PIK-CR 9-05.29
PIK County · est $1.7M
Bid dateThursday, December 19—
PIK County · est $1.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 77 more items below.
| Item | Quantity | R1Coopers Excavating LLC | R2Alan Stone CO INC | R3Shelly & Sands INC | R4Double Z Construction Company | R5Axis Civil Construction LLC | R6Complete General Construction Company | R7Miller Bros Const INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 515E12090 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 7 EACH | $45,000 | $32,000 | $28,500 | $32,000 | $32,000 | $32,700 | $35,000 | 26% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 784 CY | $181 | $200 | $175 | $195 | $225 | $195 | $195 | 12% |
| Item | Quantity | R1Coopers Excavating LLC | R2Alan Stone CO INC | R3Shelly & Sands INC | R4Double Z Construction Company | R5Axis Civil Construction LLC | R6Complete General Construction Company | R7Miller Bros Const INC |
|---|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 4 EACH | $135 | $140 | $200 | $150 | $180 | $500 | $500 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 173 FT | $6.85 | $10.00 | $12.00 | $10.00 | $14.00 | $30.00 | $50.00 |
| 202E53100 MAILBOX REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $85,000 |
| $67,000 |
| $79,000 |
| $40,000 |
| $35,000 |
| $96,000 |
| $96,000 |
| 7% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 53 CY | $1,500 | $1,500 | $1,500 | $1,300 | $1,550 | $1,500 | $1,025 | 6% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 305 FT | $225 | $150 | $88.00 | $225 | $215 | $400 | $239 | 6% |
| 203E20000 EMBANKMENT | 3,276 CY | $16.65 | $10.00 | $25.00 | $22.00 | $22.00 | $40.00 | $44.00 | 4% |
| 304E20000 AGGREGATE BASE | 890 CY | $60.00 | $60.00 | $69.00 | $78.00 | $90.00 | $65.00 | $90.00 | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $50,000 | $15,000 | $8,700 | $9,600 | $12,000 | $12,500 | $15,000 | 4% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 53 CY | $900 | $760 | $1,100 | $985 | $900 | $1,500 | $680 | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 180 FT | $228 | $260 | $220 | $228 | $220 | $225 | $228 | 3% |
| 832E30000 EROSION CONTROL | 40,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 203E10000 EXCAVATION | 3,682 CY | $10.50 | $15.00 | $26.00 | $25.00 | $22.00 | $30.00 | $44.00 | 3% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (211 CY | $182 | $250 | $220 | $258 | $275 | $258 | $258 | 3% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 158 CY | $197 | $270 | $235 | $237 | $325 | $237 | $237 | 3% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $30,000 | $32,000 | $35,180 | $41,000 | $27,000 | $95,000 | $38,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $30,000 | $45,000 | $24,000 | $15,500 | $15,000 | $15,000 | $50,500 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,000 | $41,000 | $19,000 | $20,000 | $25,000 | $20,000 | $25,000 | 2% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 391 CY | $54.00 | $60.00 | $95.00 | $110 | $105 | $75.00 | $120 | 2% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 8,820 LB | $2.00 | $2.50 | $1.80 | $2.25 | $2.50 | $1.75 | $1.85 | 1% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $15,000 | $10,000 | $2,700 | $12,000 | $10,000 | $15,000 | $13,000 | 1% |
| 9 EACH |
| $20.00 |
| $85.00 |
| $25.00 |
| $65.00 |
| $100 |
| $20.00 |
| $150 |
| 202E75000 FENCE REMOVED | 20 FT | $5.00 | $30.00 | $30.00 | $5.00 | $14.00 | $15.00 | $15.00 |
| 202E98100 REMOVAL MISC.:FLAGPOLE AND FOUNDATION | 1 EACH | $100 | $560 | $440 | $150 | $500 | $2,000 | $200 |
| 204E10000 SUBGRADE COMPACTION | 5,616 SY | $1.00 | $2.00 | $4.00 | $4.00 | $2.00 | $3.00 | $2.00 |
| 204E45000 PROOF ROLLING | 4 HOUR | $130 | $65.00 | $225 | $180 | $225 | $500 | $200 |
| 606E15050 GUARDRAIL, TYPE MGS | 312.5 FT | $22.00 | $25.00 | $20.50 | $22.00 | $20.50 | $27.28 | $22.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 2 EACH | $1,800 | $2,000 | $1,600 | $1,800 | $1,600 | $1,450 | $1,800 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,575 | $1,800 | $1,150 | $1,575 | $1,150 | $1,000 | $1,575 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,700 | $3,000 | $2,300 | $2,700 | $2,300 | $1,900 | $2,700 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 4 EACH | $1,200 | $1,100 | $2,100 | $1,500 | $1,400 | $1,500 | $3,400 |
