LOG-SR 273-00.02
LOG County · est $1.1M
Bid dateThursday, November 14—
LOG County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 65 more items below.
| Item | Quantity | R1George J Igel & CO INC | R2R G Zachrich Construction INC | R3Complete General Construction Company | % of bid |
|---|---|---|---|---|---|
| 515E10050 PRESTRESSED CONCRETE NON-COMPOSITE BOX BEAM BRIDGE | 9 EACH | $14,800 | $18,000 | $22,000 | 16% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 84 CY | $1,000 | $942 | $1,100 | 10% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $80,000 | $150,000 | $125,000 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $55,000 | $56,000 | $50,000 | 6% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 118 FT | $436 | $436 | $440 | 6% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $50,000 | $78,000 | $26,000 | 6% |
| 507E00500 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE |
| Item | Quantity | R1George J Igel & CO INC | R2R G Zachrich Construction INC | R3Complete General Construction Company |
|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 503 SY | $20.00 | $20.00 | $22.00 |
| 202E38000 GUARDRAIL REMOVED | 628 FT | $5.00 | $3.00 | $2.00 |
| 203E20000 EMBANKMENT | 255 CY | $25.00 | $55.00 | $33.00 |
| 204E10000 SUBGRADE COMPACTION | 893 SY | $6.00 | $5.58 | $4.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 250 CY | $27.00 | $18.00 | $33.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 900 FT |
| $50.00 |
| $3.00 |
| $15.00 |
| 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 113 CY | $390 | $375 | $375 | 5% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 2 EACH | $20,000 | $5,700 | $21,000 | 5% |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 83 CY | $430 | $370 | $370 | 4% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $34,000 | $70,000 | $70,000 | 4% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $30,000 | $28,000 | $45,000 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $34,000 | $32,000 | 4% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 990 FT | $27.00 | $42.00 | $50.00 | 3% |
| 203E10000 EXCAVATION | 673 CY | $35.00 | $25.00 | $26.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25" MIN, 2.2 | 630 SY | $35.00 | $15.50 | $15.50 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $5,000 | $5,000 | 2% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 7,247 LB | $2.30 | $2.00 | $2.25 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $2,550 | $1,500 | $4,500 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $10,000 | $30,000 | 2% |
| 250 CY |
| $55.00 |
| $50.00 |
| $110 |
| 204E45000 PROOF ROLLING | 1 HOUR | $118 | $300 | $125 |
| 204E50000 GEOTEXTILE FABRIC | 500 SY | $0.90 | $1.50 | $3.60 |
| 606E15050 GUARDRAIL, TYPE MGS | 250 FT | $34.00 | $34.00 | $18.80 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350 / MASH 2016 | 4 EACH | $3,300 | $3,150 | $2,540 |
| 606E34600 MGS BRIDGE TERMINAL ASSEMBLY, TYPE TST-2 | 4 EACH | $2,675 | $2,675 | $2,450 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $125 | $100 | $576 |
| 659E00300 TOPSOIL | 61 CY | $70.00 | $40.00 | $45.00 |
| 659E10000 SEEDING AND MULCHING | 552 SY | $8.00 | $7.80 | $5.85 |
| 659E14000 REPAIR SEEDING AND MULCHING | 28 SY | $4.00 | $7.80 | $1.10 |
| 659E20000 COMMERCIAL FERTILIZER | 0.07 TON | $800 | $850 | $450 |
| 659E31000 LIME | 0.11 ACRE | $1.00 | $3.82 | $50.00 |
| 659E35000 WATER | 3 MGAL | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 47 FT | $40.00 | $15.00 | $20.00 |
| 304E20000 AGGREGATE BASE | 142 CY | $75.00 | $72.00 | $120 |
| 407E20000 NON-TRACKING TACK COAT | 145 GAL | $5.00 | $2.50 | $2.50 |
| 621E00100 RPM | 20 EACH | $235 | $234 | $234 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 10 EACH | $20.00 | $12.00 | $45.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 16 EACH | $11.00 | $11.00 | $11.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 74.5 FT | $15.50 | $15.50 | $20.00 |
