BUT-US 27-00.80
BUT County · est $2.3M
Bid dateThursday, March 30—
BUT County · est $2.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 86 more items below.
| Item | Quantity | R1John R Jurgensen Company | R2Prus Construction Company | R3Sunesis Construction CO | R4Becdir Construction Company | R5Complete General Construction Company | R6Eagle Bridge CO | % of bid |
|---|---|---|---|---|---|---|---|---|
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1,018 CY | $295 | $320 | $304 | $310 | $295 | $293 | 16% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $232,369 | $250,000 | $406,049 | $350,000 | $495,000 | $400,000 | 12% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 17,150 SF | $12.50 | $13.50 |
| Item | Quantity | R1John R Jurgensen Company | R2Prus Construction Company | R3Sunesis Construction CO | R4Becdir Construction Company | R5Complete General Construction Company | R6Eagle Bridge CO |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,519 | $4,500 | $1,027 | $5,000 | $15,000 | $2,500 |
| 202E23000 PAVEMENT REMOVED | 223 SY | $41.47 | $44.00 | $71.52 | $67.00 | $25.00 | $110 |
| 202E30600 CONCRETE MEDIAN REMOVED | 496 SY | $34.87 | $27.00 | $43.13 | $36.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $12.58 |
| $10.50 |
| $12.50 |
| $12.50 |
| 11% |
| 516E11210 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 185 FT | $910 | $750 | $549 | $970 | $950 | $950 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,157 | $80,000 | $44,507 | $180,000 | $100,000 | $264,000 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $125,102 | $190,000 | $100,000 | $100,000 | 5% |
| 517E76300 RAILING, MISC.:CONCRETE RAILING WITH ASHLAR STONE | 841 FT | $110 | $325 | $314 | $350 | $350 | $360 | 5% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,966 FT | $27.58 | $17.50 | $16.61 | $17.50 | $16.50 | $20.03 | 4% |
| 513E21500 REPLACEMENT OF DETERIORATED END CROSSFRAMES | 5,396 LB | $13.33 | $4.00 | $38.06 | $4.60 | $8.00 | $4.75 | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 186 CY | $370 | $400 | $382 | $388 | $370 | $300 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 17,150 SF | $4.00 | $4.30 | $4.03 | $2.50 | $4.00 | $4.00 | 4% |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 20 EACH | $3,024 | $3,150 | $3,382 | $2,350 | $3,000 | $3,250 | 3% |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 2,144 EACH | $25.00 | $23.00 | $47.50 | $13.50 | $25.00 | $25.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 23,595 SY | $2.25 | $2.45 | $2.32 | $2.40 | $2.25 | $1.80 | 3% |
| 630E72320 OVERHEAD SIGN SUPPORT, TYPE TC-12.31, DESIGN 6 | 2 EACH | $23,500 | $26,000 | $24,210 | $25,000 | $24,050 | $23,500 | 2% |
| 622E10160 CONCRETE BARRIER, SINGLE SLOPE, TYPE D | 237 FT | $195 | $210 | $111 | $122 | $175 | $140 | 2% |
| 606E60028 IMPACT ATTENUATOR, TYPE 2 (BIDIRECTIONAL) (35mph, | 2 EACH | $22,500 | $29,700 | $25,884 | $60,000 | $30,000 | $27,000 | 2% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 13,215 LB | $3.00 | $2.00 | $2.83 | $2.35 | $2.50 | $2.25 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 17,150 SF | $2.00 | $2.15 | $2.01 | $2.50 | $2.00 | $2.00 | 2% |
