| Item | Quantity | R1Bog Construction INC | R2Black Horse Bridge Construction INC | R3Bcc Ohio INC | % of bid |
|---|---|---|---|---|---|
| 515E12031 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $11,875 | $13,000 | $12,368 | 15% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $75,000 | $80,000 | $88,750 | 12% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 185 CY | $310 | $290 | $302 | 9% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 2 EACH | $28,000 | $27,000 | $25,740 | 9% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 96 FT | $520 | $500 | $504 | 8% |
| 526E15001 REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER | 142 SY | $275 | $425 | $551 | 6% |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 55 CY |
| Item | Quantity | R1Bog Construction INC | R2Black Horse Bridge Construction INC | R3Bcc Ohio INC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,500 | $5,800 | $900 |
| 202E23500 WEARING COURSE REMOVED | 131 SY | $25.00 | $9.00 | $11.32 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 59 FT | $50.00 | $58.00 | $28.87 |
| 202E38000 GUARDRAIL REMOVED | 194 FT | $5.00 | $4.00 | $2.08 |
| 203E10000 EXCAVATION | 364 CY | $20.00 | $30.00 | $26.84 |
| 203E20000 EMBANKMENT | 81 CY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $650 |
| $680 |
| $1,418 |
| 6% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 23 CY | $1,500 | $2,400 | $2,762 | 5% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 258 SY | $120 | $200 | $130 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $40,000 | $19,172 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 10,627 LB | $2.00 | $2.20 | $2.22 | 3% |
| 304E20000 AGGREGATE BASE | 149 CY | $125 | $110 | $124 | 3% |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 38 CY | $450 | $410 | $426 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $10,000 | $4,067 | 2% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (36 CY | $400 | $325 | $338 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $14,000 | $10,000 | $12,584 | 2% |
| 202E23000 PAVEMENT REMOVED | 821 SY | $16.00 | $17.00 | $15.70 | 2% |
| 846E00111 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM, A | 21 CF | $600 | $625 | $507 | 2% |
| 526E90010 TYPE A INSTALLATION | 64 FT | $180 | $192 | $409 | 2% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| $50.00 |
| $16.00 |
| $17.33 |
| 204E10000 SUBGRADE COMPACTION | 840 SY | $5.00 | $4.00 | $2.72 |
| 606E15050 GUARDRAIL, TYPE MGS | 156.25 FT | $28.00 | $23.20 | $24.13 |
| 606E20050 ROUNDED END SECTION | 2 EACH | $100 | $65.00 | $67.60 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 1 EACH | $1,600 | $1,495 | $1,555 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,500 | $1,365 | $1,420 |
| 606E34600 MGS BRIDGE TERMINAL ASSEMBLY, TYPE TST-2 | 1 EACH | $2,320 | $2,120 | $2,205 |
| 606E34601 MGS BRIDGE TERMINAL ASSEMBLY, TYPE TST-2, AS PER P | 3 EACH | $2,400 | $2,270 | $2,361 |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 25 CY | $100 | $108 | $167 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $100 | $58.50 |
| 659E00300 TOPSOIL | 130 CY | $38.00 | $55.00 | $17.67 |
| 659E10000 SEEDING AND MULCHING | 1,168 SY | $6.50 | $4.00 | $3.95 |
| 659E14000 REPAIR SEEDING AND MULCHING | 58 SY | $1.00 | $1.00 | $1.04 |
| 659E20000 COMMERCIAL FERTILIZER | 0.16 TON | $1,000 | $500 | $676 |
| 659E31000 LIME | 0.24 ACRE | $100 | $200 | $41.58 |
| 659E35000 WATER | 10 MGAL | $1.00 | $1.00 | $1.04 |
| 660E20000 SODDING REINFORCED | 46 SY | $30.00 | $35.00 | $28.60 |
| 602E20000 CONCRETE MASONRY | 0.7 CY | $3,000 | $4,200 | $5,271 |
| 611E00200 4" CONDUIT, TYPE C | 8 FT | $100 | $28.00 | $78.19 |
| 611E04600 12" CONDUIT, TYPE C | 22 FT | $125 | $60.00 | $158 |
| 611E05700 15" CONDUIT, TYPE A, 706.02 | 47 FT | $85.00 | $140 | $158 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $3,500 | $3,200 | $2,910 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1 1/4" DEPTH) | 367 SY | $20.00 | $15.00 | $15.60 |
| 407E10000 TACK COAT | 149 GAL | $5.00 | $3.50 | $3.64 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $450 | $350 | $364 |
