D08-Bridge/Wall Repairs
D08 County · est $1.2M
Bid dateThursday, April 18—
D08 County · est $1.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 42 more items below.
| Item | Quantity | R1Sunesis Construction CO | R2John R Jurgensen Company | R3Prus Construction Company | R4Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 330 FT | $456 | $250 | $230 | $975 | 17% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $120,910 | $79,385 | $135,000 | $125,000 | 13% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 74 CY | $1,589 | $1,678 | $1,525 | $1,800 | 13% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $86,349 | $103,066 | $105,000 | $275,000 | 9% |
| 507E00400 STEEL PILES, MISC.:W24X84 | 690 FT | $123 | $122 | $125 | $150 | 9% |
| 511E81300 CONCRETE, MISC.:CONCRETE LAGGING PANEL 1 | 105 EACH | $462 | $575 | $455 |
| Item | Quantity | R1Sunesis Construction CO | R2John R Jurgensen Company | R3Prus Construction Company | R4Complete General Construction Company |
|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 342 SY | $17.27 | $17.45 | $40.00 | $25.00 |
| 202E38000 GUARDRAIL REMOVED | 312.5 FT | $6.55 | $6.50 | $7.15 | $6.50 |
| 203E10000 EXCAVATION | 60 CY | $132 | $70.13 | $100 | $45.00 |
| 203E20000 EMBANKMENT | 80 CY | $35.02 | $80.14 | $80.00 | $60.00 |
| 659E00100 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $500 |
| 5% |
| 624E10000 MOBILIZATION | 1 LS | $41,234 | $40,000 | $40,000 | $85,000 | 5% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 70 CY | $505 | $553 | $675 | $750 | 4% |
| 520E10000 PNEUMATICALLY PLACED CONCRETE SHOTCRETE | 130 SF | $245 | $170 | $280 | $228 | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 63 CY | $479 | $475 | $420 | $475 | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 16,290 LB | $1.75 | $1.40 | $1.75 | $2.00 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,208 | $22,907 | $40,000 | $50,000 | 3% |
| 832E30000 EROSION CONTROL | 20,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 530E51020 SPECIAL - RETAINING WALL, TIMBER LAGGING | 6,545 SF | $2.26 | $1.00 | $26.50 | $18.40 | 2% |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 1 LS | $13,123 | $8,592 | $23,000 | $17,000 | 1% |
| 511E81300 CONCRETE, MISC.:CONCRETE LAGGING PANEL 2 | 28 EACH | $456 | $548 | $490 | $500 | 1% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (20 CY | $630 | $625 | $575 | $625 | 1% |
| 601E32004 ROCK CHANNEL PROTECTION, TYPE A WITH GEOTEXTILE FA | 50 CY | $238 | $362 | $390 | $140 | 1% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 82 FT | $144 | $503 | $225 | $700 | 1% |
| 606E13050 GUARDRAIL, TYPE 5A | 312.5 FT | $37.31 | $37.00 | $40.70 | $37.00 | 1% |
| 2 EACH |
| $101 |
| $200 |
| $200 |
| $300 |
| 659E00300 TOPSOIL | 23 CY | $45.38 | $4.15 | $195 | $80.00 |
| 659E10000 SEEDING AND MULCHING | 200 SY | $4.73 | $15.00 | $16.50 | $15.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.03 TON | $1,412 | $800 | $2,200 | $900 |
| 659E31000 LIME | 0.05 ACRE | $202 | $15.00 | $660 | $20.00 |
| 659E35000 WATER | 2 MGAL | $1.40 | $1.00 | $11.00 | $1.00 |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 2 CY | $206 | $542 | $525 | $350 |
| 602E20000 CONCRETE MASONRY | 0.63 CY | $9,266 | $8,035 | $6,000 | $3,000 |
