CLE-/CLI BP VAR 2024
CLE County · est $3.5M
Bid dateThursday, January 25—
CLE County · est $3.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 46 more items below.
| Item | Quantity | R1Kmx Painting INC | R2Euro Paint LLC | R3Apbn INC | R4Elite Contractors INC | R5360 Construction Company INC | R6Panther Industrial Painting LLC | R7Corrosion Resistance LTD | R8Industrial Painting & Rigging INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 45,649 SF | $9.00 | $7.40 | $10.00 | $10.00 | $10.00 | $15.00 | $9.70 | $12.00 | 19% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 35,075 SF | $9.00 | $7.86 | $10.00 | $10.00 | $10.00 |
| Item | Quantity | R1Kmx Painting INC | R2Euro Paint LLC | R3Apbn INC | R4Elite Contractors INC | R5360 Construction Company INC | R6Panther Industrial Painting LLC | R7Corrosion Resistance LTD | R8Industrial Painting & Rigging INC |
|---|---|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $10,000 | $10,000 | $6,000 | $12,000 | $5,000 | $1,000 | $11,000 | $10,000 |
| 202E47201 BRIDGE TERMINAL ASSEMBLY REMOVED FOR REUSE, AS PER | 1 EACH | $150 | $150 | $150 | $150 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $15.00 |
| $9.80 |
| $12.00 |
| 15% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $300,000 | $85,574 | $120,000 | $150,000 | $198,000 | $150,000 | $442,000 | $50,000 | 14% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 15,965 SF | $15.00 | $10.94 | $10.00 | $10.00 | $10.00 | $15.00 | $16.00 | $12.00 | 11% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $66,539 | $228,880 | $200,000 | $100,000 | $120,000 | $125,000 | $250,000 | 9% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 704 SF | $150 | $107 | $20.00 | $200 | $85.00 | $60.00 | $148 | $60.00 | 5% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,853 SF | $15.00 | $15.08 | $20.00 | $14.00 | $20.00 | $17.00 | $23.75 | $18.00 | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,203 SF | $15.00 | $16.83 | $20.00 | $15.00 | $20.00 | $17.00 | $21.20 | $18.00 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 45,649 SF | $1.00 | $1.83 | $2.00 | $2.00 | $4.00 | $2.50 | $2.40 | $3.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 45,649 SF | $1.00 | $1.83 | $2.00 | $2.00 | $3.00 | $2.50 | $2.70 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 45,649 SF | $1.00 | $1.83 | $2.00 | $2.00 | $2.25 | $2.50 | $2.70 | $2.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $40,000 | $40,000 | $30,000 | $60,000 | $40,000 | $100,000 | $50,000 | $76,000 | 2% |
| 512E10101 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE), AS | 1,413 SY | $26.00 | $40.00 | $40.00 | $35.00 | $28.00 | $35.00 | $35.00 | $45.00 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 35,075 SF | $1.00 | $2.17 | $2.00 | $2.00 | $4.00 | $2.50 | $2.95 | $3.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 35,075 SF | $1.00 | $2.17 | $2.00 | $2.00 | $3.00 | $2.50 | $2.95 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 35,075 SF | $1.00 | $2.17 | $2.00 | $2.00 | $2.25 | $2.50 | $3.00 | $2.00 | 2% |
| 512E10101 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE), AS | 1,208 SY | $28.00 | $40.00 | $40.00 | $35.00 | $28.00 | $35.00 | $35.00 | $45.00 | 2% |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 1,413 SY | $22.00 | $40.00 | $30.00 | $25.00 | $30.00 | $35.00 | $25.00 | $20.00 | 1% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 5,853 SF | $5.00 | $4.14 | $10.00 | $3.00 | $10.00 | $2.50 | $5.20 | $3.00 | 1% |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 1,205 SY | $22.00 | $40.00 | $30.00 | $25.00 | $30.00 | $35.00 | $25.00 | $20.00 | 1% |
| $150 |
| $200 |
| $3,300 |
| $120,000 |
| 606E32601 BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE F, AS PER P | 1 EACH | $2,450 | $2,450 | $2,450 | $825 | $825 | $2,800 | $5,700 | $70,000 |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 600 HOUR | $1.00 | $70.00 | $100 | $50.00 | $80.00 | $10.00 | $85.00 | $125 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $10.00 | $2,220 | $1.00 | $1,500 | $2,113 | $500 | $2,113 | $5,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 28 EACH | $15.00 | $14.57 | $1.00 | $14.57 | $14.57 | $14.57 | $14.57 | $35.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 14 EACH | $25.00 | $21.61 | $1.00 | $21.61 | $21.61 | $21.61 | $21.61 | $25.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $100 | $1,156 | $1,000 | $1,156 | $1,156 | $1,156 | $1,156 | $2,300 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.08 MILE | $9,000 | $8,685 | $50.00 | $8,685 | $8,685 | $8,685 | $8,685 | $125 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 48 FT | $20.00 | $18.57 | $1.00 | $18.57 | $18.57 | $18.57 | $18.57 | $12.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,100 FT | $0.10 | $44.83 | $0.10 | $30.00 | $44.83 | $10.00 | $44.83 | $75.00 |
