NOB-SR 513-09.17
NOB County · est $1.3M
Bid dateThursday, February 22—
NOB County · est $1.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 50 more items below.
| Item | Quantity | R1Black Horse Bridge Construction INC | R2Shelly & Sands INC | R3Complete General Construction Company | R4Ohio-west Virginia Excavating CO | % of bid |
|---|---|---|---|---|---|---|
| 511E33310 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 267 CY | $1,125 | $1,455 | $1,100 | $2,100 | 25% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 249.33 FT | $480 | $470 | $490 | $600 | 10% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 64,876 LB | $1.75 | $1.70 | $2.00 | $2.00 | 10% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $84,500 | $65,000 | $100,000 | $95,000 | 7% |
| 526E25001 REINFORCED CONCRETE APPROACH SLABS (T=15"), AS PER | 167 SY | $390 | $380 | $450 | $525 | 6% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 59 CY | $815 | $1,700 | $1,500 |
| Item | Quantity | R1Black Horse Bridge Construction INC | R2Shelly & Sands INC | R3Complete General Construction Company | R4Ohio-west Virginia Excavating CO |
|---|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" AND UNDER | 127 FT | $12.00 | $8.65 | $75.00 | $35.00 |
| 202E38000 GUARDRAIL REMOVED | 476 FT | $3.00 | $2.70 | $2.00 | $8.00 |
| 203E20000 EMBANKMENT | 462 CY | $22.00 | $15.00 | $25.00 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 511 SY | $5.00 | $6.50 | $9.00 | $6.00 |
| 606E15050 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1,200 |
| 4% |
| 203E10000 EXCAVATION | 1,249 CY | $36.00 | $33.00 | $20.00 | $23.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $77,000 | $40,000 | 3% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 78 CY | $500 | $500 | $525 | $300 | 3% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $36,000 | $30,000 | $25,000 | $4,000 | 3% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 244 CY | $146 | $80.00 | $90.00 | $120 | 3% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $32,500 | $46,900 | $60,000 | $25,000 | 3% |
| 507E71200 SPECIAL - PILE ENCASEMENT | 141 FT | $225 | $155 | $225 | $125 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $31,650 | $34,000 | $35,000 | $40,000 | 3% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 95 SY | $325 | $150 | $110 | $100 | 3% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $30,500 | $30,000 | $3,000 | $5,000 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $13,500 | $55,000 | $50,000 | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 48 CY | $500 | $500 | $519 | $325 | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 684 FT | $30.00 | $17.00 | $30.00 | $15.00 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $19,500 | $7,000 | $10,000 | $20,000 | 2% |
| 425 FT |
| $19.20 |
| $19.20 |
| $19.20 |
| $42.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 1 EACH | $1,570 | $1,570 | $1,570 | $2,600 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 3 EACH | $1,340 | $1,340 | $1,340 | $2,200 |
| 606E34600 MGS BRIDGE TERMINAL ASSEMBLY, TYPE TST-2 | 4 EACH | $2,320 | $2,320 | $2,320 | $2,800 |
| 659E10000 SEEDING AND MULCHING | 3,329 SY | $1.50 | $1.25 | $1.15 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.3 TON | $983 | $1,400 | $1,400 | $1,000 |
| 659E31000 LIME | 0.69 ACRE | $158 | $150 | $150 | $600 |
| 659E35000 WATER | 9 MGAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 44 FT | $30.00 | $25.00 | $12.00 | $35.00 |
| 611E06400 15" CONDUIT, TYPE D | 45 FT | $85.00 | $65.00 | $150 | $120 |
| 611E10900 24" CONDUIT, TYPE D | 90 FT | $105 | $100 | $295 | $160 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE | — | $6.00 | $25.00 | $16.00 | $8.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE | — | $6.00 | $25.00 | $16.00 | $10.00 |
| 304E20000 AGGREGATE BASE | 106 CY | $125 | $135 | $125 | $150 |
| 407E20000 NON-TRACKING TACK COAT | 144 GAL | $3.50 | $3.50 | $5.00 | $9.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 18 EACH | $100 | $17.00 | $60.00 | $21.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 5 EACH | $10.00 | $10.00 | $10.00 | $125 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 6 EACH | $85.00 | $85.00 | $85.00 | $225 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $15.00 | $15.00 | $15.00 | $125 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 5 EACH | $125 | $125 | $125 | $225 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.26 MILE | $3,250 | $3,250 | $3,250 | $3,500 |
| 642E00300 CENTER LINE, TYPE 1 | 0.13 MILE | $5,500 | $5,500 | $5,500 | $6,500 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,320 | $2,320 | $2,320 | $3,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, (BIDIRECTIONAL) | 34 EACH | $12.00 | $8.00 | $30.00 | $35.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 34 EACH | $32.00 | $14.00 | $32.00 | $40.00 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.39 MILE | $7,250 | $3,550 | $3,550 | $4,000 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 20 FT | $14.00 | $14.00 | $14.00 | $15.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $1,800 | $4,000 | $20,000 | $4,000 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 108 FT | $55.00 | $52.00 | $45.00 | $25.00 |
| 202E23500 WEARING COURSE REMOVED | 342 SY | $12.00 | $13.00 | $35.00 | $8.00 |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 385 FT | $32.00 | $28.00 | $40.00 | $35.00 |
| 507E00150 STEEL PILES HP10X42, DRIVEN | 315 FT | $12.00 | $50.00 | $35.00 | $65.00 |
| 507E00200 STEEL PILES HP12X53, FURNISHED | 390 FT | $40.00 | $35.00 | $40.00 | $45.00 |
| 507E00250 STEEL PILES HP12X53, DRIVEN | 330 FT | $12.00 | $50.00 | $35.00 | $68.00 |
| 507E00410 STEEL PILES, MISC.: PILE SPLICE | 4 EACH | $750 | $135 | $750 | $750 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 162 SY | $35.00 | $17.00 | $16.75 | $45.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 58 SF | $10.00 | $4.00 | $17.00 | $5.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 86 SF | $14.00 | $6.50 | $12.00 | $7.00 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 371 SF | $12.00 | $14.00 | $12.00 | $12.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 52 CY | $132 | $145 | $195 | $175 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 274.38 FT | $20.00 | $17.00 | $16.50 | $15.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 104 FT | $16.00 | $7.00 | $15.00 | $10.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 92 FT | $20.00 | $6.50 | $15.00 | $10.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,450 | $8,312 | $16,000 | $22,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $12,000 | $15,000 | $7,000 | $7,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E33310 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 267 CY | $1,125 | $300k | 22% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 249.33 FT | $480 | $120k | 9% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 64,876 LB | $1.75 | $114k | 8% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $84,500 | $85k | 6% |
| 526E25001 REINFORCED CONCRETE APPROACH SLABS (T=15"), AS PER | 167 SY | $390 | $65k | 5% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 59 CY | $815 | $48k | 3% |
| 203E10000 EXCAVATION | 1,249 CY | $36 | $45k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 78 CY | $500 | $39k | 3% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $36,000 | $36k | 3% |