| 605E06000 4" BASE PIPE UNDERDRAINS | 272 FT | $15.81 | $33.24 | $25.00 | $30.00 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 5 FT | $27.86 | $93.79 | $75.00 | $225 |
| 611E10600 24" CONDUIT, TYPE C, 706.02 | 5 FT | $452 | $857 | $800 | $700 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $1,131 | $678 | $500 | $400 |
| 204E10000 SUBGRADE COMPACTION | 411 SY | $7.00 | $4.54 | $3.00 | $4.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3'' DEEP | 45 SY | $90.75 | $90.00 | $55.00 | $90.00 |
| 304E20000 AGGREGATE BASE | 66 CY | $149 | $161 | $125 | $135 |
| 407E10000 TACK COAT | 47 GAL | $10.08 | $10.00 | $8.25 | $10.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 15 CY | $655 | $650 | $690 | $650 |
| 621E00100 RPM | 7 EACH | $331 | $329 | $360 | $329 |
| 644E00100 EDGE LINE, 4" | 0.06 MILE | $19,567 | $19,405 | $21,346 | $19,405 |
| 644E00300 CENTER LINE | 0.06 MILE | $39,132 | $38,808 | $42,689 | $38,808 |
| 510E09950 DOWEL HOLES WITH CEMENT GROUT | 6 EACH | $28.64 | $115 | $110 | $60.00 |
| 511E81300 CONCRETE, MISC.:CONCRETE LAGGING PANEL 3 | 3 EACH | $442 | $535 | $570 | $725 |
| 511E81300 CONCRETE, MISC.:CONCRETE LAGGING PANEL 4 | 1 EACH | $442 | $535 | $900 | $975 |
| 511E81300 CONCRETE, MISC.:CONCRETE LAGGING PANEL 5 | 1 EACH | $1,188 | $1,195 | $1,500 | $1,200 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 352 SY | $30.25 | $23.50 | $55.00 | $23.50 |
| 512E33000 TYPE 2 WATERPROOFING | 18 SY | $35.29 | $70.35 | $70.00 | $40.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 52 SF | $4.40 | $10.05 | $20.00 | $14.00 |
| 518E20000 PREFABRICATED GEOCOMPOSITE DRAIN | 251 SY | $36.16 | $6.50 | $28.00 | $40.00 |
| 518E21101 POROUS BACKFILL, AS PER PLAN | 60 CY | $128 | $204 | $150 | $125 |
| 530E50000 SPECIAL - RETAINING WALL, L8x6x3/4 | 1 EACH | $1,812 | $4,526 | $2,000 | $1,400 |
| 690E98400 SPECIAL - CONSULTANT CONCRETE QUALITY CONTROL INCL | 1 LS | $3,781 | $12,698 | $15,000 | $15,000 |
| 840E21000 WALL EXCAVATION | 3 CY | $1,369 | $501 | $70.00 | $800 |
| 840E23050 NATURAL SOIL | 3 CY | $122 | $275 | $200 | $1,400 |
| 518E20000 PREFABRICATED GEOCOMPOSITE DRAIN | 28 SY | $77.05 | $6.50 | $46.00 | $50.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $0.01 | $2,448 | $11,500 | $11,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,169 | $80,077 | $40,000 | $25,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,042 | $5,167 | $17,000 | $21,000 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,066 | $4,955 | $5,450 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 330 FT | $455.85 | $150k | 14% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $120,910 | $121k | 12% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 74 CY | $1,589 | $118k | 11% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $86,349 | $86k | 8% |
| 507E00400 STEEL PILES, MISC.:W24X84 | 690 FT | $123.18 | $85k | 8% |
| 511E81300 CONCRETE, MISC.:CONCRETE LAGGING PANEL 1 | 105 EACH | $461.8 | $48k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $41,234 | $41k | 4% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 70 CY | $504.73 | $35k | 3% |
| 520E10000 PNEUMATICALLY PLACED CONCRETE SHOTCRETE | 130 SF | $245.41 | $32k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 63 CY | $478.96 | $30k | 3% |