FRA-IR 70-00.00
FRA County · est $63M
Bid dateThursday, January 30—
FRA County · est $63M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 269 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Kokosing Construction Company INC | R3Miller Bros Const INC | R4Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|
| 302E66001 ASPHALT CONCRETE BASE, AS PER PLAN, 25.0MM GYRATOR | 96,316 CY | $135 | $138 | $153 | $153 | 30% |
| 442E10300 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 19,309 CY | $230 | $238 | $242 | $242 | 10% |
| 304E20000 AGGREGATE BASE | 60,609 CY | $50.00 | $60.00 | $50.00 | $50.15 | 7% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 16,532 CY | $165 | $180 | $187 | $187 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $2,700,000 | $2,900,000 | $3,030,000 | $3,000,000 | 6% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 305,325 SY | $7.50 | $10.50 | $21.50 |
| Item | Quantity | R1Shelly & Sands INC | R2Kokosing Construction Company INC | R3Miller Bros Const INC | R4Complete General Construction Company |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $255,800 | $41,100 | $50,000 | $45,000 |
| 202E20010 HEADWALL REMOVED | 23 EACH | $225 | $500 | $300 | $350 |
| 202E23000 PAVEMENT REMOVED | 7,634 SY | $7.00 | $11.50 | $7.50 | $5.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 6,895 FT | $7.50 | $15.00 | $8.00 | $20.00 |
| 202E38000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $17.80 |
| 5% |
| 206E10500 CEMENT | 9,458 TON | $205 | $191 | $180 | $199 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,856,500 | $2,111,800 | $1,887,000 | $1,130,000 | 4% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 31,699 SY | $55.00 | $80.00 | $65.50 | $58.00 | 4% |
| 203E10000 EXCAVATION | 110,659 CY | $12.00 | $12.00 | $18.50 | $29.50 | 3% |
| 605E11110 6" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 125,266 FT | $10.00 | $9.50 | $10.50 | $14.90 | 3% |
| 452E17060 14.5" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1 | 7,507 SY | $150 | $165 | $149 | $140 | 3% |
| 622E41011 PORTABLE BARRIER, 50", AS PER PLAN | 62,797 FT | $17.00 | $12.00 | $16.50 | $26.00 | 2% |
| 832E30000 EROSION CONTROL | 996,615 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 119,872 FT | $8.00 | $6.50 | $8.30 | $12.20 | 2% |
| 206E15010 CEMENT STABILIZED SUBGRADE, 12 INCHES DEEP | 366,237 SY | $2.23 | $3.27 | $3.10 | $3.90 | 2% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 13,800 SY | $50.00 | $17.00 | $17.00 | $17.00 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $575,000 | $300,000 | $150,000 | $800,000 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $575,000 | $400,000 | $142,400 | $400,000 | 1% |
| 606E55010 SPECIAL - CABLE BARRIER WITH CONCRETE LINE POST FO | 28,480 FT | $18.75 | $18.75 | $18.75 | $22.50 | 1% |
| 12,717 FT |
| $2.50 |
| $2.50 |
| $2.50 |
| $2.00 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 24 EACH | $200 | $200 | $200 | $150 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 17 EACH | $125 | $125 | $125 | $100 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 18 EACH | $125 | $125 | $125 | $75.00 |
| 202E48000 CABLE BARRIER REMOVED | 28,053 FT | $2.00 | $5.00 | $2.00 | $1.20 |
| 202E58000 MANHOLE REMOVED | 2 EACH | $450 | $1,200 | $750 | $990 |
| 202E58100 CATCH BASIN REMOVED | 37 EACH | $250 | $900 | $750 | $480 |
| 202E75000 FENCE REMOVED | 30 FT | $10.00 | $125 | $13.50 | $9.00 |
| 203E20000 EMBANKMENT | 6,389 CY | $10.00 | $6.00 | $15.50 | $7.00 |
| 204E45000 PROOF ROLLING | 122 HOUR | $420 | $225 | $250 | $350 |
| 206E11000 CURING COAT | 366,237 SY | $0.65 | $1.05 | $1.05 | $1.08 |
| 206E30000 MIXTURE DESIGN FOR CHEMICALLY STABILIZED SOILS | 1 LS | $87,000 | $89,000 | $65,000 | $87,600 |
| 209E15051 RESHAPING UNDER GUARDRAIL, AS PER PLAN | 1.25 MILE | $2,500 | $6,500 | $2,500 | $8,800 |
| 606E15050 GUARDRAIL, TYPE MGS | 6,084 FT | $19.00 | $19.00 | $19.00 | $19.60 |
