MUS-TR 49-00.56 (Multiuse Path)
MUS County · est $0.7M
Bid dateThursday, January 26—
MUS County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 12 more items below.
| Item | Quantity | R1Scioto Valley Paving LLC | R2Wolf Creek Contracting Company LLC | R3Tucson INC | R4Buds INC | R5Shelly & Sands INC | R6Ohio-west Virginia Excavating CO | % of bid |
|---|---|---|---|---|---|---|---|---|
| 607E98000 FENCE, MISC.: BIKEWAY RAILING (PER ODOT SCD RM-5.2 | 5,050 FT | $38.00 | $26.47 | $36.20 | $42.50 | $35.00 | $38.45 | 31% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (314 CY | $220 | $300 | $252 | $219 | $275 | $227 | 11% |
| 601E21900 SPECIAL - GEOCELL, SLOPE PROTECTION, GEOWEB GW30V6 | 2,640 SY | $20.00 | $13.06 | $11.30 |
| Item | Quantity | R1Scioto Valley Paving LLC | R2Wolf Creek Contracting Company LLC | R3Tucson INC | R4Buds INC | R5Shelly & Sands INC | R6Ohio-west Virginia Excavating CO |
|---|---|---|---|---|---|---|---|
| 659E00100 SOIL ANALYSIS TEST | 4 EACH | $300 | $120 | $75.00 | $47.00 | $100 | $115 |
| 659E14000 REPAIR SEEDING AND MULCHING | 615 SY | $2.00 | $1.20 | $1.00 | $0.10 | $1.00 | $1.15 |
| 659E15000 INTER-SEEDING | 615 SY | $2.00 | $1.20 | $1.00 | $0.01 | $1.00 | $1.15 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1.00 |
| $29.00 |
| $56.00 |
| 8% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 225 CY | $220 | $318 | $305 | $263 | $325 | $266 | 8% |
| 203E10000 EXCAVATION | 2,602 CY | $19.00 | $27.75 | $28.00 | $39.37 | $28.00 | $16.44 | 8% |
| 304E20000 AGGREGATE BASE | 616 CY | $65.00 | $94.63 | $123 | $105 | $84.00 | $85.60 | 6% |
| 832E30000 EROSION CONTROL | 30,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 5% |
| 659E00300 TOPSOIL | 1,024 CY | $25.00 | $15.49 | $28.00 | $15.03 | $59.00 | $64.60 | 4% |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 12,290 SY | $2.00 | $1.20 | $1.30 | $0.75 | $1.00 | $1.15 | 4% |
| 203E20000 EMBANKMENT | 541 CY | $38.00 | $26.14 | $20.50 | $32.50 | $35.00 | $57.80 | 3% |
| 204E10000 SUBGRADE COMPACTION | 6,467 SY | $2.00 | $0.81 | $1.00 | $4.50 | $3.00 | $0.60 | 2% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 120 CY | $100 | $107 | $123 | $108 | $188 | $137 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $20,000 | $24,000 | $19,640 | $20,000 | $33,063 | 2% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 300 CY | $25.00 | $128 | $110 | $125 | $119 | $132 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,000 | $8,558 | $10,800 | $8,000 | $4,870 | $10,363 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $4,828 | $8,100 | $45,200 | $5,000 | $18,405 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 388 GAL | $12.00 | $10.80 | $4.35 | $4.25 | $3.25 | $5.75 | 1% |
| 670E00500 SLOPE EROSION PROTECTION | 1,833 SY | $2.50 | $3.00 | $2.60 | $1.35 | $2.50 | $2.90 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $3,500 | $2,700 | $8,800 | $4,000 | $3,850 | $2,585 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $6,720 | $9,500 | $15,000 | $3,500 | $13,202 | 1% |
| 659E20000 COMMERCIAL FERTILIZER | 1.11 TON | $1,000 | $1,680 | $1,680 | $905 | $1,400 | $1,607 |
| 659E31000 LIME | 2.54 ACRE | $1,000 | $120 | $81.00 | $154 | $100 | $131 |
| 659E35000 WATER | 66 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $2.50 | $1.15 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,000 | $3,000 | $1,780 | $2,500 | $1,200 | $3,273 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,000 | $6,120 | $4,925 | $2,000 | $4,200 | $5,855 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $1,500 | $3,600 | $9,200 | $2,200 | $6,100 | $6,442 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 24 FT | $20.00 | $48.00 | $43.25 | $15.00 | $19.50 | $46.00 |
| 630E80100 SIGN, FLAT SHEET | 4.5 SF | $35.00 | $180 | $162 | $30.00 | $26.00 | $172 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $100 | $1,200 | $1,080 | $20.00 | $27.00 | $1,150 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 607E98000 FENCE, MISC.: BIKEWAY RAILING (PER ODOT SCD RM-5.2 | 5,050 FT | $38 | $192k | 30% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (314 CY | $220 | $69k | 11% |
| 601E21900 SPECIAL - GEOCELL, SLOPE PROTECTION, GEOWEB GW30V6 | 2,640 SY | $20 | $53k | 8% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 225 CY | $220 | $50k | 8% |
| 203E10000 EXCAVATION | 2,602 CY | $19 | $49k | 8% |
| 304E20000 AGGREGATE BASE | 616 CY | $65 | $40k | 6% |
| 832E30000 EROSION CONTROL | 30,000 EACH | $1 | $30k | 5% |
| 659E00300 TOPSOIL | 1,024 CY | $25 | $26k | 4% |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 12,290 SY | $2 | $25k | 4% |
| 203E20000 EMBANKMENT | 541 CY | $38 | $21k | 3% |