VIN-SR 328-06.42
VIN County · est $0.3M
Bid dateThursday, January 11—
VIN County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Parker Corporation | R2Skeens Excavating INC | R3D G M INC | R4R C Construction Company And Son INC | R5Axis Civil Construction LLC | R6Eclipse CO LLC | R7Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 611E94701 6' X 4' CONDUIT, TYPE A, 706.05, AS PER PLAN | 40 FT | $1,019 | $1,500 | $1,500 | $800 | $1,390 | $1,087 | $1,300 | 20% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 52 CY | $406 | $400 | $400 | $400 | $420 | $405 | $450 | 11% |
| Item | Quantity | R1Parker Corporation | R2Skeens Excavating INC | R3D G M INC | R4R C Construction Company And Son INC | R5Axis Civil Construction LLC | R6Eclipse CO LLC | R7Alan Stone CO INC |
|---|---|---|---|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" AND UNDER | 25 FT | $20.00 | $20.00 | $20.00 | $50.00 | $30.00 | $19.00 | $20.00 |
| 203E20000 EMBANKMENT | 69 CY | $20.00 | $20.00 | $35.00 | $25.00 | $24.00 | $36.00 | $30.00 |
| 204E10000 SUBGRADE COMPACTION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 624E10000 MOBILIZATION |
| 1 LS |
| $16,000 |
| $6,000 |
| $9,500 |
| $20,000 |
| $20,000 |
| $22,519 |
| $27,600 |
| 8% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 22 CY | $556 | $400 | $580 | $395 | $420 | $555 | $500 | 6% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $11,000 | $13,500 | $3,000 | $850 | $12,500 | $5,121 | $12,000 | 6% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 20 CY | $550 | $800 | $700 | $500 | $550 | $1,178 | $980 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $11,000 | $5,000 | $12,500 | $20,000 | $5,500 | $15,000 | $13,000 | 6% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,500 | $3,000 | $6,000 | $14,000 | $4,500 | $8,500 | $5,000 | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $1,000 | $11,000 | $2,500 | $3,500 | $3,500 | $3,500 | 5% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $5,000 | $3,500 | $12,500 | $5,500 | $8,500 | $12,000 | 5% |
| 613E41300 LOW STRENGTH MORTAR BACKFILL (TYPE 2) | 43 CY | $150 | $250 | $180 | $195 | $168 | $207 | $210 | 3% |
| 202E35200 PIPE REMOVED, OVER 24" | 30 FT | $200 | $50.00 | $125 | $200 | $200 | $16.00 | $170 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 250 FT | $23.50 | $30.00 | $25.00 | $35.00 | $23.50 | $28.94 | $30.00 | 3% |
| 623E40500 REFERENCE MONUMENT, TYPE A | 10 EACH | $550 | $50.00 | $500 | $750 | $480 | $784 | $590 | 3% |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 3 EACH | $1,600 | $1,500 | $1,650 | $1,400 | $1,600 | $1,370 | $2,000 | 2% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 7 CY | $650 | $1,000 | $1,500 | $500 | $2,550 | $2,766 | $3,000 | 2% |
| 203E10000 EXCAVATION | 213 CY | $20.00 | $15.00 | $35.00 | $25.00 | $24.00 | $37.00 | $55.00 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" AVERAGE D | 432 SY | $8.00 | $15.00 | $13.00 | $30.00 | $18.00 | $13.00 | $25.00 | 2% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 2,592 LB | $1.25 | $2.00 | $2.50 | $3.00 | $2.50 | $6.00 | $3.00 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 32 CY | $65.00 | $180 | $150 | $150 | $125 | $142 | $260 | 1% |
| 91 SY |
| $0.50 |
| $5.00 |
| $15.00 |
| $2.00 |
| $4.00 |
| $2.00 |
| $30.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,250 | $1,200 | $1,300 | $1,850 | $1,250 | $1,080 | $1,600 |
| 659E10000 SEEDING AND MULCHING | 1,504 SY | $1.00 | $0.60 | $2.25 | $5.00 | $2.21 | $2.21 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.14 TON | $1,786 | $400 | $1,500 | $1,850 | $1,400 | $1,400 | $1,100 |
| 659E31000 LIME | 0.32 ACRE | $782 | $400 | $100 | $1,000 | $100 | $100 | $1,000 |
| 659E35000 WATER | 5 MGAL | $0.05 | $10.00 | $1.00 | $1.00 | $1.00 | $1.00 | $130 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100 | $10,000 | $1,000 | $5,500 | $7,500 | $25,000 | $10,000 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 1 CY | $650 | $1,000 | $1,500 | $500 | $2,000 | $2,712 | $5,000 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 30 SY | $12.00 | $50.00 | $30.00 | $60.00 | $36.00 | $21.00 | $35.00 |
| 512E33000 TYPE 2 WATERPROOFING | 48 SY | $14.00 | $50.00 | $25.00 | $30.00 | $39.00 | $24.00 | $80.00 |
| 512E33010 TYPE 3 WATERPROOFING | 40 SY | $18.00 | $50.00 | $50.00 | $40.00 | $65.00 | $56.00 | $110 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 24 SF | $5.00 | $20.00 | $15.00 | $25.00 | $5.00 | $10.00 | $3.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 8 CY | $150 | $150 | $150 | $125 | $325 | $119 | $430 |
| 605E31100 AGGREGATE DRAINS | 38 FT | $10.00 | $10.00 | $35.00 | $30.00 | $25.00 | $18.00 | $60.00 |
| 611E07900 18" CONDUIT, TYPE D | 30 FT | $50.00 | $80.00 | $80.00 | $125 | $65.00 | $96.00 | $110 |
| 304E20000 AGGREGATE BASE | 21 CY | $65.00 | $150 | $150 | $125 | $150 | $93.00 | $240 |
| 407E20000 NON-TRACKING TACK COAT | 104 GAL | $3.60 | $5.00 | $3.50 | $10.00 | $6.00 | $3.50 | $10.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 6 EACH | $20.00 | $50.00 | $1.00 | $50.00 | $30.00 | $11.00 | $80.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, (BIDIRECTIONAL) | 8 EACH | $15.00 | $12.00 | $15.00 | $25.00 | $12.00 | $10.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $100 | $100 | $65.00 | $250 | $65.00 | $105 | $85.00 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 2 EACH | $100 | $100 | $175 | $250 | $175 | $105 | $220 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.13 MILE | $6,800 | $7,500 | $8,000 | $12,500 | $6,800 | $6,800 | $8,700 |
| 642E00300 CENTER LINE, TYPE 1 | 0.07 MILE | $12,250 | $15,000 | $15,000 | $12,500 | $12,250 | $12,250 | $16,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E94701 6' X 4' CONDUIT, TYPE A, 706.05, AS PER PLAN | 40 FT | $1,019 | $41k | 19% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 52 CY | $406 | $21k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $16,000 | $16k | 7% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 22 CY | $556 | $12k | 6% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $11,000 | $11k | 5% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 20 CY | $550 | $11k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $11,000 | $11k | 5% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,500 | $11k | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $10k | 5% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $10k | 5% |