| 606E15550 GUARDRAIL, BARRIER DESIGN, TYPE MGS | 200 FT | $32.00 | $32.00 | $32.00 | $31.00 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 5 EACH | $2,400 | $2,400 | $2,400 | $2,300 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 20 EACH | $2,500 | $2,500 | $2,500 | $2,680 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 15 EACH | $1,200 | $1,200 | $1,200 | $1,420 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 17 EACH | $2,450 | $2,450 | $2,450 | $2,550 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $500 | $500 | $500 | $725 |
| 606E55150 SPECIAL - CABLE BARRIER, ANCHOR ASSEMBLY | 26 EACH | $3,850 | $3,850 | $3,850 | $3,260 |
| 606E55180 SPECIAL - CABLE BARRIER, SPLICE | 2 EACH | $30.00 | $30.00 | $30.00 | $495 |
| 606E55190 SPECIAL - CABLE BARRIER, POST REFLECTOR | 376 EACH | $12.00 | $12.00 | $12.00 | $15.00 |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 6 EACH | $8,000 | $8,000 | $8,000 | $9,125 |
| 607E15100 FENCE, TYPE 47RA | 50 FT | $40.00 | $40.00 | $40.00 | $69.50 |
| 622E24000 CONCRETE BARRIER, TYPE D | 230 FT | $200 | $160 | $200 | $210 |
| 622E25000 CONCRETE BARRIER END SECTION, TYPE D | 8 EACH | $4,000 | $5,000 | $4,500 | $4,795 |
| 622E25050 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 8 EACH | $4,000 | $5,000 | $4,500 | $5,070 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $145,000 | $250,000 | $65,875 | $200,000 |
| 606E55000 SPECIAL - CABLE BARRIER, MOW STRIP | 29,780 FT | $15.30 | $21.00 | $22.50 | $29.00 |
| 606E10720 SPECIAL - NOISE BARRIER PANEL REMOVAL AND REUSE | 3 EACH | $1,800 | $8,000 | $2,700 | $10,000 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 237 SY | $150 | $160 | $75.00 | $145 |
| 601E45050 BIORETENTION CELL | 1,618 CY | $110 | $105 | $88.50 | $100 |
| 659E00100 SOIL ANALYSIS TEST | 6 EACH | $75.00 | $50.00 | $50.00 | $75.00 |
| 659E00300 TOPSOIL | 27,325 CY | $8.75 | $7.00 | $5.00 | $30.00 |
| 659E10000 SEEDING AND MULCHING | 245,900 SY | $0.54 | $0.48 | $0.48 | $0.54 |
| 659E14000 REPAIR SEEDING AND MULCHING | 12,295 SY | $0.50 | $0.45 | $0.45 | $0.45 |
| 659E15000 INTER-SEEDING | 12,295 SY | $0.50 | $0.01 | $0.01 | $0.25 |
| 659E20000 COMMERCIAL FERTILIZER | 34.3 TON | $500 | $1,000 | $1,000 | $500 |
| 659E31000 LIME | 50.81 ACRE | $10.00 | $1.00 | $1.00 | $10.00 |
| 659E35000 WATER | 1,361 MGAL | $1.00 | $1.00 | $1.00 | $0.25 |
| 659E40000 MOWING | 553 MSF | $4.80 | $1.00 | $1.00 | $4.80 |
| 670E00700 DITCH EROSION PROTECTION | 11,575 SY | $1.75 | $1.95 | $1.95 | $1.75 |
| 832E15001 STORM WATER POLLUTION PREVENTION PLAN, AS PER PLAN | 1 LS | $12,000 | $10,000 | $7,535 | $12,500 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $45,000 | $50,000 | $33,350 | $47,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $22,000 | $30,000 | $22,195 | $22,000 |
| 602E20000 CONCRETE MASONRY | 7.8 CY | $3,100 | $5,500 | $2,850 | $2,780 |
| 611E01500 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 4,265 FT | $22.00 | $27.50 | $33.00 | $17.00 |
| 611E05900 15" CONDUIT, TYPE B | 2,166 FT | $105 | $165 | $60.00 | $115 |
| 611E06100 15" CONDUIT, TYPE C | 924 FT | $70.00 | $125 | $65.00 | $88.00 |
| 611E07600 18" CONDUIT, TYPE C | 1,346 FT | $82.00 | $120 | $80.00 | $97.00 |
| 611E10400 24" CONDUIT, TYPE B | 397 FT | $145 | $240 | $130 | $152 |
| 611E10600 24" CONDUIT, TYPE C | 2,062 FT | $100 | $160 | $105 | $125 |
| 611E98230 CATCH BASIN, NO. 4 | 33 EACH | $6,200 | $9,000 | $5,200 | $6,000 |
| 611E98470 CATCH BASIN, NO. 2-2B | 4 EACH | $3,000 | $4,000 | $1,900 | $1,960 |
| 611E99574 MANHOLE, NO. 3 | 6 EACH | $4,150 | $7,000 | $3,900 | $5,150 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 96 EACH | $425 | $950 | $400 | $315 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5") | 123,344 SY | $3.40 | $2.15 | $3.15 | $3.15 |
| 407E20000 NON-TRACKING TACK COAT | 34,004 GAL | $3.50 | $4.00 | $4.05 | $4.05 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 2,180 CY | $85.00 | $110 | $75.00 | $76.25 |
