| Item | Quantity | R1Shelly Company | R2Gerken Paving INC | R3Kokosing Construction Company INC | % of bid |
|---|---|---|---|---|---|
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (3184 CY | $182 | $182 | $182 | 25% |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (1476 CY | $228 | $245 | $270 | 14% |
| 253E02000 PAVEMENT REPAIR, 6" | 1,470 CY | $205 | $213 | $195 | 13% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1,504 CY | $188 | $215 | $230 | 12% |
| 253E02000 PAVEMENT REPAIR, 8" | 1,064 CY | $220 | $220 | $195 | 10% |
| 617E10100 COMPACTED AGGREGATE | 1,122 CY | $80.00 | $65.00 | $30.00 | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3" |
| Item | Quantity | R1Shelly Company | R2Gerken Paving INC | R3Kokosing Construction Company INC |
|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 3,545 SY | $3.00 | $3.85 | $2.50 |
| 202E30000 WALK REMOVED | 1,113 SF | $5.50 | $5.50 | $5.50 |
| 202E32000 CURB REMOVED | 23 FT | $15.00 | $15.00 | $15.00 |
| 202E38000 GUARDRAIL REMOVED | 412.5 FT | $2.00 | $2.00 | $2.00 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 2 EACH | $150 | $150 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 31,763 SY |
| $2.45 |
| $2.93 |
| $2.50 |
| 3% |
| 441E90000 ASPHALT CONCRETE, MISC.:BUTT JOINT AT INTERSECTION | 81 CY | $875 | $450 | $750 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $65,000 | $67,500 | $130,500 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3 1/4" | 20,855 SY | $2.45 | $2.58 | $3.00 | 2% |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 19,662 FT | $2.30 | $2.10 | $0.90 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $42,000 | $50,000 | $114,000 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 3/4" | 27,935 SY | $1.30 | $1.70 | $1.55 | 2% |
| 209E60500 LINEAR GRADING | 12.97 MILE | $2,500 | $2,500 | $750 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 10,040 GAL | $2.50 | $2.50 | $2.60 | 1% |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $300 | $525 | $230 | 1% |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 24.4 MILE | $800 | $800 | $750 | 1% |
| 608E52000 CURB RAMP | 871 SF | $22.00 | $22.00 | $22.00 | 1% |
| 621E00100 RPM | 415 EACH | $41.00 | $41.00 | $41.00 | 1% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 12.2 MILE | $900 | $900 | $1,200 | 0% |
| $150 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 3 EACH | $95.00 | $95.00 | $95.00 |
| 203E10000 EXCAVATION | 3 CY | $50.00 | $50.00 | $50.00 |
| 203E20000 EMBANKMENT | 21 CY | $60.00 | $60.00 | $60.00 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 5 STA | $75.00 | $75.00 | $75.00 |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 5.5 MILE | $1,500 | $625 | $2,500 |
| 606E15050 GUARDRAIL, TYPE MGS | 350 FT | $20.40 | $20.40 | $20.40 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 2 EACH | $2,640 | $2,640 | $2,640 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 3 EACH | $1,420 | $1,420 | $1,420 |
| 608E10000 4" CONCRETE WALK | 32 SF | $22.00 | $22.00 | $22.00 |
| 609E26000 CURB, TYPE 6 | 23 FT | $45.00 | $45.00 | $45.00 |
| 623E39600 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE | 2 EACH | $1,200 | $1,400 | $1,100 |
| 659E10000 SEEDING AND MULCHING | 228 SY | $2.00 | $2.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.02 TON | $1,500 | $1,500 | $1,500 |
| 659E35000 WATER | 1 MGAL | $50.00 | $50.00 | $50.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 4 EACH | $1,200 | $1,850 | $725 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 9 EACH | $1,200 | $1,850 | $725 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 3.73 MILE | $1,030 | $1,500 | $1,030 |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 3,093 LB | $1.00 | $1.75 | $0.50 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 1 EACH | $650 | $400 | $550 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 415 EACH | $8.00 | $11.50 | $4.00 |
| 626E00116 BARRIER REFLECTOR, TYPE 5 BIDIRECTIONAL | 9 EACH | $15.00 | $15.00 | $15.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 12.2 MILE | $800 | $800 | $800 |
| 642E00300 CENTER LINE, TYPE 1 | 6.35 MILE | $900 | $900 | $900 |
| 644E00500 STOP LINE | 37 FT | $10.00 | $10.00 | $10.00 |
| 644E00630 CROSSWALK LINE, 24" | 552 FT | $8.00 | $8.00 | $8.00 |
| 644E01000 RAILROAD SYMBOL MARKING | 2 EACH | $800 | $800 | $800 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $60.00 | $81.96 | $100 |
| 614E12460 WORK ZONE MARKING SIGN | 34 EACH | $95.00 | $115 | $95.00 |
| 614E12500 REPLACEMENT SIGN | 6 EACH | $192 | $125 | $192 |
| 614E12600 REPLACEMENT DRUM | 6 EACH | $64.00 | $55.00 | $64.00 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 2.33 MILE | $900 | $900 | $1,200 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 4.66 MILE | $800 | $800 | $750 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 74 FT | $4.00 | $4.00 | $3.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 37 FT | $4.00 | $4.00 | $3.00 |
| 614E27050 WORK ZONE CROSSWALK LINE, CLASS I, 12", 642 PAINT | 1,104 FT | $2.00 | $2.00 | $1.50 |
| 614E32200 WORK ZONE RAILROAD SYMBOL MARKING, CLASS I, 642 PA | 4 EACH | $300 | $300 | $250 |
| 614E32210 WORK ZONE RAILROAD SYMBOL MARKING, CLASS III, 642 | 2 EACH | $300 | $300 | $250 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $850 | $1,400 | $900 |
| 614E27250 WORK ZONE CROSSWALK LINE, CLASS III, 12", 642 PAIN | 552 FT | $2.00 | $2.00 | $1.50 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $2,000 | $5,500 | $1,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,500 | $6,400 | $10,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,460 | $10,000 | $3,400 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (3184 CY | $182 | $579k | 23% |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (1476 CY | $228 | $337k | 13% |
| 253E02000 PAVEMENT REPAIR, 6" | 1,470 CY | $205 | $301k | 12% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1,504 CY | $188 | $283k | 11% |
| 253E02000 PAVEMENT REPAIR, 8" | 1,064 CY | $220 | $234k | 9% |
| 617E10100 COMPACTED AGGREGATE | 1,122 CY | $80 | $90k | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3" | 31,763 SY | $2.45 | $78k | 3% |
| 441E90000 ASPHALT CONCRETE, MISC.:BUTT JOINT AT INTERSECTION | 81 CY | $875 | $71k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $65,000 | $65k | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3 1/4" | 20,855 SY | $2.45 | $51k | 2% |