CHP-SR 29-31.24
CHP County · est $0.7M
Bid dateThursday, January 11—
CHP County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 44 more items below.
| Item | Quantity | R1R & I Construction INC | R2Bcc Ohio INC | % of bid |
|---|---|---|---|---|
| 515E12070 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 9 EACH | $23,055 | $20,666 | 29% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $142,000 | $133,986 | 20% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 72 CY | $900 | $1,079 | 9% |
| 509E26000 GALVANIZED STEEL REINFORCEMENT | 16,586 LB | $3.00 | $2.35 | 7% |
| 844E10001 CONCRETE PATCHING WITH GALVANIC ANODE PROTECTION, | 174 SF | $285 | $164 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $45,000 | $86,828 | 6% |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 11 CY | $2,000 | $3,445 | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 36 CY | $574 | $683 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $18,000 | $7,299 | 3% |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 14 CY | $1,000 | $2,374 | 2% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $1,333 | $1,529 | 2% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 14 CY | $762 | $1,575 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,000 | $10,973 | 1% |
| 517E75120 RAILING (CONCRETE PARAPET WITH TWIN STEEL TUBE RAI | 73 FT | $118 | $124 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,500 | $11,545 | 1% |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 3 EACH | $2,375 | $2,494 | 1% |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $7,000 | $10,395 | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $3,450 | $3,623 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,000 | $8,199 | 1% |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 36 EACH | $160 | $205 | 1% |
| Item | Quantity | R1R & I Construction INC | R2Bcc Ohio INC |
|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $500 | $3,465 |
| 202E23000 PAVEMENT REMOVED | 27 SY | $10.00 | $59.22 |
| 202E30000 WALK REMOVED | 170 SF | $5.00 | $6.01 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 25 FT | $4.00 | $46.20 |
| 202E38000 GUARDRAIL REMOVED | 100 FT | $4.00 | $6.30 |
| 203E10000 EXCAVATION | 59 CY | $10.00 | $28.88 |
| 203E10001 EXCAVATION, AS PER PLAN | 100 CY | $10.00 | $69.30 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 203E20000 EMBANKMENT | 68 CY | $25.00 | $28.88 |
| 204E10000 SUBGRADE COMPACTION | 172 SY | $3.00 | $9.77 |
| 606E15050 GUARDRAIL, TYPE MGS | 50 FT | $28.00 | $29.40 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $2,100 | $2,205 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $650 | $683 |
| 608E10000 4" CONCRETE WALK | 214 SF | $7.95 | $41.08 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $25.00 | $94.50 |
| 659E00300 TOPSOIL | 10 CY | $44.00 | $106 |
| 659E10000 SEEDING AND MULCHING | 94 SY | $10.00 | $22.58 |
| 659E14000 REPAIR SEEDING AND MULCHING | 5 SY | $1.00 | $3.15 |
| 659E20000 COMMERCIAL FERTILIZER | 0.01 TON | $1,000 | $735 |
| 659E31000 LIME | 0.02 ACRE | $10.00 | $52.50 |
| 659E35000 WATER | 1 MGAL | $1.00 | $1.05 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 |
| 611E04400 12" CONDUIT, TYPE B | 25 FT | $40.00 | $349 |
| 304E20000 AGGREGATE BASE | 28 CY | $70.00 | $189 |
| 407E10000 TACK COAT | 26 GAL | $5.00 | $3.15 |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 50 FT | $65.00 | $28.32 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 8 EACH | $11.00 | $11.55 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 38 FT | $30.00 | $22.05 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $125 | $47.25 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3 EACH | $25.00 | $21.00 |
| 646E10010 EDGE LINE, 6" | 0.04 MILE | $19,980 | $117,149 |
| 646E10200 CENTER LINE | 0.02 MILE | $35,000 | $156,156 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $40.00 | $178 |
| 410E13000 TRAFFIC COMPACTED SURFACE, TYPE C | 10 CY | $40.00 | $178 |
| 616E10000 WATER | 10 MGAL | $1.00 | $2.57 |
| 202E22900 APPROACH SLAB REMOVED | 134 SY | $25.00 | $153 |
| 202E23500 WEARING COURSE REMOVED | 352 SY | $10.00 | $24.94 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 79 LB | $2.00 | $3.05 |
| 509E30020 NO. 4 DEFORMED GFRP REINFORCEMENT | 1,078 FT | $4.00 | $5.34 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 81 SY | $20.00 | $18.45 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 22 SF | $5.00 | $16.19 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 103 FT | $25.00 | $73.35 |
| 516E31010 2" DEEP JOINT SEALER | 79 FT | $20.00 | $23.52 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 34 CY | $70.00 | $182 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,500 | $3,675 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12070 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 9 EACH | $23,055 | $207k | 27% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $142,000 | $142k | 19% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 72 CY | $900 | $65k | 8% |
| 509E26000 GALVANIZED STEEL REINFORCEMENT | 16,586 LB | $3 | $50k | 7% |
| 844E10001 CONCRETE PATCHING WITH GALVANIC ANODE PROTECTION, | 174 SF | $285 | $50k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $45,000 | $45k | 6% |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 11 CY | $2,000 | $22k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 36 CY | $574 | $21k | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $18,000 | $18k | 2% |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 14 CY | $1,000 | $14k | 2% |