| 441E70801 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (300 CY | $305 | $450 | $255 | $255 |
| 618E40600 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 20.66 MILE | $1,000 | $1,300 | $1,000 | $1,000 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 20.45 MILE | $1,300 | $1,400 | $1,400 | $2,000 |
| 442E00100 ANTI-SEGREGATION EQUIPMENT | 24,962 CY | $8.00 | $1.00 | $7.00 | $7.00 |
| 251E01043 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 500 CY | $450 | $425 | $389 | $389 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 3 EACH | $100 | $300 | $100 | $280 |
| 625E15200 LIGHT TOWER FOUNDATION, 36" X 25' DEEP | 5 EACH | $11,700 | $15,000 | $11,700 | $23,000 |
| 625E24314 1-1/2" DUCT CABLE WITH THREE NO. 1/0 AWG 2400 VOLT | 2,306 FT | $24.00 | $25.00 | $24.00 | $24.00 |
| 625E25500 CONDUIT, 3", 725.04 | 98 FT | $27.00 | $60.00 | $27.00 | $60.00 |
| 625E27520 REMOVAL OF LUMINAIRE AND REERECTION | 15 EACH | $250 | $550 | $250 | $400 |
| 625E29002 TRENCH, 24" DEEP | 2,246 FT | $11.00 | $11.00 | $11.00 | $6.50 |
| 625E30700 PULL BOX, 725.08, 18" | 2 EACH | $1,300 | $1,500 | $1,300 | $1,150 |
| 625E32000 GROUND ROD | 10 EACH | $265 | $325 | $265 | $400 |
| 625E35021 RE-ERECT EXISTING LIGHT TOWER, AS PER PLAN | 5 EACH | $4,400 | $7,500 | $4,400 | $6,000 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 2,246 FT | $3.00 | $2.00 | $3.00 | $2.00 |
| 625E75360 LIGHT TOWER REMOVED FOR STORAGE | 5 EACH | $3,200 | $4,000 | $3,200 | $3,000 |
| 625E75540 LIGHT TOWER FOUNDATION REMOVED | 5 EACH | $300 | $450 | $300 | $775 |
| 625E75800 DISCONNECT CIRCUIT | 1 EACH | $206 | $150 | $206 | $300 |
| 621E00100 RPM | 1,012 EACH | $39.00 | $38.75 | $39.00 | $38.75 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, ONE WAY | 24 EACH | $12.00 | $12.00 | $12.00 | $12.50 |
| 626E00116 BARRIER REFLECTOR, TYPE 5, ONE WAY | 126 EACH | $12.00 | $22.00 | $22.00 | $16.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 184 FT | $12.00 | $12.00 | $12.00 | $14.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 391 FT | $13.00 | $13.00 | $13.00 | $15.00 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 188 FT | $22.00 | $22.00 | $22.00 | $17.00 |
| 630E06100 GROUND MOUNTED SUPPORT, NO. 6 POST | 193 FT | $25.00 | $25.00 | $25.00 | $19.00 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 28 FT | $16.00 | $16.00 | $16.00 | $40.00 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 70 FT | $17.00 | $17.00 | $17.00 | $45.00 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 171 FT | $21.00 | $21.00 | $21.00 | $52.00 |
| 630E08200 GROUND MOUNTED SUPPORT, PIPE | 1 EACH | $1,200 | $1,200 | $1,200 | $825 |
| 630E08600 SIGN POST REFLECTOR | 6 EACH | $45.00 | $45.00 | $45.00 | $45.00 |
| 630E72420 OVERHEAD SIGN SUPPORT, TYPE TC-15.116, DESIGN 2 | 2 EACH | $74,500 | $74,500 | $74,500 | $84,650 |
| 630E80100 SIGN, FLAT SHEET | 562 SF | $19.50 | $19.50 | $19.50 | $17.00 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 120 SF | $22.50 | $22.50 | $22.50 | $24.00 |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 565 SF | $22.50 | $22.50 | $22.50 | $24.00 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 12 EACH | $950 | $950 | $950 | $975 |
| 630E84600 GROUND MOUNTED PIPE SUPPORT FOUNDATION | 1 EACH | $650 | $650 | $650 | $625 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 60 EACH | $15.00 | $15.00 | $15.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 6 EACH | $100 | $100 | $100 | $65.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 72 EACH | $15.00 | $15.00 | $15.00 | $20.00 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 14 EACH | $375 | $375 | $375 | $265 |
| 630E86272 REMOVAL OF GROUND MOUNTED PIPE SUPPORT AND DISPOSA | 1 EACH | $375 | $375 | $375 | $125 |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 4 EACH | $300 | $300 | $300 | $295 |
| 630E89804 REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP | 2 EACH | $3,500 | $3,500 | $3,500 | $3,650 |
