| Item | Quantity | R1A P O'horo Company | R2Shelly & Sands INC | R3Marucci & Gaffney Excavating CO | R4Great Lakes Construction CO | R5Rudzik Excavating INC | R6Ruhlin Company | R7S E T INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 61,413 SF | $27.00 | $25.00 | $25.54 | $25.65 | $27.10 | $31.00 | $40.00 | 45% |
| 622E90000 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB | 3,450 FT | $175 | $190 | $198 | $200 | $223 | $179 | $215 | 16% |
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P |
| Item | Quantity | R1A P O'horo Company | R2Shelly & Sands INC | R3Marucci & Gaffney Excavating CO | R4Great Lakes Construction CO | R5Rudzik Excavating INC | R6Ruhlin Company | R7S E T INC |
|---|---|---|---|---|---|---|---|---|
| 202E30700 CONCRETE BARRIER REMOVED | 77 FT | $35.00 | $30.00 | $39.55 | $40.00 | $40.00 | $55.00 | $30.00 |
| 202E38000 GUARDRAIL REMOVED | 662 FT | $2.50 | $2.60 | $2.50 | $2.50 | $4.00 | $2.50 | $3.00 |
| 202E38500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 2,279 SY |
| $88.00 |
| $72.00 |
| $87.00 |
| $70.00 |
| $110 |
| $75.00 |
| $135 |
| 5% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 1,384 CY | $120 | $110 | $71.25 | $140 | $100 | $142 | $120 | 5% |
| 606E10920 SPECIAL - NOISE BARRIER (REFLECTIVE WITH ICON) | 4,392 SF | $36.00 | $21.00 | $25.87 | $26.00 | $27.10 | $38.00 | $45.00 | 4% |
| 832E30000 EROSION CONTROL | 143,689 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $141,000 | $125,000 | $110,000 | $55,400 | $82,500 | $80,000 | $50,000 | 4% |
| 622E90200 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB, END ANCH | 19 EACH | $6,000 | $5,000 | $6,000 | $5,750 | $16,500 | $7,400 | $5,250 | 3% |
| 611E99500 INLET, MISC.: INLET NO. 3 FOR 81" SINGLE SLOPE BAR | 7 EACH | $15,000 | $13,000 | $19,400 | $21,000 | $24,515 | $19,200 | $6,500 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $100,000 | $215,000 | $33,440 | $150,000 | $200,000 | 3% |
| 203E10000 EXCAVATION | 2,690 CY | $20.00 | $14.00 | $25.00 | $30.00 | $19.35 | $20.00 | $30.00 | 1% |
| 622E90200 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB, END SECT | 2 EACH | $20,000 | $35,000 | $27,935 | $24,500 | $16,794 | $22,800 | $26,000 | 1% |
| 659E10000 SEEDING AND MULCHING | 41,224 SY | $0.83 | $0.90 | $1.00 | $1.55 | $0.85 | $1.55 | $2.00 | 1% |
| 304E20000 AGGREGATE BASE | 419 CY | $80.00 | $80.00 | $97.53 | $125 | $88.50 | $110 | $80.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $27,648 | $24,000 | $23,350 | $30,000 | $40,918 | $35,000 | $40,000 | 1% |
| 659E00300 TOPSOIL | 5,008 CY | $5.00 | $8.00 | $19.00 | $20.00 | $11.00 | $39.00 | $70.00 | 1% |
| 441E70801 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (19 CY | $1,291 | $850 | $900 | $600 | $725 | $1,291 | $1,500 | 1% |
| 622E90200 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB, END SECT | 1 EACH | $20,000 | $37,000 | $26,770 | $23,000 | $16,800 | $10,740 | $7,000 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 10 MNTH | $2,000 | $3,300 | $1,400 | $3,700 | $1,400 | $2,640 | $2,000 | 1% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 4,892 FT | $4.00 | $18.00 | $22.00 | $24.50 | $22.50 | $24.00 | $18.00 | 1% |
| 12 FT |
| $125 |
| $74.00 |
| $33.33 |
| $50.00 |
| $375 |
| $95.00 |
| $50.00 |
| 202E75000 FENCE REMOVED | 5,114 FT | $2.50 | $4.80 | $3.00 | $3.00 | $3.00 | $3.00 | $4.00 |
| 202E98100 REMOVAL MISC.: INSPECTION WELL | 5 EACH | $200 | $350 | $5.00 | $600 | $100 | $485 | $500 |
| 202E98200 REMOVAL MISC.: CONDUIT | 25 FT | $12.00 | $30.00 | $10.00 | $50.00 | $5.00 | $95.00 | $30.00 |
| 203E20000 EMBANKMENT | 1,854 CY | $8.00 | $27.00 | $25.00 | $6.00 | $24.00 | $23.00 | $22.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 50 CY | $15.00 | $56.00 | $10.00 | $50.00 | $30.75 | $45.00 | $30.00 |
