ATB-US 6-00.00
ATB County · est $1.8M
Bid dateThursday, October 31—
ATB County · est $1.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 40 more items below.
| Item | Quantity | R1Ronyak Paving INC | R2Kokosing Construction Company INC | R3Karvo Companies INC | R4Cole Burton Contractors, LLC | % of bid |
|---|---|---|---|---|---|---|
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 3,238 CY | $200 | $235 | $230 | $280 | 45% |
| 422E25000 EMULSION, CHIP SEAL | 39,844 GAL | $3.00 | $4.00 | $3.25 | $4.50 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,000 | $60,008 | $95,000 | $125,955 | 7% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 99,103 SY | $1.00 | $0.75 | $1.50 | $1.15 | 7% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1.75") | 73,108 SY | $1.00 | $1.00 | $0.85 | $1.50 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $65,485 | $85,000 | $75,000 | $30,000 |
| Item | Quantity | R1Ronyak Paving INC | R2Kokosing Construction Company INC | R3Karvo Companies INC | R4Cole Burton Contractors, LLC |
|---|---|---|---|---|---|
| 202E98100 REMOVAL MISC.: BARRIER REFLECTORS | 37 EACH | $2.50 | $4.50 | $5.00 | $2.50 |
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 17 CY | $25.00 | $50.00 | $60.00 | $20.00 |
| 209E60200 LINEAR GRADING | 305 STA | $25.00 | $10.00 | $22.00 | $50.00 |
| 209E72000 PREPARING SUBGRADE FOR SHOULDER PAVING | 447 STA | $15.00 | $50.00 | $44.00 | $45.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 5% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | — | $30.00 | $45.00 | $37.00 | $36.00 | 4% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN (T=1.0" AVG.) | 276 CY | $145 | $140 | $118 | $70.00 | 3% |
| 646E10010 EDGE LINE, 6" | 11.65 MILE | $3,183 | $3,183 | $3,183 | $2,750 | 3% |
| 253E01000 PAVEMENT REPAIR | 300 SY | $85.00 | $150 | $120 | $88.00 | 2% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441), (TRANSVERSE) | 500 SY | $45.00 | $110 | $92.00 | $62.00 | 2% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 34 CF | $600 | $600 | $600 | $725 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 7,039 GAL | $2.50 | $2.50 | $2.90 | $3.00 | 1% |
| 621E00100 RPM | 419 EACH | $41.50 | $44.00 | $41.50 | $41.50 | 1% |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 25 CY | $600 | $235 | $410 | $350 | 1% |
| 202E23501 WEARING COURSE REMOVED, AS PER PLAN (T=1.25") | 698 SY | $20.00 | $15.00 | $6.60 | $5.50 | 1% |
| 646E10200 CENTER LINE | 5.66 MILE | $2,450 | $2,450 | $2,450 | $3,500 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $2,000 | $2,800 | $2,000 | $1,500 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 3,971 GAL | $3.00 | $4.50 | $5.00 | $5.00 | 1% |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 6 MILE | $1,976 | $1,976 | $1,976 | $1,750 | 1% |
| 5 EACH |
| $1,175 |
| $1,675 |
| $1,640 |
| $1,700 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $2,500 | $1,000 | $1,650 | $3,200 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 1 EACH | $1,300 | $2,500 | $2,350 | $2,000 |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE | 2 EACH | $1,725 | $1,750 | $1,800 | $2,500 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 1,200 LB | $3.00 | $5.00 | $1.00 | $2.75 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 675 FT | $2.00 | $2.00 | $1.75 | $3.00 |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | — | $1.25 | $2.50 | $2.20 | $2.00 |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 17 CY | $60.00 | $75.00 | $80.00 | $80.00 |
| 411E10000 STABILIZED CRUSHED AGGREGATE, (FIELD DRIVES) | 10 CY | $150 | $140 | $380 | $150 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 6.22 MILE | $1,325 | $1,500 | $1,325 | $1,325 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 4.11 MILE | $1,325 | $1,500 | $1,325 | $1,325 |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 21,912 FT | $0.50 | $1.30 | $1.15 | $1.25 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 336 EACH | $1.00 | $3.00 | $1.20 | $5.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE-WAY | 46 EACH | $25.00 | $12.37 | $12.37 | $25.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 90 FT | $20.00 | $23.00 | $22.41 | $20.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 12 SF | $50.00 | $27.00 | $26.83 | $50.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 12 EACH | $50.00 | $16.00 | $16.21 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 12 EACH | $50.00 | $22.00 | $21.62 | $50.00 |
| 646E10400 STOP LINE | 42 FT | $18.00 | $18.00 | $18.00 | $25.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $95.00 | $100 | $100 | $85.00 |
| 614E12460 WORK ZONE MARKING SIGN (ALL PHASES) | 8 EACH | $75.00 | $170 | $170 | $75.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $275 | $450 | $300 | $700 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $900 | $750 | $900 | $900 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 9.79 MILE | $1,175 | $1,175 | $1,175 | $1,250 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 5.67 MILE | $975 | $975 | $975 | $1,250 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 11.49 MILE | $650 | $650 | $650 | $650 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 80 FT | $3.00 | $3.00 | $3.00 | $4.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 40 FT | $3.00 | $3.00 | $3.00 | $4.00 |
| 202E23501 WEARING COURSE REMOVED, AS PER PLAN (T=1.25") | 266 SY | $40.00 | $35.00 | $21.00 | $6.00 |
| 407E20000 NON-TRACKING TACK COAT @ 0.08 GAL/SY | 22 GAL | $65.00 | $2.50 | $2.90 | $3.00 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 84 FT | $25.00 | $25.00 | $25.00 | $70.00 |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 10 CY | $690 | $235 | $450 | $375 |
| 407E20000 NON-TRACKING TACK COAT @ 0.08 GAL/SY | 56 GAL | $30.00 | $2.50 | $2.90 | $3.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $11,109 | $7,000 | $12,000 | $25,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $3,000 | $9,280 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 3,238 CY | $200 | $648k | 41% |
| 422E25000 EMULSION, CHIP SEAL | 39,844 GAL | $3 | $120k | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,000 | $100k | 6% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 99,103 SY | $1 | $99k | 6% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1.75") | 73,108 SY | $1 | $73k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $65,485 | $65k | 4% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | — | $30 | $60k | 4% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN (T=1.0" AVG.) | 276 CY | $145 | $40k | 3% |
| 646E10010 EDGE LINE, 6" | 11.65 MILE | $3,183 | $37k | 2% |
| 253E01000 PAVEMENT REPAIR | 300 SY | $85 | $26k | 2% |