| 807E12010 WET REFLECTIVE EPOXY PAVEMENT MARKING, EDGE LINE, | 1.42 MILE | $11,980 | $11,980 | $11,980 | $11,980 |
| 807E12110 WET REFLECTIVE EPOXY PAVEMENT MARKING, LANE LINE, | 0.39 MILE | $6,900 | $6,900 | $6,900 | $6,900 |
| 807E14010 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, EDG | 26.06 MILE | $5,214 | $5,214 | $5,214 | $5,214 |
| 807E14110 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, LAN | 26.2 MILE | $2,110 | $2,110 | $2,110 | $2,110 |
| 807E14310 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, CHA | 10,738 FT | $2.60 | $2.60 | $2.60 | $2.60 |
| 807E14410 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, DOT | 5,251 FT | $1.00 | $1.00 | $1.00 | $1.00 |
| 850E10010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1,959 | $1,959 | $1,959 | $1,959 |
| 850E10130 GROOVING FOR 12" RECESSED PAVEMENT MARKING | — | $1.30 | $1.30 | $1.30 | $1.30 |
| 850E20010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $2,990 | $2,990 | $2,990 | $2,990 |
| 625E32000 GROUND ROD | 4 EACH | $265 | $425 | $265 | $500 |
| 630E84510 RIGID OVERHEAD SIGN SUPPORT FOUNDATION | 4 EACH | $10,750 | $10,750 | $10,750 | $13,450 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 2,000 HOUR | $104 | $113 | $100 | $120 |
| 614E12200 SPECIAL - WORK ZONE GUARDRAIL | 2,189.5 FT | $25.00 | $25.00 | $25.00 | $25.20 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,200 | $3,500 | $1,991 | $2,200 |
| 614E12484 WORK ZONE INCREASED PENALTIES SIGN | 18 EACH | $950 | $800 | $251 | $700 |
| 614E12756 WORK ZONE CROSSOVER LIGHTING SYSTEM | 4 EACH | $47,000 | $80,000 | $45,375 | $80,000 |
| 614E12801 WORK ZONE RAISED PAVEMENT MARKER, AS PER PLAN, ONE | 5,265 EACH | $33.00 | $45.00 | $41.00 | $45.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 , BIDIRECTIONAL | 2,514 EACH | $6.00 | $7.00 | $12.43 | $8.60 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 , ONE WAY | 512 EACH | $7.00 | $7.00 | $11.42 | $6.80 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, ONE WAY | 29 EACH | $9.00 | $18.00 | $11.07 | $24.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 1,769 EACH | $13.00 | $17.00 | $18.92 | $18.50 |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 48 SNMT | $700 | $550 | $925 | $1,300 |
| 616E10000 WATER | 1,500 MGAL | $95.00 | $75.00 | $75.00 | $75.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 25,209 FT | $16.00 | $7.00 | $10.50 | $20.00 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 180 SNMT | $600 | $475 | $750 | $1,000 |
| 829E00100 WORK ZONE EGRESS WARNING SYSTEM | 24 SNMT | $2,000 | $1,000 | $900 | $6,000 |
| 896E00010 PORTABLE NON-INTRUSIVE TRAFFIC SENSOR, CLASS I | 96 SNMT | $1,275 | $800 | $800 | $5,000 |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 200 SY | $130 | $190 | $41.00 | $41.00 |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 250 SY | $125 | $275 | $96.25 | $96.25 |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 250 SY | $120 | $275 | $69.50 | $69.50 |
| 614E20366 WORK ZONE LANE LINE, CLASS I, 6", 648 | 46.45 MILE | $1,100 | $1,100 | $2,100 | $1,100 |
| 614E22336 WORK ZONE EDGE LINE, CLASS I, 6", 648 | 80.98 MILE | $1,984 | $1,984 | $4,100 | $1,984 |
| 614E23150 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 648 | 34,946 FT | $1.25 | $1.25 | $2.50 | $1.25 |
| 614E24142 WORK ZONE DOTTED LINE, CLASS I, 6", 648 | 20,916 FT | $0.75 | $0.75 | $2.90 | $0.75 |
| 614E25120 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS I, 648 | 309 FT | $7.00 | $7.00 | $8.00 | $7.00 |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 200 SY | $150 | $190 | $40.00 | $40.00 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 26.59 MILE | $650 | $650 | $880 | $650 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 27.48 MILE | $860 | $860 | $970 | $860 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 10,738 FT | $1.00 | $1.00 | $0.70 | $1.00 |
| 614E24612 WORK ZONE DOTTED LINE, CLASS III, 6", 642 PAINT | 5,251 FT | $0.85 | $0.85 | $0.50 | $0.85 |
