HUR-US 224-00.00
HUR County · est $8.4M
Bid dateThursday, September 28—
HUR County · est $8.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 74 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Erie Blacktop INC | R3Kokosing Construction Company INC | R4Gerken Paving INC | % of bid |
|---|---|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 14,321 CY | $215 | $222 | $235 | $212 | 38% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 3,632 CY | $170 | $163 | $190 | $165 | 8% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)LONGITUDINAL | 2,618 CY | $220 | $190 | $240 | $225 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $534,700 | $495,000 | $957,700 | $372,000 | 7% |
| 203E10000 EXCAVATION | 9,161 CY | $51.00 | $41.75 | $42.50 | $34.58 | 6% |
| 304E20000 AGGREGATE BASE | 5,635 CY | $75.00 | $63.00 | $60.00 | $78.00 |
| Item | Quantity | R1Shelly & Sands INC | R2Erie Blacktop INC | R3Kokosing Construction Company INC | R4Gerken Paving INC |
|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 1,670 SF | $4.00 | $4.20 | $4.00 | $4.00 |
| 202E32000 CURB REMOVED | 97 FT | $14.75 | $15.50 | $14.75 | $14.75 |
| 203E20000 EMBANKMENT | 1,005 CY | $40.00 | $63.00 | $60.00 | $162 |
| 203E20001 EMBANKMENT, AS PER PLAN | 16 CY | $89.00 | $93.45 | $89.00 | $89.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 5% |
| 617E10100 COMPACTED AGGREGATE | 9,226 CY | $45.00 | $65.00 | $45.00 | $55.05 | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(1.50") | 314,264 SY | $1.25 | $1.85 | $1.40 | $1.92 | 5% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE(4'-0" | 36,901 SY | $9.50 | $9.75 | $9.25 | $9.25 | 4% |
| 202E23000 PAVEMENT REMOVED | 18,860 SY | $12.50 | $15.00 | $3.00 | $27.62 | 3% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 1,028 CY | $200 | $188 | $255 | $340 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $200,000 | $200,000 | $450,000 | 2% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)TRANSVERSE | 291 CY | $450 | $380 | $400 | $398 | 2% |
| 253E02000 PAVEMENT REPAIR | 291 CY | $310 | $380 | $270 | $285 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN(0.4 GAL/SY) | 14,515 GAL | $5.00 | $4.85 | $4.50 | $5.50 | 1% |
| 209E60501 LINEAR GRADING, AS PER PLAN | 38.14 MILE | $1,800 | $1,755 | $2,000 | $1,700 | 1% |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 82,904 FT | $0.60 | $2.10 | $1.85 | $2.75 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 38.49 MILE | $1,250 | $1,315 | $1,250 | $1,250 | 1% |
| 407E10000 TACK COAT(0.09 GAL/SY) | 19,636 GAL | $2.25 | $2.50 | $2.70 | $2.50 | 1% |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 32 EACH | $1,350 | $1,420 | $1,350 | $1,350 | 1% |
| 203E20001 EMBANKMENT, AS PER PLAN(CURB RAMPS) (6" AVERAGE DE | 13 CY | $80.00 | $84.00 | $80.00 | $80.00 |
| 204E10000 SUBGRADE COMPACTION | 30,703 SY | $1.00 | $1.10 | $1.00 | $1.10 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 3.5 STA | $56.00 | $58.80 | $56.00 | $56.00 |
| 209E80000 GRADING MAILBOX APPROACHES | 232 EACH | $100 | $260 | $10.00 | $550 |
| 606E35150 BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 4 | 8 EACH | $720 | $760 | $720 | $720 |
| 608E10000 4" CONCRETE WALK | 1,078 SF | $18.00 | $18.90 | $18.00 | $18.00 |
| 608E52000 CURB RAMP | 620 SF | $18.00 | $18.90 | $18.00 | $18.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99155 INLET RECONSTRUCTED TO GRADE, AS PER PLAN | 4 EACH | $2,600 | $2,730 | $2,600 | $2,600 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(VARIABLE THICKN | 93 SY | $50.00 | $8.30 | $1.40 | $2.00 |
| 407E10000 TACK COAT(0.05 GAL/SY) | 1,859 GAL | $2.25 | $2.50 | $2.70 | $2.50 |
| 609E26000 CURB, TYPE 6 | 59 FT | $30.00 | $31.50 | $30.00 | $30.00 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 9.18 MILE | $1,200 | $1,195 | $1,135 | $735 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 16.37 MILE | $1,300 | $880 | $835 | $735 |
| 621E00100 RPM | 1,261 EACH | $30.50 | $32.00 | $30.50 | $30.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,248 EACH | $5.00 | $6.00 | $2.00 | $7.00 |
| 630E89902 REMOVAL OF MISCELLANEOUS TRAFFIC CONTROL ITEM(PEDE | 3 EACH | $2,000 | $630 | $600 | $2,125 |
| 642E00104 EDGE LINE, 6", TYPE 1(WHITE) | 36.75 MILE | $700 | $735 | $700 | $700 |
| 642E00300 CENTER LINE, TYPE 1(TOTAL PAY QUANTITY) | 19.25 MILE | $975 | $1,025 | $975 | $975 |
| 642E40001 SPEED MEASUREMENT MARKING, AS PER PLAN | 1 EACH | $2,000 | $3,685 | $4,600 | $2,000 |
| 644E00400 CHANNELIZING LINE, 8" | 530 FT | $3.00 | $3.15 | $3.00 | $3.00 |
| 644E00500 STOP LINE | 870 FT | $6.50 | $6.85 | $6.50 | $6.50 |
| 644E00620 CROSSWALK LINE, 12" | 1,894 FT | $4.00 | $4.20 | $4.00 | $4.00 |
| 644E00621 CROSSWALK LINE, 12", AS PER PLAN | 178 FT | $7.50 | $7.85 | $7.50 | $7.50 |
| 644E01000 RAILROAD SYMBOL MARKING | 6 EACH | $500 | $525 | $500 | $500 |