| 509E40000 REINFORCING STEEL, MISC.:GALVANIZED REBAR | 7,369 LB | $4.00 | $2.15 | $3.60 | $2.85 | $3.00 | $3.00 | 2% |
| $50.00 |
| $45.00 |
| 202E38000 GUARDRAIL REMOVED | 1,588 FT | $2.50 | $5.40 | $5.03 | $2.65 | $5.00 | $2.50 |
| 202E42001 ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER PLAN | 8 EACH | $350 | $135 | $629 | $365 | $125 | $700 |
| 202E42206 ANCHOR ASSEMBLY REMOVED | 2 EACH | $125 | $135 | $629 | $130 | $125 | $125 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $125 | $108 | $510 | $130 | $100 | $125 |
| 202E47800 IMPACT ATTENUATOR REMOVED | 2 EACH | $250 | $162 | $151 | $265 | $150 | $250 |
| 606E15050 GUARDRAIL, TYPE MGS | 350 FT | $21.50 | $27.00 | $32.53 | $22.60 | $25.00 | $21.50 |
| 606E15550 GUARDRAIL, BARRIER DESIGN, TYPE MGS | 75 FT | $38.50 | $43.20 | $40.27 | $40.50 | $40.00 | $38.50 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,650 | $2,916 | $2,718 | $2,800 | $2,700 | $2,650 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350) | 2 EACH | $2,600 | $2,916 | $2,718 | $2,750 | $2,700 | $2,600 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 6 EACH | $2,550 | $2,808 | $2,617 | $2,700 | $2,600 | $2,550 |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 2 EACH | $5,250 | $5,076 | $4,731 | $5,500 | $4,700 | $5,250 |
| 609E24510 CURB, TYPE 4-C | 111 FT | $49.96 | $70.00 | $62.34 | $52.50 | $55.00 | $50.00 |
| 622E10100 CONCRETE BARRIER, SINGLE SLOPE, TYPE B1 | 130 FT | $185 | $600 | $438 | $460 | $375 | $525 |
| 622E24851 CONCRETE BARRIER END SECTION, TYPE B1. AS PER PLAN | 2 EACH | $9,000 | $18,700 | $8,053 | $7,875 | $15,000 | $8,500 |
| 622E25000 CONCRETE BARRIER END SECTION, TYPE D | 2 EACH | $4,500 | $9,800 | $7,549 | $3,675 | $5,000 | $4,000 |
| 622E25050 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 2 EACH | $4,250 | $1,050 | $3,523 | $3,150 | $8,500 | $4,000 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 , BIDIRECTIONAL | 12 EACH | $13.00 | $16.20 | $15.10 | $12.50 | $15.00 | $20.00 |
| 659E00300 TOPSOIL | 33 CY | $5.00 | $195 | $101 | $80.00 | $42.50 | $120 |
| 659E10000 SEEDING AND MULCHING | 300 SY | $6.50 | $6.50 | $7.98 | $6.00 | $6.00 | $12.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $2,500 | $1,620 | $2,517 | $1,925 | $1,500 | $1,500 |
| 659E31000 LIME | 0.06 ACRE | $200 | $540 | $201 | $800 | $500 | $100 |
| 659E35000 WATER | 2 MGAL | $100 | $108 | $101 | $10.00 | $100 | $25.00 |
| 690E98400 SPECIAL - SPECIAL MISC.: WORK INVOLVING ASBESTOS C | 1 LS | $116 | $2,000 | $252 | $250 | $3,000 | $200 |
| 832E30000 EROSION CONTROL | 7,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 204E10000 SUBGRADE COMPACTION | 831 SY | $10.31 | $3.00 | $6.50 | $5.00 | $6.00 | $12.00 |
| 304E20000 AGGREGATE BASE | 136 CY | $97.38 | $150 | $112 | $134 | $75.00 | $160 |
| 407E20000 NON-TRACKING TACK COAT | 1,828 GAL | $10.00 | $10.80 | $10.32 | $10.50 | $10.00 | $1.00 |
| 442E22400 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 40 CY | $655 | $710 | $676 | $688 | $655 | $450 |
| 621E00100 RPM | 22 EACH | $175 | $185 | $179 | $185 | $175 | $175 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 22 EACH | $39.19 | $19.00 | $45.70 | $60.00 | $25.00 | $20.00 |