| 896E00021 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 24 SNMT | $1,000 | $600 | $700 | $1,250 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $75,000 | $60,000 | $40,000 | $110,000 |
| 202E22900 APPROACH SLAB REMOVED | 200 SY | $40.00 | $85.00 | $43.00 | $95.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $16,500 | $1.00 | $7,500 | $400 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $2,000 | $25,000 | $9,500 | $50,000 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 13,723 LB | $1.25 | $1.50 | $1.10 | $1.50 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 700 LB | $1.00 | $1.50 | $1.40 | $1.50 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 136 EACH | $35.00 | $32.00 | $35.00 | $50.00 |
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 43 CY | $1,750 | $1,800 | $1,625 | $2,500 |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 9 CY | $1,450 | $1,200 | $1,725 | $2,500 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 47 SY | $47.00 | $26.68 | $20.00 | $26.68 |
| 512E10051 SEALING OF CONCRETE SURFACES (NON-EPOXY), AS PER P | 161 SY | $65.00 | $32.74 | $56.00 | $32.74 |
| 512E33000 TYPE 2 WATERPROOFING | 5 SY | $150 | $33.00 | $161 | $95.00 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 109 FT | $50.00 | $75.00 | $41.00 | $90.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 113 SF | $12.00 | $6.00 | $7.00 | $15.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 112 SF | $14.00 | $10.00 | $7.00 | $15.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 127 FT | $45.00 | $29.00 | $30.00 | $46.00 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $60,000 | $30,000 | $31,050 | $60,000 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 53 CY | $140 | $130 | $159 | $175 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 126 FT | $7.00 | $10.00 | $11.00 | $15.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 100 FT | $12.00 | $22.00 | $19.00 | $15.00 |
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 297 SY | $325 | $370 | $355 | $395 |
| 526E90030 TYPE C INSTALLATION | 109 FT | $285 | $330 | $200 | $450 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 25 SY | $170 | $44.00 | $250 | $35.00 |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 347 SY | $115 | $90.00 | $93.00 | $150 |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 310 SY | $115 | $147 | $107 | $140 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 2 CY | $275 | $278 | $248 | $264 |
| 848E50000 HAND CHIPPING | 4 SY | $170 | $750 | $256 | $150 |
| 848E50100 TEST SLAB | 1 LS | $2,900 | $4,800 | $2,400 | $10,000 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED, 1 3/4" THICK | 547 SY | $9.50 | $7.50 | $12.00 | $17.50 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 4 SY | $175 | $750 | $256 | $200 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $75,000 | $60,000 | $40,000 | $90,000 |
| 202E22900 APPROACH SLAB REMOVED | 200 SY | $40.00 | $85.00 | $43.00 | $80.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $15,000 | $1.00 | $7,500 | $400 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $2,000 | $25,000 | $9,500 | $30,000 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 13,723 LB | $1.25 | $1.50 | $1.10 | $1.25 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 700 LB | $1.00 | $1.50 | $1.40 | $1.25 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 136 EACH | $35.00 | $32.00 | $35.00 | $30.00 |
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 43 CY | $1,750 | $1,800 | $1,630 | $2,000 |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 9 CY | $1,450 | $1,200 | $1,725 | $2,000 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 47 SY | $36.00 | $26.68 | $20.00 | $26.68 |
| 512E10051 SEALING OF CONCRETE SURFACES (NON-EPOXY), AS PER P | 161 SY | $65.00 | $32.74 | $56.00 | $32.74 |
