| Item | Quantity | R1Erie Blacktop INC | R2Gerken Paving INC | R3Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 12,858 CY | $147 | $143 | $156 | 20% |
| 442E10081 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 10,307 CY | $170 | $165 | $177 | 18% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 7,416 CY | $188 | $189 | $198 | 14% |
| 304E20000 AGGREGATE BASE | 11,874 CY | $52.50 | $63.50 | $60.00 | 6% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE | 71,218 SY | $8.00 | $9.05 | $9.75 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $500,000 | $230,000 | $400,000 | 5% |
| 203E10001 EXCAVATION, AS PER PLAN | 11,874 CY | $34.50 | $36.50 |
| Item | Quantity | R1Erie Blacktop INC | R2Gerken Paving INC | R3Shelly & Sands INC |
|---|---|---|---|---|
| 202E30000 WALK REMOVED | 1,391 SF | $4.10 | $4.00 | $3.00 |
| 202E32000 CURB REMOVED | 11 FT | $16.30 | $16.00 | $150 |
| 202E38000 GUARDRAIL REMOVED | 1,693.75 FT | $1.65 | $1.60 | $2.00 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 2 EACH | $281 | $275 | $294 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 15 EACH | $112 | $110 | $117 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 6 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $32.50 |
| 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (6.5 INCH) | 71,218 SY | $5.00 | $5.80 | $4.75 | 4% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 1,777 CY | $200 | $205 | $250 | 4% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 6,295 CY | $52.50 | $87.00 | $55.00 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $300,000 | $175,000 | $275,000 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3.0 INCH) | 210,942 SY | $1.40 | $2.70 | $2.00 | 3% |
| 605E31100 AGGREGATE DRAINS | 19,228 FT | $10.50 | $6.00 | $10.00 | 2% |
| 204E13000 EXCAVATION OF SUBGRADE | 6,295 CY | $28.00 | $32.00 | $15.00 | 2% |
| 617E10100 COMPACTED AGGREGATE | 1,816 CY | $62.00 | $55.00 | $58.00 | 1% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 200 CY | $425 | $375 | $400 | 1% |
| 204E10000 SUBGRADE COMPACTION | 71,218 SY | $1.05 | $0.50 | $1.00 | 1% |
| 407E10000 TACK COAT | 29,124 GAL | $2.55 | $2.50 | $2.25 | 1% |
| 659E00300 TOPSOIL (4" THICK) | 949 CY | $73.50 | $113 | $27.00 | 1% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 351 CY | $188 | $195 | $191 | 1% |
| $76.50 |
| $75.00 |
| $80.00 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 8 EACH | $61.20 | $60.00 | $64.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 45 CY | $66.50 | $65.18 | $70.00 |
| 203E20001 EMBANKMENT, AS PER PLAN (AT CURB RAMPS) | 9 CY | $51.00 | $50.00 | $255 |
| 204E45000 PROOF ROLLING | 126 HOUR | $200 | $110 | $251 |
| 204E50000 GEOTEXTILE FABRIC | 12,590 SY | $2.10 | $1.50 | $0.35 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 42.56 STA | $51.00 | $50.00 | $54.00 |
| 209E60500 LINEAR GRADING | 1.86 MILE | $1,900 | $3,500 | $6,000 |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 24.28 MILE | $1,450 | $1,850 | $2,075 |
| 209E80000 GRADING MAILBOX APPROACHES | 32 EACH | $195 | $140 | $291 |
| 605E05110 4" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 1,000 FT | $12.60 | $12.00 | $22.00 |
| 606E13000 GUARDRAIL, TYPE 5 | 1,118.75 FT | $17.35 | $17.00 | $18.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 600 FT | $18.60 | $18.20 | $20.00 |
| 606E17000 RAISING TYPE 5 GUARDRAIL | 1,650 FT | $4.30 | $4.20 | $4.00 |
| 606E26100 ANCHOR ASSEMBLY, TYPE E (MASH 2016) | 9 EACH | $2,428 | $2,380 | $2,540 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 7 EACH | $2,489 | $2,440 | $2,600 |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 6 EACH | $995 | $975 | $1,040 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,377 | $1,350 | $1,442 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 8 EACH | $903 | $885 | $945 |
| 608E10000 4" CONCRETE WALK | 171 SF | $16.60 | $16.25 | $21.00 |
| 608E52000 CURB RAMP | 895 SF | $16.60 | $16.25 | $15.00 |
| 608E52001 CURB RAMP, AS PER PLAN | 148 SF | $23.50 | $23.00 | $29.00 |
| 609E26000 CURB, TYPE 6 | 5 FT | $53.05 | $52.00 | $176 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 1,000 LB | $3.25 | $1.75 | $3.00 |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 7 EACH | $715 | $825 | $700 |
| 623E39601 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE, AS PER P | 2 EACH | $1,110 | $1,850 | $1,600 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $1,540 | $3,020 | $6,000 |
| 659E10000 SEEDING AND MULCHING | 38 SY | $9.20 | $9.00 | $7.00 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 4,277 SY | $2.65 | $4.75 | $10.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.01 TON | $5,610 | $5,500 | $4,687 |
| 659E35000 WATER | 0.21 MGAL | $153 | $150 | $11.00 |
| 670E00500 SLOPE EROSION PROTECTION | 8,535 SY | $3.10 | $1.40 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,229 | $2,500 | $2,340 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $7,711 | $4,500 | $6,300 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $11,166 | $11,000 | $12,000 |
