CLI-/GRE Culvert Repair FY2024
CLI County · est $0.5M
Bid dateThursday, September 14—
CLI County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 16 more items below.
| Item | Quantity | R1Bcc Ohio INC | R2Axis Civil Construction LLC | R3Madex Construction CO | R4Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|
| 611E96550 FIELD PAVING OF EXISTING PIPE, 11'-10" X 7'-7" CMP | 176 FT | $284 | $250 | $397 | $300 | 14% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 9'-6" X 6'-5" CMP A | 164 FT | $226 | $180 | $262 | $260 | 10% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 10'-8" X 6'-11" CMP | 124 FT | $244 | $210 | $302 | $300 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,984 | $45,000 | $16,327 | $35,000 | 8% |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD A | 256 SF | $109 | $120 | $43.69 | $40.00 | 8% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 7'-3" X 5'-3" CMP P | 128 FT | $186 | $180 | $246 |
| Item | Quantity | R1Bcc Ohio INC | R2Axis Civil Construction LLC | R3Madex Construction CO | R4Alan Stone CO INC |
|---|---|---|---|---|---|
| 659E20000 COMMERCIAL FERTILIZER | 0.94 TON | $1,676 | $250 | $1,280 | $979 |
| 659E31000 LIME | 1.45 ACRE | $18.10 | $100 | $350 | $400 |
| 659E35000 WATER | 38.3 MGAL | $2.96 | $1.00 | $24.59 | $12.97 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $2,310 | $7,500 | $10,926 | $30,000 |
| 611E97700 CONDUIT, MISC.: REPAIR METHOD C | 8 SF |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $260 |
| 7% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 10'-8" X 6'-11" CMP | 73 FT | $276 | $450 | $363 | $300 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $19,719 | $30,000 | $65,268 | $45,000 | 6% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 10'-8" X 6'-11" CMP | 69 FT | $275 | $250 | $327 | $350 | 5% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $14,325 | $7,500 | $17,761 | $35,000 | 4% |
| 659E10000 SEEDING AND MULCHING | 7,030 SY | $1.50 | $2.30 | $3.63 | $4.27 | 3% |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD B | 88 SF | $115 | $180 | $89.13 | $100 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $9,240 | $20,000 | $10,475 | $35,000 | 3% |
| 832E30000 EROSION CONTROL | 9,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 202E98400 REMOVAL MISC.:, EXISTING CONCRETE FIELD PAVING | 580 SF | $14.58 | $50.00 | $13.27 | $56.00 | 2% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 485 FT | $16.89 | $85.00 | $46.84 | $210 | 2% |
| 611E97700 CONDUIT, MISC.: REPAIR METHOD A | 64 SF | $111 | $120 | $49.74 | $40.00 | 2% |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD A | 58 SF | $113 | $120 | $53.09 | $40.00 | 2% |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD A | 51 SF | $115 | $120 | $60.38 | $40.00 | 2% |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD A | 48 SF | $115 | $120 | $64.15 | $40.00 | 2% |
| $438 |
| $250 |
| $326 |
| $800 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $3,234 | $7,500 | $9,768 | $34,000 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $924 | $5,000 | $9,189 | $19,000 |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD B | 15 SF | $264 | $180 | $337 | $320 |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD C | 4 SF | $534 | $250 | $421 | $1,300 |
| 690E98000 SPECIAL - RESEAL JOINT WITH HYDROPHOBIC GROUT | 1 EACH | $2,298 | $4,500 | $4,277 | $3,500 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $1,848 | $7,500 | $8,505 | $14,000 |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD B | 20 SF | $177 | $180 | $337 | $300 |
| 690E98000 SPECIAL - WELDED STRAP RUST REPAIR | 10 EACH | $280 | $600 | $755 | $800 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $4,620 | $7,500 | $9,768 | $26,000 |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD B | 11 SF | $214 | $180 | $285 | $300 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,850 | $6,500 | $14,763 | $7,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E96550 FIELD PAVING OF EXISTING PIPE, 11'-10" X 7'-7" CMP | 176 FT | $283.85 | $50k | 13% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 9'-6" X 6'-5" CMP A | 164 FT | $225.82 | $37k | 9% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 10'-8" X 6'-11" CMP | 124 FT | $244.33 | $30k | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,984 | $30k | 8% |
| 611E97700 CONDUIT, MISC.:REPAIR METHOD A | 256 SF | $109.49 | $28k | 7% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 7'-3" X 5'-3" CMP P | 128 FT | $186.14 | $24k | 6% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 10'-8" X 6'-11" CMP | 73 FT | $275.87 | $20k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $19,719 | $20k | 5% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 10'-8" X 6'-11" CMP | 69 FT | $274.62 | $19k | 5% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $14,325 | $14k | 4% |