CLE-SR 232-01.80
CLE County · est $0.5M
Bid dateThursday, September 12—
CLE County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 4 more items below.
| Item | Quantity | R1Axis Civil Construction LLC | R2Bcc Ohio INC | R3Ford Development CORP | R4Kt Holden Construction LLC | R5Turn-key Tunneling INC | % of bid |
|---|---|---|---|---|---|---|---|
| 837E10000 LINER PIPE, 132?, 748.06 OR 707.75 OR 707.18 | 120 FT | $1,430 | $1,128 | $1,815 | $1,500 | $1,950 | 50% |
| 837E21000 BACKFILL FOR LINER PIPE | 120 FT | $325 | $384 | $400 | $520 | $625 | 11% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 12.39 CY | $1,190 | $1,647 | $2,000 | $2,100 | $2,017 | 4% |
| 602E20000 CONCRETE MASONRY | 11.89 CY | $1,190 | $1,664 | $2,000 | $2,000 | $2,289 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $12,500 | $20,592 | $2,400 | $12,000 | $7,500 | 4% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 136 FT |
| Item | Quantity | R1Axis Civil Construction LLC | R2Bcc Ohio INC | R3Ford Development CORP | R4Kt Holden Construction LLC | R5Turn-key Tunneling INC |
|---|---|---|---|---|---|---|
| 659E20000 COMMERCIAL FERTILIZER | 0.22 TON | $300 | $588 | $400 | $560 | $2,126 |
| 659E31000 LIME | 0.33 ACRE | $350 | $42.00 | $100 | $40.00 | $1,635 |
| 659E35000 WATER | 8.6 MGAL | $1.00 | $1.05 | $10.00 | $1.00 | $1.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 6 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $90.00 |
| $82.59 |
| $150 |
| $300 |
| $300 |
| 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $22,558 | $10,000 | $23,500 | $34,800 | 3% |
| 601E11000 RIPRAP, TYPE D | 47.5 SY | $190 | $342 | $50.00 | $350 | $191 | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $8,500 | $15,417 | $4,000 | $35,000 | $48,000 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $7,500 | $3,510 | $3,000 | $12,600 | $18,300 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 212.5 FT | $29.50 | $34.02 | $33.00 | $32.40 | $35.32 | 2% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 144" C | 16 FT | $375 | $434 | $800 | $500 | $1,090 | 2% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,750 | $2,814 | $3,100 | $2,680 | $2,921 | 2% |
| 202E20010 HEADWALL REMOVED | 2 EACH | $2,500 | $3,795 | $500 | $3,200 | $1,635 | 1% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 659E10000 SEEDING AND MULCHING | 1,600 SY | $3.00 | $3.10 | $1.00 | $2.95 | $8.72 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $4,389 | $4,000 | $8,000 | $8,500 | 1% |
| 202E38000 GUARDRAIL REMOVED | 205 FT | $10.00 | $2.10 | $4.00 | $2.00 | $2.18 | 1% |
| 202E42001 ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER PLAN | 3 EACH | $550 | $310 | $100 | $295 | $322 | 0% |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,350 | $1,439 | $1,500 | $1,370 | $1,493 | 0% |
| $15.00 |
| $15.75 |
| $17.00 |
| $15.00 |
| $16.35 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 837E10000 LINER PIPE, 132?, 748.06 OR 707.75 OR 707.18 | 120 FT | $1,430 | $172k | 50% |
| 837E21000 BACKFILL FOR LINER PIPE | 120 FT | $325 | $39k | 11% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 12.39 CY | $1,190 | $15k | 4% |
| 602E20000 CONCRETE MASONRY | 11.89 CY | $1,190 | $14k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $12,500 | $13k | 4% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 136 FT | $90 | $12k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 601E11000 RIPRAP, TYPE D | 47.5 SY | $190 | $9k | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $8,500 | $9k | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $7,500 | $8k | 2% |