TRU-SR 7/SR 7D-08.74/00.00
TRU County · est $1.6M
Bid dateThursday, October 17—
TRU County · est $1.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 42 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Kirila Contractors INC | R3Karvo Companies INC | R4Cole Burton Contractors, LLC | R5Shelly Company | % of bid |
|---|---|---|---|---|---|---|---|
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 3,044 CY | $206 | $224 | $230 | $230 | $212 | 45% |
| 422E25000 EMULSION, CHIP SEAL | 29,217 GAL | $3.50 | $2.91 | $3.60 | $4.00 | $2.80 | 7% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 73,041 SY | $1.30 | $1.07 | $1.50 | $1.25 | $2.00 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $80,251 | $86,000 | $100,000 | $130,748 | $183,000 | 6% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441 | 1,800 SY | $40.00 | $21.25 | $35.00 | $35.00 | $50.00 | 5% |
| 253E01000 PAVEMENT REPAIR | 300 SY |
| Item | Quantity | R1Shelly & Sands INC | R2Kirila Contractors INC | R3Karvo Companies INC | R4Cole Burton Contractors, LLC | R5Shelly Company |
|---|---|---|---|---|---|---|
| 202E23500 WEARING COURSE REMOVED | 19 SY | $60.00 | $30.00 | $15.00 | $35.00 | $65.00 |
| 202E30000 WALK REMOVED | 318 SF | $15.00 | $15.00 | $15.00 | $4.50 | $10.00 |
| 202E32000 CURB REMOVED | 29 FT | $25.00 | $25.00 | $60.00 | $28.00 | $20.00 |
| 202E98100 REMOVAL MISC.: BARRIER REFLECTOR | 6 EACH | $2.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $160 |
| $116 |
| $75.00 |
| $135 |
| $120 |
| 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE | 36,520 SY | $1.25 | $1.98 | $1.25 | $1.25 | $2.00 | 3% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | 36,514 SY | $1.25 | $1.39 | $1.75 | $1.00 | $2.25 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $55,820 | $100,000 | $40,000 | $40,000 | 3% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 4 EACH | $8,850 | $8,850 | $8,850 | $8,850 | $8,850 | 3% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 491 CY | $70.00 | $100 | $100 | $65.00 | $100 | 2% |
| 646E10010 EDGE LINE, 6" | 8.25 MILE | $2,750 | $2,750 | $2,800 | $2,750 | $3,111 | 2% |
| 407E20000 NON-TRACKING TACK COAT @ 0.09 GAL/SY | 6,574 GAL | $3.05 | $3.42 | $2.75 | $3.50 | $3.00 | 1% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441 | 200 SY | $90.00 | $70.00 | $55.00 | $130 | $80.00 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $3,000 | $2,000 | $2,500 | $1,500 | $2,200 | 1% |
| 209E60200 LINEAR GRADING | 398 STA | $45.00 | $40.00 | $42.00 | $45.00 | $40.00 | 1% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 2 EACH | $8,950 | $8,950 | $8,950 | $8,950 | $8,950 | 1% |
| 646E10200 CENTER LINE | 3.76 MILE | $4,250 | $4,250 | $4,150 | $4,250 | $3,111 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 16 SNMT | $850 | $875 | $1,021 | $850 | $850 | 1% |
| 621E00100 RPM | 311 EACH | $43.45 | $63.25 | $43.45 | $48.50 | $44.00 | 1% |
| $2.50 |
| $5.00 |
| $2.50 |
| $2.50 |
| 203E10000 EXCAVATION | 50 CY | $40.00 | $60.00 | $15.00 | $20.00 | $50.00 |
| 203E10000 EXCAVATION | 1 CY | $1,500 | $1,500 | $150 | $250 | $1,000 |
| 608E10000 4" CONCRETE WALK | 88 SF | $10.00 | $10.00 | $35.00 | $20.00 | $25.00 |
| 608E52000 CURB RAMP | 166 SF | $35.00 | $35.00 | $35.00 | $115 | $37.00 |
| 608E53020 DETECTABLE WARNING | 104 SF | $37.50 | $37.50 | $25.00 | $143 | $38.00 |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 4 EACH | $2,000 | $2,000 | $3,000 | $2,150 | $1,400 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $2,000 | $1,000 | $572 | $8,000 | $5,000 |
