| Item | Quantity | R1D G M INC | R2Axis Civil Construction LLC | R3John R Jurgensen Company | % of bid |
|---|---|---|---|---|---|
| 611E94946 9' X 9' CONDUIT, TYPE A, 706.05 | 99 FT | $2,020 | $1,900 | $1,387 | 27% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 41,782 LB | $1.50 | $2.00 | $1.49 | 8% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 95 CY | $600 | $1,055 | $881 | 8% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 135 CY | $400 | $600 | $610 | 7% |
| 203E20000 EMBANKMENT | 3,002 CY | $17.00 | $25.00 | $21.55 | 7% |
| 601E34401 ROCK CHANNEL PROTECTION, WITH GROUT, AS PER PLAN | 232 CY | $150 | $275 | $216 | 5% |
| 611E21400 48" CONDUIT, TYPE D, 706.02 | 70 FT | $471 | $610 |
| Item | Quantity | R1D G M INC | R2Axis Civil Construction LLC | R3John R Jurgensen Company |
|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $500 | $750 | $706 |
| 202E23000 PAVEMENT REMOVED | 336 SY | $10.00 | $13.00 | $11.13 |
| 202E38000 GUARDRAIL REMOVED | 828 FT | $1.00 | $6.00 | $6.00 |
| 202E53100 MAILBOX REMOVED | 1 EACH | $100 | $300 | $491 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 36" | 93 FT | $90.00 | $95.00 | $106 |
| 202E98000 REMOVAL MISC.: CONCRETE SLAB | 1 LS | $500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $403 |
| 4% |
| 832E30000 EROSION CONTROL | 30,000 EACH | $1.00 | $1.00 | $1.00 | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 93 CY | $300 | $300 | $333 | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 83 CY | $335 | $400 | $680 | 4% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $27,500 | $32,000 | $37,461 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $25,000 | $17,566 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $20,000 | $7,000 | $6,016 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $40,000 | $40,000 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $17,500 | $35,000 | $48,176 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $16,000 | $15,125 | $15,125 | 2% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $14,000 | $13,000 | $55,862 | 2% |
| 503E31100 ROCK EXCAVATION | 184 CY | $60.00 | $115 | $100 | 1% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 122 CY | $90.00 | $130 | $74.65 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,000 | $8,000 | $5,372 | 1% |
| $3,500 |
| $7,664 |
| 203E10000 EXCAVATION | 582 CY | $15.00 | $25.00 | $38.77 |
| 204E10000 SUBGRADE COMPACTION | 515 SY | $5.00 | $3.00 | $3.75 |
| 204E45000 PROOF ROLLING | 1 HOUR | $70.00 | $250 | $231 |
| 623E40500 REFERENCE MONUMENT | 4 EACH | $400 | $600 | $788 |
| 690E50000 SPECIAL - MAILBOX SUPPORT | 1 EACH | $300 | $500 | $557 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $8,000 | $14,000 | $18,000 |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 30 CY | $90.00 | $100 | $347 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 10 CY | $60.00 | $125 | $327 |
| 659E00300 TOPSOIL | 70 CY | $20.00 | $50.00 | $5.00 |
| 659E10000 SEEDING AND MULCHING | 4,133 SY | $1.75 | $1.15 | $0.92 |
| 659E14000 REPAIR SEEDING AND MULCHING | 207 SY | $0.05 | $1.15 | $0.78 |
| 659E20000 COMMERCIAL FERTILIZER | 0.56 TON | $1,000 | $1,400 | $893 |
| 659E31000 LIME | 0.85 ACRE | $100 | $100 | $153 |
| 659E35000 WATER | 22 MGAL | $1.00 | $1.00 | $1.00 |
| 660E25000 SODDING STAKED | 240 SY | $12.00 | $15.00 | $18.34 |
| 670E00500 SLOPE EROSION PROTECTION | 633 SY | $2.50 | $2.50 | $1.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $1,475 | $1,475 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $8,000 | $4,800 | $3,450 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $8,500 | $8,500 | $8,067 |
| 836E10020 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 363 SY | $6.00 | $6.00 | $5.05 |
| 602E20000 CONCRETE MASONRY | 2.2 CY | $1,600 | $2,400 | $2,183 |
| 605E31100 AGGREGATE DRAINS | 118 FT | $20.00 | $18.00 | $46.94 |
| 611E01400 6" CONDUIT, TYPE E | 50 FT | $6.00 | $22.00 | $43.83 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $6.00 | $22.00 | $43.83 |
| 611E01800 8" CONDUIT, TYPE B | 50 FT | $8.00 | $27.00 | $55.78 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 46 FT | $10.00 | $8.00 | $3.43 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, VARIABLE DEPTH | 433 SY | $15.00 | $12.00 | $34.50 |
| 304E20000 AGGREGATE BASE | 63 CY | $80.00 | $115 | $83.80 |
| 407E10000 TACK COAT | 237 GAL | $3.50 | $5.00 | $15.00 |
| 621E00100 RPM | 7 EACH | $330 | $351 | $425 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 7 EACH | $1.00 | $45.00 | $21.12 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 55.3 FT | $20.00 | $35.00 | $25.00 |
| 630E80100 SIGN, FLAT SHEET | 9 SF | $20.00 | $45.50 | $39.75 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH | $20.00 | $10.00 | $20.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $50.00 | $65.00 | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $15.00 | $15.00 | $30.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.18 MILE | $6,000 | $8,960 | $4,600 |
| 642E00300 CENTER LINE, TYPE 1 | 0.09 MILE | $12,000 | $17,940 | $4,600 |
| 642E01000 RAILROAD SYMBOL MARKING, TYPE 1 | 1 EACH | $850 | $450 | $300 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 40 CY | $170 | $240 | $388 |
| 304E20000 AGGREGATE BASE | 40 CY | $50.00 | $64.00 | $217 |
| 407E10000 TACK COAT | 26 GAL | $3.50 | $4.00 | $5.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 20 CY | $200 | $375 | $605 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 8 HOUR | $40.00 | $75.00 | $99.84 |
| 616E10000 WATER | 7 MGAL | $1.00 | $1.00 | $228 |
| 642E00300 CENTER LINE, TYPE 1 | 0.1 MILE | $6,500 | $300 | $10,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $5,000 | $18,000 | $29,261 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 5 CY | $1,000 | $2,500 | $1,839 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 183 SY | $30.00 | $35.00 | $26.50 |
| 512E33000 TYPE 2 WATERPROOFING | 368 SY | $16.00 | $20.00 | $24.50 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 89 SF | $15.00 | $9.00 | $11.59 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 88 CY | $90.00 | $120 | $164 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 151 FT | $20.00 | $7.00 | $10.58 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 66 FT | $20.00 | $7.00 | $35.25 |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $750 | $1,500 | $1,831 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E94946 9' X 9' CONDUIT, TYPE A, 706.05 | 99 FT | $2,020 | $200k | 22% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 41,782 LB | $1.5 | $63k | 7% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 95 CY | $600 | $57k | 6% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 135 CY | $400 | $54k | 6% |
| 203E20000 EMBANKMENT | 3,002 CY | $17 | $51k | 6% |
| 601E34401 ROCK CHANNEL PROTECTION, WITH GROUT, AS PER PLAN | 232 CY | $150 | $35k | 4% |
| 611E21400 48" CONDUIT, TYPE D, 706.02 | 70 FT | $471 | $33k | 4% |
| 832E30000 EROSION CONTROL | 30,000 EACH | $1 | $30k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 93 CY | $300 | $28k | 3% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 83 CY | $335 | $28k | 3% |