| 832E30000 EROSION CONTROL | 16,000 EACH | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 5 EACH | $825 | $1,800 | $800 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $825 | $1,525 | $600 |
| 253E02000 PAVEMENT REPAIR (LONGITUDINAL) | 178 CY | $200 | $240 | $400 |
| 253E02000 PAVEMENT REPAIR (TRANSVERSE) | 19 CY | $425 | $745 | $500 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25 INCH) | 851 SY | $1.90 | $5.50 | $30.00 |
| 254E01600 PATCHING PLANED SURFACE | 1,055 SY | $11.00 | $15.00 | $4.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 12,847 GAL | $4.80 | $5.25 | $3.50 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 22.36 MILE | $1,015 | $615 | $1,030 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 4 EACH | $700 | $650 | $490 |
| 621E00100 RPM | 891 EACH | $33.65 | $33.00 | $35.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 886 EACH | $4.10 | $8.00 | $6.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 50 EACH | $12.25 | $12.00 | $13.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 26.56 MILE | $1,428 | $1,000 | $1,070 |
| 642E00300 CENTER LINE, TYPE 1 | 13.28 MILE | $1,938 | $1,300 | $1,400 |
| 644E00500 STOP LINE | 552 FT | $7.15 | $7.00 | $7.00 |
| 644E00620 CROSSWALK LINE, 12" | 455 FT | $4.10 | $4.00 | $4.00 |
| 644E01000 RAILROAD SYMBOL MARKING | 2 EACH | $663 | $650 | $694 |
| 644E50300 PAVEMENT MARKING, MISC.: CROSSWALK LINE, 18", AS P | 24 FT | $15.30 | $15.00 | $16.00 |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 4 EACH | $1,683 | $1,650 | $1,760 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 50 CY | $185 | $80.00 | $24.00 |
| 410E13000 TRAFFIC COMPACTED SURFACE, TYPE C | 550 CY | $108 | $80.00 | $36.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $81.60 | $100 | $90.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $14,280 | $14,000 | $15,000 |
| 614E12460 WORK ZONE MARKING SIGN | 88 EACH | $61.20 | $60.00 | $64.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $325 | $475 | $340 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $918 | $900 | $961 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 39.84 MILE | $1,020 | $1,000 | $1,067 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 378 FT | $2.05 | $2.00 | $2.00 |
| 614E40051 BUSINESS ENTRANCE SIGN, AS PER PLAN | 3 EACH | $255 | $250 | $270 |
| 202E98200 REMOVAL MISC.: JOINT SEALER | 68 FT | $4.75 | $4.62 | $29.00 |
| 512E10301 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN, AS | 27 SY | $49.10 | $48.13 | $107 |
| 516E31000 JOINT SEALER | 68 FT | $19.20 | $18.81 | $38.00 |
| 519E12510 SPECIAL - PATCHING CONCRETE BRIDGE DECK | 20 SY | $688 | $674 | $534 |
| 202E98200 REMOVAL MISC.: JOINT SEALER | 82 FT | $4.75 | $4.62 | $29.00 |
| 512E10301 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN, AS | 134 SY | $49.10 | $48.13 | $43.00 |
| 516E31000 JOINT SEALER | 82 FT | $19.20 | $18.81 | $37.00 |
| 202E98200 REMOVAL MISC.: JOINT SEALER | 76 FT | $4.75 | $4.62 | $29.00 |
| 254E01010 PAVEMENT PLANING, PORTLAND CEMENT CONCRETE (1.25 I | 36 SY | $100 | $98.18 | $21.00 |
| 512E10301 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN, AS | 70 SY | $49.10 | $48.13 | $54.00 |
| 516E31000 JOINT SEALER | 76 FT | $19.20 | $18.81 | $37.00 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 262.5 FT | $110 | $108 | $115 |
| 519E12510 SPECIAL - PATCHING CONCRETE BRIDGE DECK | 5 SY | $688 | $674 | $1,070 |
| 202E98200 REMOVAL MISC.: JOINT SEALER | 92 FT | $4.75 | $4.62 | $29.00 |
| 512E10301 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN, AS | 53 SY | $49.10 | $48.13 | $80.00 |
| 516E31000 JOINT SEALER | 92 FT | $19.20 | $18.81 | $37.00 |
| 519E12510 SPECIAL - PATCHING CONCRETE BRIDGE DECK | 14 SY | $688 | $674 | $640 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $6,000 | $5,250 | $2,162 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $40,000 | $55,000 | $40,000 |
| 619E16020 FIELD OFFICE, TYPE C | 7 MNTH | $2,500 | $3,500 | $4,600 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $12,000 | $4,530 | $25,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 12,858 CY | $147 | $1.89M | 18% |
| 442E10081 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 10,307 CY | $170 | $1.75M | 17% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 7,416 CY | $188 | $1.39M | 13% |
| 304E20000 AGGREGATE BASE | 11,874 CY | $52.5 | $623k | 6% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE | 71,218 SY | $8 | $570k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $500,000 | $500k | 5% |
| 203E10001 EXCAVATION, AS PER PLAN | 11,874 CY | $34.5 | $410k | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (6.5 INCH) | 71,218 SY | $5 | $356k | 3% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 1,777 CY | $200 | $355k | 3% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 6,295 CY | $52.5 | $330k | 3% |