FRA-/FAI-US 33-31.04/00.00 Noise Wall
FRA County · est $1.1M
Bid dateThursday, December 15—
FRA County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 10 more items below.
| Item | Quantity | R1Alan Stone CO INC | R2George J Igel & CO INC | R3Shelly & Sands INC | R4Complete General Construction Company | R5Ohio-west Virginia Excavating CO | R6Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 30,432 SF | $31.00 | $34.75 | $31.50 | $33.00 | $38.63 | $42.44 | 83% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $35,000 | $26,000 | $77,200 | $42,000 | $35,000 | $26,212 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $35,000 | $40,000 | $40,000 |
| Item | Quantity | R1Alan Stone CO INC | R2George J Igel & CO INC | R3Shelly & Sands INC | R4Complete General Construction Company | R5Ohio-west Virginia Excavating CO | R6Sunesis Construction CO |
|---|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 68 CY | $14.00 | $7.50 | $45.00 | $20.00 | $55.00 | $19.97 |
| 616E10000 WATER | 1 MGAL | $1.00 | $95.00 | $40.00 | $70.00 | $1.27 | $80.08 |
| 659E14000 REPAIR SEEDING AND MULCHING | 375 SY | $0.80 | $0.80 | $0.85 | $0.85 | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $40,000 |
| $40,000 |
| $96,791 |
| 3% |
| 832E30000 EROSION CONTROL | 25,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 1,557 FT | $15.00 | $18.00 | $25.00 | $14.00 | $17.00 | $13.77 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $12,500 | $32,675 | $75,000 | $25,000 | $27,952 | 1% |
| 659E00300 TOPSOIL | 828 CY | $14.00 | $7.00 | $12.00 | $20.00 | $32.00 | $23.01 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $7,000 | $8,300 | $13,000 | $20,000 | $9,043 | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $7,100 | $7,100 | $10,000 | $10,500 | $12,000 | $10,653 | 1% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $6,000 | $10,000 | $10,000 | $4,000 | $7,500 | $4,650 | 1% |
| 659E10000 SEEDING AND MULCHING | 7,497 SY | $0.80 | $0.67 | $0.85 | $0.85 | $1.00 | $1.28 | 1% |
| 607E15000 FENCE, TYPE 47 | 170 FT | $35.00 | $28.50 | $28.50 | $20.00 | $30.00 | $28.50 | 1% |
| 607E98000 FENCE, MISC.: TEMPORARY RIGHT OF WAY FENCE | 1,839 FT | $2.50 | $2.50 | $3.00 | $10.00 | $20.00 | $4.72 | 0% |
| 202E75000 FENCE REMOVED | 1,839 FT | $2.00 | $1.50 | $2.00 | $10.00 | $4.44 | $3.39 | 0% |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $3,600 | $5,800 | $11,000 | $8,700 | $11,000 | $2,660 | 0% |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,800 | $1,500 | $1,700 | $1,500 | $2,000 | $1,475 | 0% |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $285 | $340 | $400 | $325 | $275 | $253 | 0% |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 9 SY | $150 | $125 | $200 | $250 | $200 | $169 | 0% |
| 659E20000 COMMERCIAL FERTILIZER | 1.01 TON | $1,100 | $893 | $800 | $800 | $900 | $893 | 0% |
| 203E20000 EMBANKMENT | 81 CY | $12.00 | $4.00 | $10.00 | $20.00 | $55.00 | $21.83 | 0% |
| $0.78 |
| 659E15000 INTER-SEEDING | 375 SY | $0.80 | $0.80 | $0.85 | $0.85 | $1.00 | $0.78 |
| 659E31000 LIME | 1.55 ACRE | $185 | $154 | $80.00 | $80.00 | $90.00 | $154 |
| 659E35000 WATER | 41 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E01500 6" CONDUIT, TYPE F, FOR DRAINAGE CONNECTION | 50 FT | $11.00 | $41.00 | $17.00 | $6.00 | $25.00 | $13.11 |
| 611E01500 6" CONDUIT, TYPE F, FOR UNDERDRAIN OUTLET | 84 FT | $8.50 | $45.00 | $30.00 | $50.00 | $30.00 | $15.80 |
| 611E02500 8" CONDUIT, TYPE E, FOR DRAINAGE CONNECTION | 50 FT | $12.00 | $31.00 | $20.00 | $8.00 | $35.00 | $17.97 |
| 611E04600 12" CONDUIT, TYPE C, FOR DRAINAGE CONNECTION | 50 FT | $16.00 | $29.00 | $35.00 | $125 | $80.00 | $68.73 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 30,432 SF | $31 | $943k | 82% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $35,000 | $35k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $35,000 | $35k | 3% |
| 832E30000 EROSION CONTROL | 25,000 EACH | $1 | $25k | 2% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 1,557 FT | $15 | $23k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $15k | 1% |
| 659E00300 TOPSOIL | 828 CY | $14 | $12k | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $8k | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $7,100 | $7k | 1% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $6,000 | $6k | 1% |