CLE-/HAM Culverts FY24
CLE County · est $1.1M
Bid dateThursday, October 26—
CLE County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 32 more items below.
| Item | Quantity | R1Rack & Ballauer Excavating CO INC | R2Axis Civil Construction LLC | R3John R Jurgensen Company | R4Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|
| 899E10000 CURED-IN-PLACE PIPE LINER, 58"x36" CMP ARCH | 152 FT | $1,000 | $1,325 | $667 | $1,200 | 16% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $110,000 | $80,000 | $108,870 | $49,000 | 11% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 60" CMP | 606 FT | $165 | $135 | $297 | $297 | 10% |
| 659E00300 TOPSOIL | 1,354 CY | $65.00 | $35.00 | $126 | $119 | 9% |
| 602E20000 CONCRETE MASONRY | 35.58 CY | $2,100 | $2,500 | $2,126 | $3,500 | 8% |
| 611E58900 87" X 63" CONDUIT, TYPE A, 707.02 Aluminized, 707. | 98 FT | $650 | $1,280 | $1,131 | $1,408 |
| Item | Quantity | R1Rack & Ballauer Excavating CO INC | R2Axis Civil Construction LLC | R3John R Jurgensen Company | R4Sunesis Construction CO |
|---|---|---|---|---|---|
| 202E11004 STRUCTURE REMOVED | 1 EACH | $8,000 | $7,500 | $21,011 | $10,000 |
| 202E20010 HEADWALL REMOVED | 6 EACH | $1,200 | $2,500 | $1,977 | $1,700 |
| 202E23000 PAVEMENT REMOVED | 211 SY | $25.00 | $15.00 | $25.69 | $54.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 140 FT | $43.00 | $120 | $70.00 | $159 |
| 202E42010 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 899E10000 CURED-IN-PLACE PIPE LINER, 50"x31" CMP ARCH | 77 FT | $800 | $1,025 | $748 | $963 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $55,000 | $100,000 | $40,000 | $148,350 | 6% |
| 614E12420 DETOUR SIGNING | 1 LS | $35,000 | $25,000 | $21,510 | $2,300 | 4% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 96" CMP | 162 FT | $190 | $230 | $538 | $216 | 3% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 53 CY | $500 | $750 | $862 | $1,000 | 3% |
| 611E22200 54" CONDUIT, TYPE A, 707.02 Aluminized, 706.02, 70 | 76 FT | $340 | $1,090 | $749 | $1,175 | 3% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 72"x44" CMP ARCH | 56 FT | $445 | $250 | $510 | $241 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $24,000 | $50,000 | $68,427 | $54,500 | 2% |
| 611E20700 48" CONDUIT, TYPE A, 707.02 Aluminized, 706.02, 70 | 82 FT | $270 | $750 | $613 | $774 | 2% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 54 CY | $335 | $450 | $817 | $900 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3" DEPTH | 417 SY | $40.00 | $45.00 | $89.58 | $60.00 | 2% |
| 203E20000 EMBANKMENT | 393 CY | $42.00 | $50.00 | $80.23 | $125 | 2% |
| 203E35141 GRANULAR MATERIAL, TYPE E, AS PER PLAN | 156.5 CY | $105 | $150 | $158 | $164 | 2% |
| 832E30000 EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 1 EACH |
| $160 |
| $250 |
| $350 |
| $350 |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 56 FT | $50.00 | $180 | $146 | $42.00 |
| 203E10000 EXCAVATION | 153 CY | $42.00 | $50.00 | $74.19 | $77.00 |
| 204E10000 SUBGRADE COMPACTION | 231 SY | $17.00 | $4.00 | $5.13 | $20.25 |
| 204E13001 EXCAVATION OF SUBGRADE, AS PER PLAN | 156.5 CY | $52.00 | $50.00 | $139 | $120 |
| 204E50000 GEOTEXTILE FABRIC | 588 SY | $1.00 | $3.50 | $8.36 | $5.75 |
| 209E10000 DITCH CLEANOUT | 160 FT | $85.00 | $80.00 | $62.46 | $65.00 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $500 | $110,000 | $96,331 | $83,880 |
| 606E15050 GUARDRAIL, TYPE MGS | 162.5 FT | $27.60 | $45.00 | $26.50 | $29.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,480 | $1,500 | $1,500 | $1,700 |
| 623E40500 REFERENCE MONUMENT, TYPE A | 12 EACH | $900 | $800 | $1,205 | $2,150 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $10,000 | $22,000 | $8,051 | $5,000 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 39.5 CY | $215 | $180 | $528 | $230 |
| 659E10000 SEEDING AND MULCHING | 12,200 SY | $1.00 | $3.50 | $0.92 | $2.15 |
| 659E20000 COMMERCIAL FERTILIZER | 1.65 TON | $1,600 | $300 | $1,500 | $1,500 |
| 659E31000 LIME | 2.52 ACRE | $200 | $100 | $200 | $200 |
| 659E35000 WATER | 65.9 MGAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 843E50000 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 20 SF | $250 | $250 | $361 | $50.00 |
| 304E20000 AGGREGATE BASE | 37 CY | $150 | $200 | $342 | $247 |
| 407E10000 TACK COAT | 107 GAL | $4.00 | $4.00 | $80.05 | $10.00 |
| 621E00100 RPM | 3 EACH | $970 | $1,555 | $917 | $1,565 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $35.00 | $50.00 | $88.24 | $30.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 6 EACH | $14.00 | $30.00 | $15.00 | $15.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.06 MILE | $47,025 | $68,500 | $47,025 | $82,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.03 MILE | $62,700 | $108,600 | $62,700 | $82,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $75.00 | $75.00 | $104 | $85.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $20,000 | $11,085 | $10,400 |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $25,000 | $13,300 | $6,300 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 899E10000 CURED-IN-PLACE PIPE LINER, 58"x36" CMP ARCH | 152 FT | $1,000 | $152k | 13% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $110,000 | $110k | 10% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 60" CMP | 606 FT | $165 | $100k | 9% |
| 659E00300 TOPSOIL | 1,354 CY | $65 | $88k | 8% |
| 602E20000 CONCRETE MASONRY | 35.58 CY | $2,100 | $75k | 7% |
| 611E58900 87" X 63" CONDUIT, TYPE A, 707.02 Aluminized, 707. | 98 FT | $650 | $64k | 6% |
| 899E10000 CURED-IN-PLACE PIPE LINER, 50"x31" CMP ARCH | 77 FT | $800 | $62k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $55,000 | $55k | 5% |
| 614E12420 DETOUR SIGNING | 1 LS | $35,000 | $35k | 3% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 96" CMP | 162 FT | $190 | $31k | 3% |