| 203E98000 ROADWAY, MISC.: TEMPORARY OVER-STEEPENED FILL | 260 CY | $22.00 | $20.00 | $28.00 | $10.00 | $55.00 | $80.00 | $40.00 |
| 204E10000 SUBGRADE COMPACTION | 2,504 SY | $2.50 | $0.60 | $3.50 | $1.34 | $2.50 | $2.25 | $2.00 |
| 204E45000 PROOF ROLLING | 2 HOUR | $75.00 | $250 | $85.00 | $350 | $200 | $575 | $200 |
| 209E60201 LINEAR GRADING, AS PER PLAN | 3 STA | $350 | $900 | $500 | $500 | $300 | $600 | $500 |
| 606E15050 GUARDRAIL, TYPE MGS | 100 FT | $31.20 | $33.00 | $31.20 | $31.20 | $34.35 | $31.20 | $35.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,920 | $3,000 | $2,920 | $2,920 | $3,215 | $2,920 | $3,000 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 2 EACH | $2,960 | $3,000 | $2,960 | $2,960 | $3,260 | $2,960 | $3,000 |
| 607E23000 FENCE, TYPE CLT | 77 FT | $45.00 | $45.00 | $45.00 | $45.00 | $59.50 | $45.00 | $50.00 |
| 607E98000 FENCE, MISC.: TEMPORARY FENCE | 5,114 FT | $2.50 | $4.00 | $7.00 | $3.25 | $5.10 | $7.00 | $8.00 |
| 609E24510 CURB, TYPE 4-C | 38 FT | $50.00 | $69.00 | $50.00 | $120 | $115 | $83.51 | $55.00 |
| 622E90200 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB, WINDOW S | 1 EACH | $12,000 | $10,000 | $15,450 | $10,500 | $16,800 | $20,800 | $26,000 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $100 | $5,000 | $2,500 | $50.00 | $5,000 | $4,250 | $20,000 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION | 1 LS | $5,000 | $5,000 | $3,500 | $7,500 | $5,000 | $4,250 | $6,000 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 84 SY | $110 | $120 | $190 | $145 | $160 | $95.00 | $130 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 6 CY | $250 | $290 | $95.00 | $350 | $200 | $650 | $175 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $130 | $10.00 | $25.00 | $50.00 | $25.00 | $150 |
| 659E14000 REPAIR SEEDING AND MULCHING | 2,062 SY | $0.80 | $0.85 | $0.27 | $1.55 | $0.50 | $1.55 | $1.50 |
| 659E15000 INTER-SEEDING | 2,062 SY | $0.80 | $0.85 | $0.27 | $0.10 | $0.50 | $0.01 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 5.75 TON | $887 | $900 | $250 | $250 | $700 | $25.00 | $900 |
| 659E31000 LIME | 8.52 ACRE | $153 | $160 | $10.00 | $25.00 | $1.00 | $25.00 | $200 |
| 659E35000 WATER | 229 MGAL | $1.00 | $1.00 | $0.01 | $1.00 | $1.00 | $1.00 | $10.00 |
| 670E00500 SLOPE EROSION PROTECTION | 3,878 SY | $1.50 | $1.60 | $3.00 | $1.25 | $10.00 | $1.25 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $5,000 | $2,300 | $2,180 | $2,250 | $2,400 | $2,200 | $3,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,000 | $12,000 | $7,760 | $2,500 | $9,630 | $11,640 | $15,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $2,000 | $13,000 | $10,000 | $12,000 | $12,000 | $12,100 | $18,000 |
| 602E20000 CONCRETE MASONRY | 1.89 CY | $2,300 | $3,400 | $2,580 | $4,000 | $3,455 | $3,000 | $4,000 |
| 605E31100 AGGREGATE DRAINS | 50 FT | $30.00 | $36.00 | $10.00 | $15.00 | $30.00 | $25.00 | $15.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 301 FT | $24.00 | $27.00 | $25.00 | $30.00 | $26.00 | $57.56 | $25.00 |
| 611E06100 15" CONDUIT, TYPE C | 141 FT | $62.00 | $143 | $153 | $125 | $165 | $115 | $115 |
| 611E06700 15" CONDUIT, TYPE F | 86 FT | $90.00 | $100 | $182 | $100 | $175 | $175 | $100 |
| 611E97400 CONDUIT, MISC.: TYPE B FOR DRAINAGE DISCHARGE CONT | 25 FT | $14.00 | $40.00 | $8.00 | $50.00 | $20.50 | $142 | $130 |
| 611E97400 CONDUIT, MISC.: TYPE C FOR DRAINAGE DISCHARGE CONT | 25 FT | $12.00 | $40.00 | $6.00 | $50.00 | $20.50 | $142 | $120 |
| 611E97400 CONDUIT, MISC.: TYPE E FOR DRAINAGE DISCHARGE CONT | 25 FT | $9.00 | $40.00 | $6.00 | $50.00 | $20.50 | $142 | $115 |