| 690E98400 SPECIAL - MISC.: WORK INVOLVING ASBESTOS CONTAININ | 1 LS | $1,000 | $10,000 | $100 | $5,000 | $750 | $1,000 | $1,100 | $18,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100 | $30,000 | $1.00 | $5,000 | $100 | $2,000 | $15,000 | $250,000 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 704 SF | $20.00 | $26.60 | $20.00 | $5.00 | $50.00 | $7.00 | $37.00 | $5.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 704 SF | $20.00 | $26.60 | $10.00 | $5.00 | $25.00 | $7.00 | $37.00 | $5.00 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 704 SF | $20.00 | $26.60 | $10.00 | $5.00 | $15.00 | $7.00 | $55.00 | $5.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 2 MNHR | $200 | $50.00 | $100 | $150 | $150 | $200 | $100 | $125 |
| 514E10000 FINAL INSPECTION REPAIR | 1 EACH | $200 | $50.00 | $100 | $200 | $300 | $300 | $550 | $500 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 5,203 SF | $5.00 | $4.62 | $10.00 | $5.00 | $10.00 | $2.50 | $6.00 | $3.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 5,203 SF | $3.00 | $4.62 | $5.00 | $5.00 | $3.00 | $2.50 | $5.50 | $2.00 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 5,203 SF | $2.00 | $4.62 | $5.00 | $5.00 | $3.00 | $2.50 | $8.75 | $2.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 7 MNHR | $200 | $50.00 | $100 | $150 | $150 | $200 | $100 | $125 |
| 514E10000 FINAL INSPECTION REPAIR | 5 EACH | $200 | $50.00 | $100 | $200 | $150 | $300 | $550 | $350 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 28 MNHR | $200 | $50.00 | $100 | $150 | $150 | $200 | $100 | $125 |
| 514E10000 FINAL INSPECTION REPAIR | 30 EACH | $150 | $50.00 | $100 | $200 | $150 | $300 | $450 | $350 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 25 SF | $400 | $279 | $850 | $850 | $990 | $300 | $850 | $1,000 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $5,000 | $3,675 | $2,000 | $1,000 | $3,000 | $4,000 | $1,000 | $100,000 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 0.2 CY | $25,000 | $24,230 | $2,000 | $5,000 | $23,000 | $30,000 | $5,000 | $1,500 |
| 512E10101 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE), AS | 903 SY | $28.00 | $40.00 | $40.00 | $35.00 | $28.00 | $35.00 | $35.00 | $45.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 903 SY | $25.00 | $40.00 | $30.00 | $25.00 | $30.00 | $35.00 | $25.00 | $20.00 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 15,965 SF | $1.00 | $3.01 | $2.00 | $2.00 | $6.00 | $2.50 | $4.50 | $3.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 15,965 SF | $1.00 | $3.01 | $2.00 | $2.00 | $4.00 | $2.50 | $5.90 | $2.00 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 15,965 SF | $1.00 | $3.01 | $2.00 | $2.00 | $2.50 | $2.50 | $5.20 | $2.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 21 MNHR | $200 | $50.00 | $100 | $150 | $150 | $200 | $100 | $125 |
| 514E10000 FINAL INSPECTION REPAIR | 14 EACH | $150 | $50.00 | $100 | $200 | $150 | $300 | $450 | $350 |
| 517E75001 RAILING, ALUMINUM, AS PER PLAN | 14 FT | $125 | $125 | $125 | $125 | $125 | $200 | $125 | $3,500 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 164 FT | $80.00 | $71.00 | $150 | $150 | $145 | $100 | $150 | $300 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 35 MNHR | $200 | $50.00 | $100 | $150 | $150 | $200 | $100 | $125 |
| 514E10000 FINAL INSPECTION REPAIR | 39 EACH | $100 | $50.00 | $100 | $200 | $150 | $300 | $450 | $350 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 8 SF | $300 | $279 | $850 | $850 | $1,205 | $400 | $850 | $1,500 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 5,853 SF | $3.00 | $4.14 | $5.00 | $3.00 | $3.00 | $2.50 | $6.70 | $2.00 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 5,853 SF | $1.00 | $4.14 | $5.00 | $3.00 | $3.00 | $2.50 | $7.50 | $2.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 11 MNHR | $200 | $50.00 | $100 | $150 | $150 | $200 | $100 | $125 |
| 514E10000 FINAL INSPECTION REPAIR | 5 EACH | $200 | $50.00 | $100 | $200 | $150 | $300 | $500 | $350 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,000 | $30,000 | $1,000 | $5,000 | $500 | $100 | $5,500 | $25,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 45,649 SF | $9 | $411k | 17% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 35,075 SF | $9 | $316k | 13% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $300,000 | $300k | 12% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 15,965 SF | $15 | $239k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $200k | 8% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 704 SF | $150 | $106k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,853 SF | $15 | $88k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 5,203 SF | $15 | $78k | 3% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 45,649 SF | $1 | $46k | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 45,649 SF | $1 | $46k | 2% |