| 512E33000 TYPE 2 WATERPROOFING | 5 SY | $150 | $33.00 | $161 | $80.00 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 109 FT | $60.00 | $75.00 | $41.00 | $90.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 113 SF | $12.00 | $6.00 | $7.00 | $10.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 112 SF | $14.00 | $10.00 | $7.00 | $10.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 127 FT | $45.00 | $29.00 | $30.00 | $46.00 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $60,000 | $30,000 | $31,250 | $40,000 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 53 CY | $140 | $130 | $159 | $125 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 126 FT | $8.00 | $10.00 | $11.00 | $10.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 100 FT | $12.00 | $22.00 | $19.00 | $10.00 |
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 297 SY | $325 | $370 | $355 | $325 |
| 526E90030 TYPE C INSTALLATION | 109 FT | $275 | $330 | $200 | $375 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 25 SY | $170 | $44.00 | $250 | $35.00 |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 347 SY | $120 | $90.00 | $93.00 | $105 |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 310 SY | $116 | $147 | $107 | $105 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 2 CY | $275 | $278 | $248 | $264 |
| 848E50000 HAND CHIPPING | 4 SY | $170 | $750 | $256 | $125 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED, 1 3/4" THICK | 547 SY | $9.50 | $7.50 | $12.00 | $14.00 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 4 SY | $170 | $750 | $256 | $150 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $88,000 | $60,000 | $40,000 | $130,000 |
| 202E22900 APPROACH SLAB REMOVED | 200 SY | $40.00 | $85.00 | $43.00 | $95.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $14,000 | $1.00 | $7,550 | $400 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $2,000 | $25,000 | $9,500 | $50,000 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 11,558 LB | $1.24 | $1.50 | $1.20 | $1.50 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 800 LB | $1.00 | $1.50 | $1.40 | $1.50 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 146 EACH | $32.00 | $32.00 | $36.50 | $50.00 |
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 49 CY | $1,550 | $1,800 | $1,575 | $2,500 |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 9 CY | $1,500 | $1,200 | $1,725 | $2,500 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 50 SY | $36.00 | $25.49 | $26.00 | $25.49 |
| 512E10051 SEALING OF CONCRETE SURFACES (NON-EPOXY), AS PER P | 216 SY | $65.00 | $28.95 | $54.00 | $28.95 |
| 512E33000 TYPE 2 WATERPROOFING | 5 SY | $150 | $33.00 | $161 | $95.00 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 118 FT | $50.00 | $75.00 | $41.50 | $90.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 122 SF | $14.00 | $6.00 | $8.00 | $15.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 120 SF | $13.00 | $10.00 | $8.00 | $15.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 136 FT | $45.00 | $29.00 | $30.50 | $46.00 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $60,000 | $30,000 | $31,250 | $60,000 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 57 CY | $130 | $130 | $160 | $175 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 135 FT | $7.00 | $10.00 | $12.00 | $15.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 100 FT | $14.00 | $22.00 | $19.00 | $15.00 |
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 297 SY | $325 | $370 | $359 | $395 |
| 526E90030 TYPE C INSTALLATION | 118 FT | $275 | $330 | $203 | $450 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 35 SY | $180 | $44.00 | $144 | $45.00 |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 496 SY | $100 | $90.00 | $82.00 | $120 |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 459 SY | $105 | $147 | $104 | $120 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 3 CY | $275 | $278 | $279 | $264 |