| 644E01200 PARKING LOT STALL MARKING | 1,441 FT | $3.00 | $3.15 | $3.00 | $3.00 |
| 644E01300 LANE ARROW | 5 EACH | $95.00 | $100 | $95.00 | $95.00 |
| 646E10010 EDGE LINE, 6"(WHITE) | 0.2 MILE | $15,000 | $15,750 | $15,000 | $15,000 |
| 646E10200 CENTER LINE(TOTAL PAY QUANITITY) | 0.1 MILE | $25,000 | $26,250 | $25,000 | $25,000 |
| 625E31510 PULL BOX REMOVED | 15 EACH | $296 | $210 | $200 | $620 |
| 632E30500 MESSENGER WIRE, MISC.:UNLASH AND RELASH | 412 FT | $5.00 | $5.25 | $5.00 | $12.50 |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 1 EACH | $1,200 | $2,625 | $2,500 | $2,400 |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 4 EACH | $10,600 | $11,075 | $10,550 | $10,820 |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 4 EACH | $10,350 | $10,750 | $10,250 | $10,460 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $80.00 | $89.25 | $100 | $100 |
| 614E12460 WORK ZONE MARKING SIGN(R4-1-24) DO NOT PASS | 22 EACH | $55.00 | $57.75 | $55.00 | $55.00 |
| 614E12460 WORK ZONE MARKING SIGN(R4-2-24) PASS WITH CARE | 22 EACH | $55.00 | $57.75 | $55.00 | $55.00 |
| 614E12460 WORK ZONE MARKING SIGN(W8-H12A-36) NO EDGE LINE | 36 EACH | $55.00 | $57.75 | $55.00 | $55.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $250 | $335 | $125 | $700 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $900 | $945 | $900 | $1,800 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 1,060 FT | $1.25 | $1.35 | $1.25 | $1.25 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 1,740 FT | $4.00 | $4.20 | $2.00 | $4.00 |
| 202E98200 REMOVAL MISC.:JOINT SEALER | 86 FT | $4.62 | $4.85 | $4.62 | $4.62 |
| 516E31000 JOINT SEALER | 86 FT | $19.08 | $20.00 | $19.08 | $19.08 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 89 FT | $112 | $118 | $112 | $112 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 38 SF | $135 | $142 | $135 | $135 |
| 202E98200 REMOVAL MISC.:JOINT SEALER | 98 FT | $4.62 | $4.85 | $4.62 | $4.62 |
| 516E31000 JOINT SEALER | 98 FT | $19.08 | $20.00 | $19.08 | $19.08 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 300 FT | $109 | $114 | $109 | $109 |
| 202E38201 GUARDRAIL REMOVED FOR REUSE, AS PER PLAN | 100 FT | $8.80 | $9.25 | $8.80 | $8.80 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(VARIABLE THICKN | 28 SY | $1.50 | $1.85 | $1.40 | $100 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 93 FT | $19.08 | $20.00 | $19.08 | $19.08 |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1 CY | $210 | $222 | $235 | $2,400 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 100 FT | $110 | $115 | $110 | $110 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 103 FT | $30.20 | $32.00 | $30.20 | $30.20 |
| 202E38201 GUARDRAIL REMOVED FOR REUSE, AS PER PLAN | 100 FT | $8.80 | $9.25 | $8.80 | $8.80 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(VARIABLE THICKN | 8 SY | $1.50 | $1.85 | $1.40 | $100 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 80 FT | $19.08 | $20.00 | $19.08 | $19.08 |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1 CY | $210 | $222 | $235 | $2,400 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 100 FT | $110 | $115 | $110 | $110 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 30 FT | $30.20 | $32.00 | $30.20 | $30.20 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 125 FT | $110 | $115 | $110 | $110 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 81 FT | $19.08 | $20.00 | $19.08 | $19.08 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 101 FT | $110 | $115 | $110 | $110 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 82 FT | $19.08 | $20.00 | $19.08 | $19.08 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 76 FT | $110 | $118 | $112 | $112 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $3,000 | $15,000 | $10,000 | $10,500 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $40,000 | $50,000 | $50,000 | $6,000 |
| 619E16010 FIELD OFFICE, TYPE B | 5 MNTH | $4,500 | $2,785 | $2,600 | $4,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $14,300 | $15,000 | $9,330 | $20,475 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 14,321 CY | $215 | $3.08M | 35% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 3,632 CY | $170 | $617k | 7% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)LONGITUDINAL | 2,618 CY | $220 | $576k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $534,700 | $535k | 6% |
| 203E10000 EXCAVATION | 9,161 CY | $51 | $467k | 5% |
| 304E20000 AGGREGATE BASE | 5,635 CY | $75 | $423k | 5% |
| 617E10100 COMPACTED AGGREGATE | 9,226 CY | $45 | $415k | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(1.50") | 314,264 SY | $1.25 | $393k | 5% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE(4'-0" | 36,901 SY | $9.5 | $351k | 4% |
| 202E23000 PAVEMENT REMOVED | 18,860 SY | $12.5 | $236k | 3% |