D05-PM FY2024 (C) Epoxy
D05 County · est $0.8M
Bid dateThursday, February 8—
D05 County · est $0.8M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 646E10010 EDGE LINE, 6" | 38.7 MILE | $2,980 | $115k | 22% |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 52.67 MILE | $1,400 | $74k | 14% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1Oglesby Construction INC | R2Griffin Pavement Striping LLC | R3A & A Safety INC | % of bid |
|---|---|---|---|---|---|
| 646E10010 EDGE LINE, 6" | 38.7 MILE | $2,980 | $2,730 | $3,560 | 22% |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 52.67 MILE | $1,400 | $1,886 | $2,376 | 14% |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 8,286 FT | $7.00 | $8.20 | $11.60 | 11% |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 37,152 FT | $1.00 | $1.45 | $1.25 | 7% |
| 646E20300 LANE ARROW | 278 EACH | $125 | $180 | $200 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $72,810 | $100,000 | 5% |
| 646E20410 WORD ON PAVEMENT, 96" | 110 EACH | $200 | $230 |
| Item | Quantity | R1Oglesby Construction INC | R2Griffin Pavement Striping LLC | R3A & A Safety INC |
|---|---|---|---|---|
| 646E10510 CROSSWALK LINE, 12" | 432 FT | $3.80 | $5.00 | $7.90 |
| 646E20504 DOTTED LINE, 6" | 2,329 FT | $0.50 | $1.50 | $1.40 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $125 | $1,000 | $1,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $225 |
| 4% |
| 646E10400 STOP LINE | 2,932 FT | $7.50 | $9.00 | $12.35 | 4% |
| 646E10300 CHANNELIZING LINE, 8" | 17,131 FT | $1.25 | $2.15 | $1.50 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $21,000 | $34,150 | $20,000 | 4% |
| 646E10200 CENTER LINE | 8.28 MILE | $2,300 | $5,290 | $5,140 | 4% |
| 646E10310 CHANNELIZING LINE, 12" | 9,416 FT | $1.75 | $2.55 | $1.75 | 3% |
| 646E50000 REMOVAL OF PAVEMENT MARKING | 403 EACH | $40.00 | $90.00 | $250 | 3% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 150 HOUR | $70.00 | $65.00 | $75.00 | 2% |
| 646E10110 LANE LINE, 6" | 5.95 MILE | $1,520 | $1,880 | $1,260 | 2% |
| 646E10800 ISLAND MARKING | 1,970 SF | $4.50 | $3.90 | $7.90 | 2% |
| 646E20320 WRONG WAY ARROW | 30 EACH | $200 | $280 | $350 | 1% |
| 646E50200 REMOVAL OF PAVEMENT MARKING | 1,970 SF | $3.00 | $1.80 | $3.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,500 | $9,000 | $6,220 | 1% |
| 646E90000 PAVEMENT MARKING, MISC.: SPEED REDUCTION MARKINGS | 333 FT | $6.75 | $16.00 | $100 | 0% |
| 8,286 FT |
| $7 |
| $58k |
| 11% |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 37,152 FT | $1 | $37k | 7% |
| 646E20300 LANE ARROW | 278 EACH | $125 | $35k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $27k | 5% |
| 646E20410 WORD ON PAVEMENT, 96" | 110 EACH | $200 | $22k | 4% |
| 646E10400 STOP LINE | 2,932 FT | $7.5 | $22k | 4% |
| 646E10300 CHANNELIZING LINE, 8" | 17,131 FT | $1.25 | $21k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $21,000 | $21k | 4% |