| 626E00110 BARRIER REFLECTOR, TYPE 2(WHITE/WHITE) | 24 EACH | $13.00 | $15.00 | $12.00 | $13.00 | $12.00 | $12.50 | $13.00 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $500 | $1,700 | $200 | $250 | $200 | $295 | $295 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 4 EACH | $500 | $510 | $250 | $275 | $250 | $365 | $365 |
| 659E00100 SOIL ANALYSIS TEST | 1 EACH | $500 | $170 | $125 | $150 | $150 | $150 | $150 |
| 659E00300 TOPSOIL | 991 CY | $15.00 | $10.00 | $16.00 | $40.00 | $45.00 | $25.00 | $60.00 |
| 659E10000 SEEDING AND MULCHING | 8,925 SY | $0.90 | $1.00 | $1.02 | $2.00 | $0.80 | $0.80 | $0.80 |
| 659E14000 REPAIR SEEDING AND MULCHING | 446 SY | $0.50 | $2.00 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 659E15000 INTER-SEEDING | 446 SY | $0.01 | $2.00 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 659E20000 COMMERCIAL FERTILIZER | 1.2 TON | $1,500 | $1,600 | $921 | $1,250 | $1,250 | $1,250 | $1,250 |
| 659E31000 LIME | 1.8 ACRE | $200 | $500 | $162 | $150 | $150 | $150 | $150 |
| 659E35000 WATER | 72 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 660E25000 SODDING STAKED | 345 SY | $20.00 | $20.00 | $15.20 | $20.00 | $20.00 | $20.00 | $20.00 |
| 670E00500 SLOPE EROSION PROTECTION | 1,869 SY | $1.95 | $2.00 | $1.46 | $2.50 | $2.25 | $2.50 | $2.50 |
| 670E00700 DITCH EROSION PROTECTION | 1,206 SY | $1.95 | $2.00 | $1.52 | $2.50 | $2.25 | $2.50 | $2.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $2,400 | $2,200 | $2,175 | $3,000 | $3,000 | $3,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $7,500 | $18,000 | $13,000 | $10,710 | $10,000 | $7,350 | $7,350 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $10,000 | $11,000 | $9,700 | $10,000 | $10,000 | $10,000 | $9,700 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 3 CY | $87.00 | $300 | $245 | $190 | $140 | $250 | $155 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 29 CY | $87.00 | $150 | $125 | $140 | $140 | $250 | $150 |
| 602E20000 CONCRETE MASONRY | 2.1 CY | $1,500 | $2,800 | $2,700 | $3,500 | $2,250 | $5,000 | $2,600 |
| 605E31100 AGGREGATE DRAINS | 1,224 FT | $5.00 | $7.50 | $17.00 | $12.00 | $12.50 | $15.00 | $15.00 |
| 611E01800 8" CONDUIT, TYPE B, FOR DRAINAGE CONNECTION | 100 FT | $5.00 | $25.00 | $21.00 | $12.00 | $25.00 | $8.00 | $90.00 |
| 611E02500 8" CONDUIT, TYPE E, FOR DRAINAGE CONNECTION | 100 FT | $5.00 | $25.00 | $21.00 | $8.00 | $25.00 | $8.00 | $90.00 |
| 611E02600 8" CONDUIT, TYPE F, FOR DRAINAGE CONNECTION | 100 FT | $5.00 | $25.00 | $20.00 | $8.00 | $25.00 | $8.00 | $90.00 |
| 611E04200 12" CONDUIT, TYPE A 706.02, 707.01 (AL), OR 707.33 | 36 FT | $45.00 | $120 | $118 | $85.00 | $60.00 | $200 | $75.00 |
| 611E04400 12" CONDUIT, TYPE B, FOR DRAINAGE CONNECTION | 100 FT | $6.00 | $35.00 | $36.00 | $24.00 | $60.00 | $12.00 | $110 |
| 611E04600 12" CONDUIT, TYPE C 706.02, 707.33, OR 15" 707.13 | 138 FT | $40.00 | $80.00 | $88.00 | $80.00 | $60.00 | $150 | $70.00 |
| 611E04900 12" CONDUIT, TYPE D 706.02, 707.33, OR 15" 707.01 | 52 FT | $30.00 | $85.00 | $56.00 | $85.00 | $60.00 | $150 | $75.00 |
| 611E05100 12" CONDUIT, TYPE E, FOR DRAINAGE CONNECTION | 100 FT | $6.00 | $35.00 | $30.00 | $18.00 | $50.00 | $12.00 | $110 |
| 611E05200 12" CONDUIT, TYPE F, FOR DRAINAGE CONNECTION | 100 FT | $6.00 | $35.00 | $30.00 | $18.00 | $50.00 | $12.00 | $110 |
| 611E07200 18" CONDUIT, TYPE A 706.02, 707.01, (AL), OR 707.3 | 75 FT | $50.00 | $100 | $122 | $95.00 | $85.00 | $180 | $95.00 |
| 611E07900 18" CONDUIT, TYPE D 706.02, 707.01 (AL), OR 707.33 | 44 FT | $35.00 | $110 | $118 | $105 | $85.00 | $225 | $115 |
| 611E10900 24" CONDUIT, TYPE D 706.02, 707.33, OR 30" 707.01 | 71 FT | $50.00 | $100 | $90.00 | $110 | $95.00 | $150 | $140 |
| 611E98470 CATCH BASIN, NO. 2-2B | 3 EACH | $1,750 | $2,600 | $3,200 | $3,000 | $2,800 | $5,000 | $2,400 |
| 301E56100 ASPHALT CONCRETE BASE, PG64-22, (449), (DRIVEWAYS) | 50 CY | $184 | $200 | $175 | $295 | $360 | $295 | $295 |