| 625E32000 GROUND ROD | 2 EACH | $400 | $362 | $315 | $420 | $313 | $422 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 2 EACH | $170 | $145 | $136 | $179 | $135 | $170 |
| 630E80100 SIGN, FLAT SHEET | 10 SF | $28.50 | $37.00 | $34.73 | $30.00 | $34.50 | $28.50 |
| 630E84010 CONCRETE BARRIER MEDIAN OVERHEAD SIGN SUPPORT FOUN | 2 EACH | $11,500 | $10,000 | $9,261 | $7,875 | $9,200 | $7,500 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $25.00 | $21.60 | $20.14 | $26.00 | $20.00 | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $25.00 | $37.80 | $35.24 | $26.00 | $35.00 | $25.00 |
| 630E86310 REMOVAL OF STRUCTURE MOUNTED SIGN AND DISPOSAL | 1 EACH | $400 | $216 | $201 | $420 | $200 | $400 |
| 630E86320 REMOVAL OF STRUCTURE MOUNTED SIGN AND REERECTION | 2 EACH | $1,200 | $2,900 | $2,718 | $1,260 | $2,700 | $1,200 |
| 630E97700 SIGNING, MISC.: REMOVAL OF STRUCTURE MOUNTED SIGN | 3 EACH | $1,000 | $270 | $252 | $1,050 | $250 | $1,000 |
| 644E00100 EDGE LINE, 4" | 0.32 MILE | $6,065 | $6,550 | $6,105 | $3,700 | $6,065 | $6,065 |
| 644E00104 EDGE LINE, 6" | 2.65 MILE | $5,215 | $5,630 | $5,250 | $5,040 | $5,215 | $5,215 |
| 644E00204 LANE LINE, 6" | 1.4 MILE | $2,355 | $2,550 | $2,371 | $2,625 | $2,355 | $2,355 |
| 644E00400 CHANNELIZING LINE, 8" | 520 FT | $1.25 | $1.35 | $1.26 | $1.85 | $1.25 | $1.25 |
| 644E00404 CHANNELIZING LINE, 12" | 410 FT | $3.00 | $3.25 | $3.02 | $2.65 | $3.00 | $3.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 450 FT | $8.65 | $9.35 | $8.71 | $8.40 | $8.65 | $8.65 |
| 644E01300 LANE ARROW | 4 EACH | $125 | $135 | $126 | $209 | $125 | $125 |
| 646E10010 EDGE LINE, 6" | 0.14 MILE | $36,090 | $38,975 | $36,330 | $49,500 | $36,090 | $36,090 |
| 646E10110 LANE LINE, 6" | 0.04 MILE | $12,105 | $13,075 | $12,186 | $25,000 | $12,105 | $12,105 |
| 411E10001 STABILIZED CRUSHED AGGREGATE, AS PER PLAN | 68 CY | $152 | $150 | $285 | $200 | $115 | $128 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 200 HOUR | $116 | $90.00 | $101 | $70.00 | $80.00 | $110 |
| 614E11630 INCREASED BARRIER DELINEATION | 829 FT | $3.50 | $3.75 | $3.52 | $3.70 | $3.50 | $3.50 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,742 | $2,500 | $2,265 | $2,450 | $2,300 | $2,300 |
| 614E12801 WORK ZONE RAISED PAVEMENT MARKER, AS PER PLAN | 780 EACH | $6.00 | $6.50 | $6.04 | $26.50 | $6.00 | $32.50 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE-WAY | 53 EACH | $25.77 | $14.00 | $44.34 | $13.50 | $13.00 | $13.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 53 EACH | $25.77 | $21.00 | $19.13 | $20.00 | $19.00 | $19.00 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 1.47 MILE | $610 | $650 | $614 | $640 | $610 | $610 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.4 MILE | $1,495 | $1,600 | $1,505 | $1,570 | $1,495 | $1,495 |
| 614E22056 WORK ZONE EDGE LINE, CLASS I, 6", 807 PAINT | 3.88 MILE | $3,650 | $3,950 | $3,674 | $3,835 | $3,650 | $3,650 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 2.72 MILE | $1,320 | $1,425 | $1,329 | $1,385 | $1,320 | $1,320 |
| 614E23010 WORK ZONE CHANNELIZING LINE, CLASS I, 12" | 644 FT | $1.30 | $1.40 | $1.31 | $1.40 | $1.30 | $1.30 |
