NOB-IR 77-11.97
NOB County · est $0.8M
Bid dateThursday, July 13—
NOB County · est $0.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 17 more items below.
| Item | Quantity | R1Daniel R Schmoldt Enterprises INC | R2International Excavating Of Ohio, LLC | R3Ohio-west Virginia Excavating CO | R4Turn-key Tunneling INC | R5Stanley Miller Construction Company | % of bid |
|---|---|---|---|---|---|---|---|
| 611E96600 CONDUIT, BORED OR JACKED: 42" CONDUIT, TYPE B | 318 FT | $1,150 | $820 | $895 | $1,045 | $677 | 43% |
| 611E96600 CONDUIT, BORED OR JACKED: 36" CONDUIT, TYPE B | 226 FT | $950 | $725 | $855 | $910 | $575 | 25% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 828 FT | $38.00 | $65.00 | $30.00 | $41.00 | $38.00 | 4% |
| 611E98271 CATCH BASIN, NO. 4A, AS PER PLAN | 2 EACH | $15,125 | $3,750 | $22,000 | $13,000 | $11,611 | 4% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 100 CY | $215 | $95.00 | $220 | $200 | $235 | 3% |
| 624E10000 |
| Item | Quantity | R1Daniel R Schmoldt Enterprises INC | R2International Excavating Of Ohio, LLC | R3Ohio-west Virginia Excavating CO | R4Turn-key Tunneling INC | R5Stanley Miller Construction Company |
|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 4 EACH | $1,000 | $7,000 | $500 | $2,050 | $1,250 |
| 202E32700 GUTTER REMOVED | 35 SY | $66.00 | $25.00 | $60.00 | $105 | $138 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 22 FT | $33.00 | $50.00 | $110 | $280 | $168 |
| 202E58100 CATCH BASIN REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $20,000 |
| $15,000 |
| $38,200 |
| $17,500 |
| $56,778 |
| 2% |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $4,950 | $400 | $3,000 | $3,625 | $5,000 | 2% |
| 643E00204 LANE LINE, 6" | 1.38 MILE | $13,504 | $10,000 | $12,500 | $2,025 | $13,640 | 2% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 36" CMP | 318 FT | $51.05 | $225 | $105 | $112 | $271 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $12,500 | $70,000 | $15,000 | $33,000 | 2% |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 1.38 MILE | $10,351 | $12,000 | $9,500 | $9,785 | $10,456 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,911 | $15,000 | $16,000 | $5,000 | $15,000 | 2% |
| 659E10000 SEEDING AND MULCHING | 4,250 SY | $2.75 | $5.00 | $1.65 | $5.00 | $2.00 | 1% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 71 CY | $130 | $110 | $210 | $200 | $230 | 1% |
| 602E20000 CONCRETE MASONRY | 3.36 CY | $2,500 | $5,500 | $2,100 | $3,825 | $3,075 | 1% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $8,000 | $29,000 | $13,000 | $15,000 | $58,000 | 1% |
| 607E15000 FENCE, TYPE 47 | 240 FT | $32.40 | $58.00 | $34.00 | $21.00 | $35.00 | 1% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 27" CMP | 223 FT | $28.72 | $175 | $78.00 | $58.00 | $171 | 1% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $25,000 | $5,000 | $32,500 | $46,447 | 1% |
| 2 EACH |
| $1,000 |
| $550 |
| $1,000 |
| $4,700 |
| $1,998 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 15" CMP | 32 FT | $23.44 | $100 | $200 | $230 | $190 |
| 202E75000 FENCE REMOVED | 230 FT | $5.00 | $15.00 | $5.00 | $37.00 | $22.00 |
| 203E10000 EXCAVATION | 35 CY | $45.00 | $55.00 | $100 | $78.00 | $70.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.39 TON | $1,650 | $12,000 | $1,500 | $1,200 | $800 |
| 659E31000 LIME | 0.88 ACRE | $500 | $10,000 | $100 | $800 | $150 |
| 659E35000 WATER | 12 MGAL | $2.00 | $25.00 | $1.00 | $1.00 | $1.00 |
| 611E01500 6" CONDUIT, TYPE F | 40 FT | $28.00 | $50.00 | $70.00 | $210 | $86.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $125 | $450 | $750 | $150 | $110 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 1 EACH | $500 | $375 | $1,050 | $200 | $167 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 39 EACH | $27.50 | $200 | $25.00 | $38.00 | $30.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 39 EACH | $38.50 | $220 | $35.00 | $38.00 | $45.00 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 3,360 FT | $0.61 | $2.00 | $0.60 | $1.00 | $0.64 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,500 | $7,500 | $20,000 | $10,000 | $30,056 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E96600 CONDUIT, BORED OR JACKED: 42" CONDUIT, TYPE B | 318 FT | $1,150 | $366k | 42% |
| 611E96600 CONDUIT, BORED OR JACKED: 36" CONDUIT, TYPE B | 226 FT | $950 | $215k | 25% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 828 FT | $38 | $31k | 4% |
| 611E98271 CATCH BASIN, NO. 4A, AS PER PLAN | 2 EACH | $15,125 | $30k | 3% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 100 CY | $215 | $22k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $4,950 | $20k | 2% |
| 643E00204 LANE LINE, 6" | 1.38 MILE | $13,504 | $19k | 2% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 36" CMP | 318 FT | $51.05 | $16k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $15k | 2% |