| 611E97400 CONDUIT, MISC.: TYPE F FOR DRAINAGE DISCHARGE CONT | 25 FT | $9.00 | $40.00 | $6.00 | $50.00 | $20.50 | $142 | $115 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 17 EACH | $210 | $400 | $300 | $400 | $700 | $580 | $400 |
| 611E99720 INSPECTION WELL | 5 EACH | $500 | $450 | $10.00 | $2,000 | $360 | $1,200 | $1,200 |
| 407E20000 NON-TRACKING TACK COAT | 137 GAL | $3.00 | $3.15 | $10.00 | $4.00 | $20.00 | $3.00 | $4.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 20 CY | $916 | $850 | $900 | $600 | $875 | $916 | $1,000 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 4,050 FT | $2.00 | $0.30 | $2.00 | $1.50 | $2.50 | $2.00 | $5.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 33.8 FT | $20.00 | $20.00 | $20.00 | $12.00 | $22.00 | $20.00 | $25.00 |
| 630E80100 SIGN, FLAT SHEET | 49.5 SF | $32.00 | $34.00 | $32.00 | $16.00 | $36.00 | $32.00 | $35.00 |
| 630E80100 SIGN, FLAT SHEET (TYPE 730.20) | 1 SF | $50.00 | $54.00 | $50.00 | $57.00 | $55.00 | $50.00 | $55.00 |
| 630E81021 CONCRETE MEDIAN BARRIER SIGN BRACKET, AS PER PLAN | 6 EACH | $780 | $830 | $780 | $400 | $980 | $780 | $800 |
| 630E82000 SIGN BACKING ASSEMBLY | 2 EACH | $325 | $345 | $325 | $148 | $360 | $325 | $350 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 6 EACH | $10.00 | $10.00 | $10.00 | $25.00 | $10.00 | $10.00 | $15.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 9 EACH | $15.00 | $16.00 | $15.00 | $26.00 | $15.00 | $15.00 | $20.00 |
| 644E00204 LANE LINE, 6" | 0.83 MILE | $6,975 | $7,400 | $6,975 | $6,975 | $7,700 | $6,975 | $7,500 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 300 HOUR | $50.00 | $90.00 | $60.00 | $95.00 | $75.00 | $90.00 | $90.00 |
| 614E12484 WORK ZONE INCREASED PENALTIES SIGN | 3 EACH | $250 | $260 | $248 | $200 | $275 | $248 | $250 |
| 614E12801 WORK ZONE RAISED PAVEMENT MARKER, AS PER PLAN | 239 EACH | $8.15 | $8.50 | $45.85 | $7.35 | $9.00 | $8.15 | $50.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $500 | $950 | $1,025 | $750 | $990 | $1,025 | $1,100 |
| 614E22326 WORK ZONE EDGE LINE, CLASS I, 6", 873 | 1.77 MILE | $10,709 | $11,000 | $10,709 | $8,850 | $11,781 | $10,709 | $11,000 |
| 614E23130 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 873 | 3,120 FT | $4.77 | $5.00 | $4.77 | $3.80 | $5.30 | $4.77 | $5.00 |
| 614E24122 WORK ZONE DOTTED LINE, CLASS I, 6", 873 | 1,880 FT | $1.79 | $2.00 | $1.79 | $1.95 | $2.00 | $1.79 | $2.00 |
| 616E10000 WATER | 50 MGAL | $1.00 | $42.00 | $0.01 | $50.00 | $0.10 | $102 | $40.00 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 18 SNMT | $500 | $770 | $722 | $595 | $885 | $722 | $750 |
| 517E74501 RAILING, CONCRETE, AS PER PLAN | 12 FT | $400 | $435 | $795 | $550 | $1,000 | $820 | $250 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,000 | $45,000 | $60,479 | $42,000 | $68,235 | $202,000 | $140,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $35,000 | $44,750 | $42,000 | $35,000 | $13,000 | $65,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 61,413 SF | $27 | $1.66M | 42% |
| 622E90000 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB | 3,450 FT | $175 | $604k | 15% |
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 2,279 SY | $88 | $201k | 5% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 1,384 CY | $120 | $166k | 4% |
| 606E10920 SPECIAL - NOISE BARRIER (REFLECTIVE WITH ICON) | 4,392 SF | $36 | $158k | 4% |
| 832E30000 EROSION CONTROL | 143,689 EACH | $1 | $144k | 4% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $141,000 | $141k | 4% |
| 622E90200 BARRIER, MISC.:CONCRETE BARRIER, 81" SSB, END ANCH | 19 EACH | $6,000 | $114k | 3% |
| 611E99500 INLET, MISC.: INLET NO. 3 FOR 81" SINGLE SLOPE BAR | 7 EACH | $15,000 | $105k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 3% |