| 407E10000 TACK COAT | 387 GAL | $3.50 | $5.00 | $3.50 | $2.50 | $6.00 | $2.50 | $2.50 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $220 | $490 | $405 | $525 | $440 | $525 | $525 |
| 441E70700 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (15 CY | $192 | $1,000 | $300 | $415 | $400 | $415 | $415 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 338.5 FT | $15.50 | $15.00 | $15.00 | $15.50 | $15.50 | $13.00 | $15.50 |
| 630E80100 SIGN, FLAT SHEET | 122.5 SF | $18.00 | $20.00 | $20.00 | $18.00 | $18.00 | $28.00 | $18.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 3 EACH | $20.00 | $20.00 | $25.00 | $20.00 | $20.00 | $15.00 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $25.00 | $30.00 | $25.00 | $25.00 | $25.00 | $15.00 | $25.00 |
| 644E00100 EDGE LINE, 4" | 0.65 MILE | $6,439 | $7,200 | $5,491 | $6,439 | $6,439 | $6,525 | $6,439 |
| 644E00300 CENTER LINE | 0.31 MILE | $12,259 | $14,000 | $8,802 | $12,259 | $12,259 | $12,005 | $12,259 |
| 646E10000 EDGE LINE, 4" | 0.03 MILE | $47,900 | $54,000 | $40,000 | $47,900 | $47,900 | $85,625 | $47,900 |
| 646E10200 CENTER LINE | 0.02 MILE | $215,436 | $241,000 | $70,000 | $215,436 | $215,436 | $164,205 | $215,436 |
| 614E12420 DETOUR SIGNING | 1 LS | $4,605 | $5,200 | $4,650 | $9,800 | $4,500 | $9,000 | $4,605 |
| 616E10000 WATER | 1 MGAL | $1.00 | $1.00 | $70.00 | $50.00 | $1.00 | $100 | $300 |
| 202E23500 WEARING COURSE REMOVED | 77 SY | $9.00 | $25.00 | $24.00 | $20.00 | $12.50 | $50.00 | $31.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $500 | $23,000 | $32,023 | $25,000 | $10,000 | $70,000 | $13,750 |
| 507E00101 STEEL PILES HP10X42, FURNISHED, AS PER PLAN | 400 FT | $30.00 | $30.00 | $25.60 | $40.00 | $36.00 | $30.00 | $30.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 87 SY | $32.00 | $50.00 | $23.50 | $23.50 | $23.50 | $23.50 | $13.00 |
| 512E33010 TYPE 3 WATERPROOFING | 36 SY | $58.00 | $70.00 | $65.00 | $55.00 | $20.00 | $65.00 | $44.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 39 SF | $5.00 | $20.00 | $6.00 | $20.00 | $7.00 | $20.00 | $6.00 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 249 SF | $13.69 | $7.00 | $10.00 | $10.00 | $15.00 | $35.00 | $11.00 |
| 516E31010 2" DEEP JOINT SEALER | 56 FT | $10.00 | $40.00 | $30.00 | $25.00 | $40.00 | $30.00 | $19.00 |
| 516E41500 1" ELASTOMERIC BEARING PAD, TYPE PEPTYPE PEP | 28 EACH | $79.20 | $110 | $77.00 | $225 | $95.00 | $200 | $106 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 14 CY | $100 | $210 | $126 | $150 | $165 | $175 | $150 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 203 FT | $15.86 | $15.00 | $16.00 | $20.00 | $16.00 | $16.00 | $14.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 96 FT | $10.00 | $10.00 | $7.50 | $13.00 | $12.00 | $15.00 | $16.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 60 FT | $10.00 | $15.00 | $18.00 | $18.00 | $20.00 | $20.00 | $18.00 |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 64 CY | $100 | $100 | $128 | $120 | $140 | $95.00 | $106 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 69 CY | $130 | $160 | $217 | $180 | $185 | $275 | $190 |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $15,000 | $25,000 | $4,300 | $8,000 | $15,000 | $10,000 | $50,000 |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $200 | $1,000 | $3,700 | $1,200 | $1,200 | $1,500 | $2,700 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12090 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 7 EACH | $45,000 | $315k | 21% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 784 CY | $181 | $142k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $85,000 | $85k | 6% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 53 CY | $1,500 | $80k | 5% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 305 FT | $225 | $69k | 5% |
| 203E20000 EMBANKMENT | 3,276 CY | $16.65 | $55k | 4% |
| 304E20000 AGGREGATE BASE | 890 CY | $60 | $53k | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $50,000 | $50k | 3% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 53 CY | $900 | $48k | 3% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 180 FT | $228 | $41k | 3% |