| 630E80100 SIGN, FLAT SHEET | 23 SF | $18.00 | $18.00 | $30.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 6 EACH | $15.00 | $15.00 | $10.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $45.00 | $45.00 | $65.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $20.00 | $20.00 | $15.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.14 MILE | $12,825 | $12,825 | $12,825 |
| 642E00300 CENTER LINE, TYPE 1 | 0.07 MILE | $17,095 | $17,095 | $17,095 |
| 204E10000 SUBGRADE COMPACTION | 25 SY | $16.00 | $2.60 | $10.00 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 3 CY | $835 | $1,100 | $1,100 |
| 304E20000 AGGREGATE BASE | 4 CY | $200 | $72.00 | $120 |
| 407E20000 NON-TRACKING TACK COAT | 35 GAL | $5.00 | $2.50 | $2.50 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 17 CY | $575 | $685 | $685 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 32 HOUR | $100 | $90.00 | $90.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 300 FT | $2.57 | $2.57 | $2.57 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,237 | $2,237 | $2,240 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 14 EACH | $11.29 | $11.29 | $11.30 |
| 614E13312 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 15 EACH | $13.57 | $13.57 | $13.60 |
| 614E13360 OBJECT MARKER, TWO WAY | 25 EACH | $21.52 | $21.52 | $21.60 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.32 MILE | $11,271 | $11,271 | $11,300 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 38 FT | $5.95 | $5.95 | $5.95 |
| 616E10000 WATER | 4 MGAL | $55.00 | $60.00 | $150 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 570 FT | $26.00 | $38.00 | $31.05 |
| 202E23500 WEARING COURSE REMOVED | 100 SY | $36.00 | $40.00 | $25.00 |
| 407E20000 NON-TRACKING TACK COAT | 24 GAL | $5.00 | $2.50 | $5.00 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 22 CY | $650 | $685 | $370 |
| 511E31611 CLASS QC2 CONCRETE, SUPERSTRUCTURE, AS PER PLAN | 7 CY | $1,500 | $1,300 | $2,500 |
| 512E10000 SEALING OF CONCRETE SURFACES | 72 SY | $20.00 | $22.00 | $20.00 |
| 512E33000 TYPE 2 WATERPROOFING | 14 SY | $70.00 | $30.00 | $70.00 |
| 512E33010 TYPE 3 WATERPROOFING | 224 SY | $35.00 | $42.00 | $35.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 28 SF | $9.00 | $12.00 | $14.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 79 FT | $45.00 | $46.00 | $42.50 |
| 516E43200 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 36 EACH | $220 | $250 | $200 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 44 CY | $150 | $125 | $150 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 112 FT | $25.00 | $20.00 | $20.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 106 FT | $8.00 | $12.00 | $10.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 42 FT | $20.00 | $12.00 | $22.00 |
| 523E20001 DYNAMIC LOAD TESTING, AS PER PLAN | 2 EACH | $4,600 | $4,000 | $5,000 |
| 523E20501 RESTRIKE, AS PER PLAN | 2 EACH | $4,000 | $3,390 | $3,200 |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 96 CY | $140 | $142 | $190 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,000 | $18,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E10050 PRESTRESSED CONCRETE NON-COMPOSITE BOX BEAM BRIDGE | 9 EACH | $14,800 | $133k | 12% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 84 CY | $1,000 | $84k | 8% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $80,000 | $80k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $55,000 | $55k | 5% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 118 FT | $436 | $51k | 5% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $50,000 | $50k | 5% |
| 507E00500 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 900 FT | $50 | $45k | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 113 CY | $390 | $44k | 4% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 2 EACH | $20,000 | $40k | 4% |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 83 CY | $430 | $36k | 3% |