DAR-SR 571-13.65
DAR County · est $0.8M
Bid dateThursday, February 9—
DAR County · est $0.8M
Bid form · ODOT
| Item | Qty | Unit price |
|---|
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 6 more items below.
| Item | Quantity | R1Strawser Construction INC | R2American Pavements INC | % of bid |
|---|---|---|---|---|
| 421E10010 MICROSURFACING, SURFACE COURSE | 163,361 SY | $2.72 | $4.25 | 52% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 500 SY | $190 | $297 | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $67,332 | $99,250 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $60,444 | $39,860 | 7% |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 33.69 MILE | $1,750 | $1,439 | 7% |
| 621E00100 RPM | 772 EACH | $45.00 | $45.00 | 4% |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 22.46 MILE | $900 | $825 | 2% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 772 EACH | $25.00 | $35.00 | 2% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 22.46 MILE | $785 | $882 | 2% |
| 614E12460 WORK ZONE MARKING SIGN | 90 EACH | $110 | $110 | 1% |
| 642E00300 CENTER LINE, TYPE 1 | 11.23 MILE | $875 | $882 | 1% |
| 103E06000 PREMIUM FOR CONTRACT PERFORMANCE BOND, PAYMENT BON | 1 LS | $4,500 | $9,500 | 1% |
| 646E10400 STOP LINE | 114 FT | $12.00 | $14.80 | 0% |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 228 FT | $4.25 | $3.00 | 0% |
| 644E30000 REMOVAL OF PAVEMENT MARKING STOP LINE | 114 FT | $5.00 | $4.00 | 0% |
| 614E27250 WORK ZONE CROSSWALK LINE, CLASS III, 12", 642 PAIN | 128 FT | $4.25 | $2.50 | 0% |
| 644E30020 REMOVAL OF PAVEMENT MARKING | 5 EACH | $100 | $120 | 0% |
| 646E98000 PAVEMENT MARKING, MISC.: "XING" | 2 EACH | $205 | $250 | 0% |
| 646E10510 CROSSWALK LINE, 12" | 64 FT | $6.25 | $8.90 | 0% |
| 644E30000 REMOVAL OF PAVEMENT MARKING CHANNELIZING LINE | 165 FT | $2.00 | $1.00 | 0% |
| Item | Quantity | R1Strawser Construction INC | R2American Pavements INC |
|---|---|---|---|
| 644E30000 REMOVAL OF PAVEMENT MARKING CROSSWALK LINE | 64 FT | $5.00 | $2.00 |
| 646E10300 CHANNELIZING LINE, 8" | 165 FT | $1.75 | $3.00 |
| 646E20300 LANE ARROW | 1 EACH | $175 | $150 |
| 646E20600 BIKE LANE SYMBOL MARKING | 2 EACH | $155 | $300 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 330 FT | $0.30 | $0.90 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 2 EACH | $60.00 | $80.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| Extended |
|---|
| % |
|---|
| 421E10010 MICROSURFACING, SURFACE COURSE | 163,361 SY | $2.72 | $444k | 52% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 500 SY | $190 | $95k | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $67,332 | $67k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $60,444 | $60k | 7% |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 33.69 MILE | $1,750 | $59k | 7% |
| 621E00100 RPM | 772 EACH | $45 | $35k | 4% |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 22.46 MILE | $900 | $20k | 2% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 772 EACH | $25 | $19k | 2% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 22.46 MILE | $785 | $18k | 2% |
| 614E12460 WORK ZONE MARKING SIGN | 90 EACH | $110 | $10k | 1% |