SAN-SR 19-10.84 Resurfacing
SAN County · est $3.8M
Bid dateThursday, November 3—
SAN County · est $3.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 48 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2M & B Asphalt CO INC | R3Erie Blacktop INC | R4Gerken Paving INC | % of bid |
|---|---|---|---|---|---|---|
| 441E50301 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (6697 CY | $149 | $155 | $166 | $160 | 32% |
| 424E14001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (3401 CY | $240 | $219 | $245 | $240 | 27% |
| 253E02000 PAVEMENT REPAIR | 2,955.4 CY | $140 | $170 | $200 | $202 | 13% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 3" | 120,528 SY | $2.00 | $2.90 | $2.08 | $3.25 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $137,507 | $42,000 | $105,000 | $70,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $100,000 | $75,000 |
| Item | Quantity | R1Kokosing Construction Company INC | R2M & B Asphalt CO INC | R3Erie Blacktop INC | R4Gerken Paving INC |
|---|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 5,862 FT | $1.60 | $1.60 | $1.70 | $1.60 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 3 EACH | $295 | $295 | $310 | $295 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 13 EACH | $135 | $135 | $142 | $135 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 12 EACH | $85.00 | $85.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 5,174.5 FT | $18.00 | $18.00 | $18.90 | $18.00 | 3% |
| 617E10100 COMPACTED AGGREGATE | 1,345 CY | $35.00 | $63.00 | $62.00 | $66.00 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 16,874 GAL | $2.50 | $2.35 | $2.65 | $2.00 | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 14 EACH | $2,780 | $2,780 | $2,920 | $2,780 | 1% |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 22 EACH | $1,100 | $1,800 | $1,575 | $1,600 | 1% |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 14 EACH | $1,345 | $1,345 | $1,420 | $1,345 | 1% |
| 621E00100 RPM | 532 EACH | $31.25 | $31.25 | $33.00 | $31.25 | 1% |
| 209E60500 LINEAR GRADING | 15 MILE | $1,000 | $550 | $1,725 | $1,900 | 0% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $13,150 | $15,000 | $16,000 | $17,000 | 0% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 662.5 FT | $19.20 | $19.20 | $20.20 | $19.20 | 0% |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 14 MILE | $892 | $1,275 | $1,200 | $892 | 0% |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 13 MILE | $925 | $925 | $975 | $925 | 0% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 13.25 MILE | $850 | $850 | $895 | $850 | 0% |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 13 MILE | $850 | $850 | $895 | $850 | 0% |
| $89.25 |
| $85.00 |
| 202E42050 ANCHOR ASSEMBLY REMOVED, TYPE B | 2 EACH | $110 | $110 | $116 | $110 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 12 EACH | $50.00 | $50.00 | $52.50 | $50.00 |
| 203E20000 EMBANKMENT | 100 CY | $58.50 | $58.50 | $61.50 | $58.50 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 68 STA | $43.00 | $43.00 | $45.50 | $43.00 |
| 601E20010 CRUSHED AGGREGATE SLOPE PROTECTION | 100 CY | $76.00 | $76.00 | $80.00 | $76.00 |
| 606E17350 GUARDRAIL, TYPE MGS, 25' LONG-SPAN | 25 FT | $27.60 | $27.60 | $29.00 | $27.60 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 2 EACH | $2,120 | $2,120 | $2,230 | $2,120 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,640 | $2,640 | $2,775 | $2,640 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 8 EACH | $895 | $895 | $940 | $895 |
| 614E13318 BARRIER REFLECTOR, TYPE 5 BIDIRECTIONAL | 138 EACH | $11.60 | $11.60 | $12.20 | $11.60 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 1 EACH | $500 | $1,800 | $1,000 | $1,400 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 1 EACH | $1,700 | $2,000 | $1,350 | $1,800 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $500 | $1,100 | $1,400 | $1,400 |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE | 1 EACH | $1,700 | $1,500 | $1,900 | $1,800 |
| 623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE | 1 EACH | $640 | $1,250 | $850 | $1,000 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 1 EACH | $500 | $400 | $850 | $850 |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 13.3 MILE | $400 | $1,200 | $1,725 | $1,400 |
| 516E31200 SPECIAL - SAWING AND SEALING BITUMINOUS CONCRETE J | 240 FT | $19.31 | $20.00 | $20.30 | $19.31 |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 5,859 LB | $0.58 | $0.68 | $2.30 | $1.90 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 532 EACH | $7.00 | $7.00 | $7.50 | $7.00 |
| 642E00204 LANE LINE, 6", TYPE 1 | 0.54 MILE | $800 | $800 | $840 | $800 |
| 642E00300 CENTER LINE, TYPE 1 | 6.77 MILE | $925 | $925 | $975 | $925 |
| 644E00404 CHANNELIZING LINE, 12" | 629 FT | $2.00 | $2.00 | $2.10 | $2.00 |
| 644E00500 STOP LINE | 142 FT | $8.00 | $8.00 | $8.40 | $8.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 535 FT | $8.00 | $8.00 | $8.40 | $8.00 |
| 644E01000 RAILROAD SYMBOL MARKING | 2 EACH | $700 | $700 | $735 | $700 |
| 644E01300 LANE ARROW | 10 EACH | $85.00 | $85.00 | $89.25 | $85.00 |
| 644E40000 SPEED MEASUREMENT MARKING | 6 EACH | $150 | $200 | $158 | $150 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: LOOP | 1 EACH | $250 | $250 | $265 | $250 |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 1 EACH | $9,750 | $9,750 | $10,250 | $9,750 |
| 614E12460 WORK ZONE MARKING SIGN | 28 EACH | $125 | $100 | $132 | $115 |
| 614E12500 REPLACEMENT SIGN | 5 EACH | $240 | $100 | $252 | $115 |
| 614E12600 REPLACEMENT DRUM | 5 EACH | $64.00 | $50.00 | $68.00 | $55.00 |
| 614E20010 WORK ZONE LANE LINE, CLASS I, 6" | 1.1 MILE | $800 | $800 | $840 | $800 |
| 614E20410 WORK ZONE LANE LINE, CLASS II, 6" | 0.55 MILE | $800 | $800 | $840 | $800 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 6.5 MILE | $925 | $925 | $975 | $925 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 13 MILE | $850 | $850 | $895 | $850 |
| 614E23010 WORK ZONE CHANNELIZING LINE, CLASS I, 12" | 1,258 FT | $1.00 | $1.00 | $1.05 | $1.00 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 629 FT | $1.00 | $1.00 | $1.05 | $1.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 284 FT | $4.00 | $4.00 | $4.20 | $4.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 142 FT | $4.00 | $4.00 | $4.20 | $4.00 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $4,000 | $7,500 | $4,000 | $5,600 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $5,000 | $8,750 | $17,090 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50301 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (6697 CY | $149 | $998k | 31% |
| 424E14001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (3401 CY | $240 | $816k | 25% |
| 253E02000 PAVEMENT REPAIR | 2,955.4 CY | $140 | $414k | 13% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 3" | 120,528 SY | $2 | $241k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $137,507 | $138k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 5,174.5 FT | $18 | $93k | 3% |
| 617E10100 COMPACTED AGGREGATE | 1,345 CY | $35 | $47k | 1% |
| 407E20000 NON-TRACKING TACK COAT | 16,874 GAL | $2.5 | $42k | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 14 EACH | $2,780 | $39k | 1% |