.71 MILE | $3,396 | $13k | 2% |