| 621E00100 RPM | 8 EACH | $425 | $400 | $400 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 10 EACH | $50.00 | $20.00 | $18.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 12 EACH | $15.00 | $13.50 | $14.04 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 20 FT | $20.00 | $15.00 | $15.60 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 12.5 FT | $20.00 | $18.00 | $18.72 |
| 630E08510 STREET NAME SIGN SUPPORT, NO. 2 POST | 10 FT | $25.00 | $16.00 | $16.64 |
| 630E08600 SIGN POST REFLECTOR | 1 EACH | $100 | $45.00 | $46.80 |
| 630E80100 SIGN, FLAT SHEET | 12.75 SF | $25.00 | $20.00 | $20.80 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 7 EACH | $100 | $10.00 | $10.40 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $100 | $15.00 | $15.60 |
| 646E10010 EDGE LINE, 6" | 0.14 MILE | $30,000 | $14,200 | $14,768 |
| 646E10200 CENTER LINE | 0.07 MILE | $60,000 | $26,800 | $28,872 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 20 HOUR | $30.00 | $75.00 | $78.00 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,500 | $2,180 | $2,080 |
| 614E12420 DETOUR SIGNING | 1 LS | $6,000 | $6,500 | $3,952 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $150 | $250 | $426 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 14 EACH | $15.00 | $45.00 | $14.74 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 6 EACH | $20.00 | $50.00 | $17.14 |
| 614E13360 OBJECT MARKER, TWO WAY | 20 EACH | $30.00 | $40.00 | $19.35 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.18 MILE | $12,000 | $17,150 | $12,568 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.16 MILE | $7,500 | $5,850 | $6,084 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.51 MILE | $10,000 | $11,150 | $9,428 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.32 MILE | $5,000 | $3,045 | $3,166 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 29 FT | $25.00 | $14.00 | $14.56 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $7,000 | $7,310 | $13,667 |
| 616E10000 WATER | 10 MGAL | $1.00 | $10.00 | $1.31 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 410 FT | $22.00 | $27.00 | $30.11 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 180 FT | $28.00 | $30.00 | $94.01 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $7,500 | $30,700 | $11,443 |
| 503E21100 UNCLASSIFIED EXCAVATION | 203 CY | $35.00 | $100 | $97.68 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 198 EACH | $22.00 | $34.00 | $25.61 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 82 SY | $38.00 | $36.00 | $35.42 |
| 512E33000 TYPE 2 WATERPROOFING | 36 SY | $60.00 | $30.00 | $24.48 |
| 512E44400 TYPE B WATERPROOFING | 10 SY | $95.00 | $55.00 | $211 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 148 SF | $10.00 | $13.00 | $8.48 |
| 516E41100 1/8" PREFORMED BEARING PAD | 16 EACH | $30.00 | $45.00 | $69.59 |
| 516E43101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 32 EACH | $130 | $140 | $194 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 22 CY | $125 | $124 | $232 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 98 FT | $20.00 | $14.00 | $15.79 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 18 FT | $15.00 | $18.00 | $17.28 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $10,000 | $15,500 | $11,326 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,500 | $38,000 | $24,336 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $500 | $750 | $2,209 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12031 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $11,875 | $95k | 11% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $75,000 | $75k | 9% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 185 CY | $310 | $57k | 7% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 2 EACH | $28,000 | $56k | 7% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 96 FT | $520 | $50k | 6% |
| 526E15001 REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER | 142 SY | $275 | $39k | 5% |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 55 CY | $650 | $36k | 4% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 23 CY | $1,500 | $35k | 4% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 258 SY | $120 | $31k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $25k | 3% |