HOC-SR 328-06.22
HOC County · est $0.3M
Bid dateThursday, January 11—
HOC County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 24 more items below.
| Item | Quantity | R1Axis Civil Construction LLC | R2Parker Corporation | R3R C Construction Company And Son | R4INC D G M INC | R5Alan Stone CO INC | R6Ohio-west Virginia Excavating CO | R7Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 611E52901 34" X 53" CONDUIT, TYPE A, 706.04, AS PER PLAN | 56 FT | $560 | $757 | $800 | $950 | $1,100 | $487 | $552 | 13% |
| 602E20000 CONCRETE MASONRY | 11.66 CY | $1,850 | $650 | $1,250 | $1,600 | $2,495 | $4,100 | $793 | 9% |
| 624E10000 |
| Item | Quantity | R1Axis Civil Construction LLC | R2Parker Corporation | R3R C Construction Company And Son | R4INC D G M INC | R5Alan Stone CO INC | R6Ohio-west Virginia Excavating CO | R7Eclipse CO LLC |
|---|---|---|---|---|---|---|---|---|
| 203E20000 EMBANKMENT | 48 CY | $24.00 | $20.00 | $25.00 | $35.00 | $32.20 | $42.00 | $44.00 |
| 204E10000 SUBGRADE COMPACTION | 346 SY | $3.00 | $0.50 | $2.00 | $12.00 | $4.62 | $6.00 | $1.00 |
| 623E40500 REFERENCE MONUMENT, TYPE A | 8 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $20,000 |
| $17,750 |
| $12,500 |
| $8,000 |
| $33,500 |
| $37,500 |
| $24,460 |
| 9% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 172 SY | $100 | $75.00 | $125 | $150 | $98.89 | $168 | $121 | 7% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 52 CY | $330 | $501 | $395 | $530 | $450 | $650 | $500 | 7% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 52 CY | $320 | $501 | $395 | $530 | $400 | $650 | $500 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $14,000 | $17,250 | $12,000 | $23,000 | $27,000 | $30,600 | $32,000 | 6% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $12,000 | $9,250 | $2,000 | $11,000 | $16,000 | $3,300 | $12,000 | 5% |
| 202E35200 PIPE REMOVED, OVER 24" | 40 FT | $300 | $150 | $100 | $120 | $50.00 | $120 | $27.00 | 5% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $10,000 | $13,250 | $5,500 | $20,000 | $5,000 | $29,500 | $105,000 | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" AVERAGE D | 639 SY | $13.00 | $8.00 | $30.00 | $12.50 | $25.00 | $16.00 | $12.50 | 4% |
| 613E41300 LOW STRENGTH MORTAR BACKFILL (TYPE 2) | 52 CY | $150 | $150 | $195 | $300 | $135 | $263 | $188 | 3% |
| 304E20000 AGGREGATE BASE | 69 CY | $110 | $65.00 | $125 | $150 | $104 | $155 | $107 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $7,500 | $8,250 | $5,000 | $3,000 | $3,300 | $4,800 | $8,842 | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 348 FT | $20.00 | $10.00 | $30.00 | $30.00 | $21.00 | $49.00 | $37.70 | 3% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,500 | $1,500 | $1,000 | $2,200 | $2,450 | $2,400 | $2,952 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,500 | $9,250 | $12,000 | $4,000 | $12,000 | $1,900 | $15,000 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $4,500 | $12,250 | $4,000 | $2,000 | $13,000 | $7,400 | $5,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,500 | $10,250 | $16,000 | $13,000 | $7,000 | $6,500 | $10,500 | 2% |
| 203E10000 EXCAVATION | 175 CY | $24.00 | $20.00 | $25.00 | $35.00 | $33.98 | $43.00 | $47.00 | 2% |
| $250 |
| $550 |
| $750 |
| $500 |
| $1,200 |
| $500 |
| $531 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 1 EACH | $512 | $550 | $750 | $400 | $250 | $400 | $96.00 |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 20 CY | $110 | $65.00 | $175 | $150 | $144 | $316 | $123 |
| 659E10000 SEEDING AND MULCHING | 847 SY | $3.70 | $1.00 | $10.00 | $4.00 | $4.27 | $5.00 | $3.70 |
| 659E20000 COMMERCIAL FERTILIZER | 0.08 TON | $1,400 | $3,125 | $1,850 | $1,500 | $979 | $1,800 | $1,400 |
| 659E31000 LIME | 0.18 ACRE | $100 | $1,389 | $1,000 | $100 | $400 | $100 | $100 |
| 659E35000 WATER | 3 MGAL | $1.00 | $0.05 | $1.00 | $1.00 | $12.97 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 8 FT | $25.00 | $10.00 | $35.00 | $60.00 | $170 | $220 | $31.00 |
| 407E20000 NON-TRACKING TACK COAT | 102 GAL | $5.00 | $3.05 | $10.00 | $3.00 | $5.15 | $4.00 | $3.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 5 EACH | $25.00 | $20.00 | $50.00 | $1.00 | $24.15 | $125 | $11.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $125 | $100 | $250 | $100 | $91.01 | $400 | $105 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 3 EACH | $245 | $100 | $250 | $100 | $128 | $400 | $105 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.24 MILE | $1,780 | $3,900 | $8,500 | $4,000 | $6,519 | $5,000 | $11,256 |
| 642E00300 CENTER LINE, TYPE 1 | 0.12 MILE | $2,815 | $7,200 | $8,500 | $7,500 | $11,359 | $9,300 | $14,176 |
| 642E00500 STOP LINE, TYPE 1 | 20 FT | $8.00 | $14.00 | $25.00 | $15.00 | $25.00 | $18.00 | $8.00 |
| 502E11100 STRUCTURE FOR MAINTAINING TRAFFIC | 1 LS | $3,200 | $2,000 | $5,000 | $5,000 | $4,900 | $4,000 | $1,478 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $1,000 | $200 | $1,000 | $2,500 | $500 | $9,200 | $12,469 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 17 EACH | $14.00 | $10.00 | $25.00 | $42.00 | $22.29 | $55.00 | $16.25 |
| 614E13360 OBJECT MARKER, TWO WAY | 17 EACH | $20.00 | $10.00 | $25.00 | $44.00 | $27.20 | $57.00 | $46.00 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.27 MILE | $11,925 | $5,556 | $1,000 | $5,000 | $7,170 | $6,000 | $22,390 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 22 FT | $14.00 | $10.00 | $25.00 | $15.00 | $25.00 | $18.00 | $10.54 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E52901 34" X 53" CONDUIT, TYPE A, 706.04, AS PER PLAN | 56 FT | $560 | $31k | 12% |
| 602E20000 CONCRETE MASONRY | 11.66 CY | $1,850 | $22k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 8% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 172 SY | $100 | $17k | 7% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 52 CY | $330 | $17k | 7% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 52 CY | $320 | $17k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $14,000 | $14k | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $12,000 | $12k | 5% |
| 202E35200 PIPE REMOVED, OVER 24" | 40 FT | $300 | $12k | 5% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $10,000 | $10k | 4% |