| 614E23110 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 807 PAI | 631 FT | $1.85 | $2.00 | $1.86 | $1.95 | $1.85 | $1.85 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 410 FT | $1.20 | $1.30 | $1.21 | $1.25 | $1.20 | $1.20 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 175 FT | $1.00 | $1.08 | $1.01 | $1.05 | $1.00 | $1.00 |
| 614E24102 WORK ZONE DOTTED LINE, CLASS I, 6", 807 PAINT | 3,180 FT | $1.40 | $1.50 | $1.41 | $1.50 | $1.40 | $1.40 |
| 614E25620 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS III, 642 | 200 FT | $3.00 | $3.24 | $3.02 | $3.15 | $3.00 | $3.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 6 FT | $6.60 | $7.10 | $6.64 | $7.00 | $6.60 | $6.60 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 12 SNMT | $660 | $918 | $856 | $740 | $850 | $850 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 100 LB | $3.00 | $3.50 | $4.90 | $2.00 | $4.75 | $1.75 |
| 509E30020 NO. 4 GFRP DEFORMED BARS | 12,785 FT | $2.25 | $1.25 | $1.88 | $2.00 | $2.00 | $1.60 |
| 512E10101 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE), AS | 1,285 SY | $21.50 | $22.75 | $23.66 | $23.00 | $22.75 | $22.75 |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 1,535 SY | $14.00 | $18.00 | $13.94 | $13.50 | $13.50 | $13.50 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 17,150 SF | $1.00 | $1.10 | $1.01 | $2.50 | $1.00 | $1.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 30 MNHR | $150 | $162 | $151 | $160 | $150 | $150 |
| 514E10000 FINAL INSPECTION REPAIR | 12 EACH | $200 | $216 | $201 | $220 | $200 | $200 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $20,000 | $12,500 | $23,797 | $40,000 | $30,000 | $50,000 |
| 518E12700 SCUPPER, VERTICAL EXTENSION | 16 EACH | $1,070 | $650 | $1,119 | $830 | $1,000 | $1,100 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 142 SF | $150 | $250 | $359 | $190 | $200 | $265 |
| 530E00200 SPECIAL - STRUCTURES (CONSULTANT FOR CONCRETE QUAL | 1 LS | $13,760 | $21,000 | $11,742 | $13,500 | $14,300 | $10,000 |
| 625E25500 CONDUIT, 3", 725.04 | 841 FT | $24.50 | $26.50 | $19.44 | $25.50 | $85.00 | $38.00 |
| 511E53014 CLASS QC3 CONCRETE, MISC.: SUPERSTRUCTURE CONCRETE | 23 CY | $1,200 | $2,850 | $2,446 | $750 | $4,000 | $4,000 |
| 511E53014 CLASS QC3 CONCRETE, MISC.:SUBSTRUCTURE CONCRETE, A | 15 CY | $850 | $4,000 | $3,394 | $2,750 | $6,000 | $4,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $21,024 | $23,000 | $0.01 | $60,000 | $30,000 | $65,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $20,693 | $11,000 | $12,080 | $12,500 | $10,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1,018 CY | $295 | $300k | 12% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $232,369 | $232k | 9% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 17,150 SF | $12.5 | $214k | 8% |
| 516E11210 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 185 FT | $909.94 | $168k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,157 | $100k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 517E76300 RAILING, MISC.:CONCRETE RAILING WITH ASHLAR STONE | 841 FT | $110 | $93k | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,966 FT | $27.58 | $82k | 3% |
| 513E21500 REPLACEMENT OF DETERIORATED END CROSSFRAMES | 5,396 LB | $13.33 | $72k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 186 CY | $370 | $69k | 3% |