| 659E10000 SEEDING AND MULCHING | 11,057 SY | $1.10 | $1.10 | $1.10 | $2.30 | $1.10 |
| 659E20000 COMMERCIAL FERTILIZER | 1.49 TON | $918 | $1,000 | $918 | $405 | $920 |
| 659E31000 LIME | 2.28 ACRE | $158 | $200 | $158 | $20.00 | $160 |
| 659E35000 WATER | 59.7 MGAL | $1.00 | $1.00 | $1.00 | $0.50 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 1,780 FT | $0.10 | $1.85 | $0.25 | $2.75 | $4.00 |
| 304E20000 AGGREGATE BASE | 50 CY | $50.00 | $75.00 | $25.00 | $80.00 | $60.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 3,535 GAL | $3.50 | $4.80 | $5.25 | $5.00 | $5.15 |
| 618E41000 RUMBLE STRIPES, EDGE LINE | 5.28 MILE | $865 | $950 | $865 | $875 | $865 |
| 618E43000 RUMBLE STRIPES, CENTER LINE | 2.64 MILE | $865 | $950 | $865 | $875 | $1,500 |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 13,940 FT | $0.75 | $0.75 | $1.00 | $1.50 | $1.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 210 EACH | $5.00 | $5.00 | $1.00 | $3.00 | $9.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 | 24 EACH | $25.00 | $25.00 | $11.96 | $25.00 | $25.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 72 FT | $17.50 | $17.50 | $29.53 | $17.50 | $17.50 |
| 630E80100 SIGN, FLAT SHEET | 50 SF | $37.50 | $37.50 | $32.18 | $37.50 | $37.50 |
| 646E10300 CHANNELIZING LINE, 8" | 295 FT | $2.00 | $2.00 | $2.00 | $2.00 | $1.80 |
| 646E10400 STOP LINE | 66 FT | $12.50 | $12.50 | $12.00 | $12.50 | $16.00 |
| 646E10520 CROSSWALK LINE, 24" | 262 FT | $12.50 | $12.50 | $11.50 | $12.50 | $15.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 10 FT | $15.00 | $15.00 | $11.25 | $15.00 | $15.00 |
| 646E20300 LANE ARROW | 5 EACH | $200 | $200 | $150 | $200 | $175 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $85.00 | $75.00 | $100 | $85.00 | $100 |
| 614E12460 WORK ZONE MARKING SIGN | 10 EACH | $65.00 | $65.00 | $71.45 | $65.00 | $65.00 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 3.76 MILE | $950 | $1,350 | $2,005 | $1,350 | $950 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 3.76 MILE | $950 | $1,350 | $1,295 | $1,350 | $950 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 7.95 MILE | $500 | $850 | $1,160 | $850 | $500 |
| 614E23000 WORK ZONE CHANNELIZING LINE, CLASS I, 8" | 295 FT | $1.00 | $1.00 | $0.95 | $1.00 | $1.00 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 295 FT | $1.00 | $1.00 | $0.90 | $1.00 | $1.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 132 FT | $4.00 | $4.00 | $4.75 | $4.00 | $4.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 66 FT | $4.00 | $4.00 | $4.70 | $4.00 | $4.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $12,498 | $17,000 | $20,000 | $5,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $12,000 | $2,500 | $7,000 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 3,044 CY | $205.5 | $626k | 42% |
| 422E25000 EMULSION, CHIP SEAL | 29,217 GAL | $3.5 | $102k | 7% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 73,041 SY | $1.3 | $95k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $80,251 | $80k | 5% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441 | 1,800 SY | $40 | $72k | 5% |
| 253E01000 PAVEMENT REPAIR | 300 SY | $160 | $48k | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE | 36,520 SY | $1.25 | $46k | 3% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | 36,514 SY | $1.25 | $46k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 4 EACH | $8,850 | $35k | 2% |