| 848E50000 HAND CHIPPING | 5 SY | $135 | $750 | $214 | $250 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED, 1 3/4" THICK | 696 SY | $8.50 | $7.50 | $13.00 | $15.00 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 5 SY | $135 | $750 | $214 | $300 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $88,000 | $60,000 | $40,000 | $105,000 |
| 202E22900 APPROACH SLAB REMOVED | 200 SY | $40.00 | $85.00 | $43.25 | $80.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $14,000 | $1.00 | $7,550 | $400 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $2,000 | $25,000 | $9,500 | $30,000 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 11,558 LB | $1.24 | $1.50 | $1.20 | $1.25 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 800 LB | $1.00 | $1.50 | $1.40 | $1.25 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 146 EACH | $32.00 | $32.00 | $36.50 | $30.00 |
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 49 CY | $1,550 | $1,800 | $1,580 | $1,900 |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 9 CY | $1,500 | $1,200 | $1,725 | $1,900 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 50 SY | $36.00 | $25.49 | $26.00 | $25.49 |
| 512E10051 SEALING OF CONCRETE SURFACES (NON-EPOXY), AS PER P | 216 SY | $65.00 | $28.95 | $53.50 | $28.95 |
| 512E33000 TYPE 2 WATERPROOFING | 5 SY | $150 | $33.00 | $161 | $80.00 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 118 FT | $50.00 | $75.00 | $41.50 | $90.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 122 SF | $14.00 | $6.00 | $7.60 | $10.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 120 SF | $12.00 | $10.00 | $7.80 | $10.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 136 FT | $45.00 | $29.00 | $30.50 | $46.00 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $60,000 | $30,000 | $31,250 | $40,000 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 57 CY | $130 | $130 | $159 | $125 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 135 FT | $7.00 | $10.00 | $11.75 | $10.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 100 FT | $14.00 | $22.00 | $18.50 | $10.00 |
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 297 SY | $325 | $370 | $358 | $325 |
| 526E90030 TYPE C INSTALLATION | 118 FT | $275 | $330 | $203 | $375 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 35 SY | $180 | $44.00 | $144 | $45.00 |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 496 SY | $95.00 | $90.00 | $81.50 | $105 |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 459 SY | $105 | $147 | $104 | $105 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 3 CY | $275 | $278 | $279 | $264 |
| 848E50000 HAND CHIPPING | 5 SY | $135 | $750 | $214 | $250 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED, 1 3/4" THICK | 696 SY | $8.50 | $7.50 | $13.00 | $12.00 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 5 SY | $135 | $750 | $214 | $250 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $285,043 | $300,000 | $225,000 | $305,000 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $29,000 | $10,000 | $5,000 | $25,000 |
| 111E10100 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 18,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 619E16020 FIELD OFFICE, TYPE C | 30 MNTH | $6,250 | $6,000 | $5,000 | $2,600 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 302E66001 ASPHALT CONCRETE BASE, AS PER PLAN, 25.0MM GYRATOR | 96,316 CY | $135 | $13.0M | 24% |
| 442E10300 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 19,309 CY | $230 | $4.44M | 8% |
| 304E20000 AGGREGATE BASE | 60,609 CY | $50 | $3.03M | 6% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 16,532 CY | $165 | $2.73M | 5% |
| 624E10000 MOBILIZATION | 1 LS | $2,700,000 | $2.70M | 5% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 305,325 SY | $7.5 | $2.29M | 4% |
| 206E10500 CEMENT | 9,458 TON | $205 | $1.94M | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,856,500 | $1.86M | 3% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 31,699 SY | $55 | $1.74M | 3% |
| 203E10000 EXCAVATION | 110,659 CY | $12 | $1.33M | 2% |