HUR-SR 4-00.00
HUR County · est $5.5M
Bid dateThursday, February 13—
HUR County · est $5.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 44 more items below.
| Item | Quantity | R1Erie Blacktop INC | R2Gerken Paving INC | % of bid |
|---|---|---|---|---|
| 253E02001 PAVEMENT REPAIR, AS PER PLAN (LONGITUDINAL) | 6,252 CY | $148 | $222 | 22% |
| 442E20171 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 5,352 CY | $170 | $172 | 21% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 3,842 CY | $206 | $187 | 19% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE | 13,239 SY | $21.75 | $20.70 | 7% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 1,210 CY | $195 | $212 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $220,000 | $135,000 | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3.0 INCH) | 109,556 SY | $1.85 | $2.41 | 5% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN (TRANSVERSE) | 400 CY | $400 | $435 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $120,000 | $160,000 | 3% |
| 605E31101 AGGREGATE DRAINS, AS PER PLAN | 11,600 FT | $5.50 | $8.00 | 2% |
| 617E10100 COMPACTED AGGREGATE | 907 CY | $59.20 | $80.00 | 1% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 122 CY | $350 | $390 | 1% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 199 CY | $206 | $190 | 1% |
| 407E10000 TACK COAT | 14,349 GAL | $2.55 | $2.25 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 6,401 GAL | $4.80 | $6.75 | 1% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 2,580 SY | $11.25 | $5.00 | 1% |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 35,069 FT | $0.75 | $1.90 | 1% |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 13.28 MILE | $1,850 | $2,100 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $22,000 | $24,000 | 1% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 313 CY | $70.00 | $70.00 | 1% |
| Item | Quantity | R1Erie Blacktop INC | R2Gerken Paving INC |
|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 350 FT | $2.10 | $2.00 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 4 EACH | $105 | $135 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $105 | $75.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 10 CY | $68.25 | $136 |
| 204E13000 EXCAVATION OF SUBGRADE | 313 CY | $33.80 | $40.00 |
| 204E45000 PROOF ROLLING | 8 HOUR | $135 | $100 |
| 204E50000 GEOTEXTILE FABRIC | 626 SY | $2.40 | $3.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 209E15001 RESHAPING UNDER GUARDRAIL, AS PER PLAN | 5.5 STA | $78.75 | $60.00 |
| 209E80000 GRADING MAILBOX APPROACHES | 14 EACH | $220 | $600 |
| 606E13000 GUARDRAIL, TYPE 5 | 100 FT | $23.50 | $21.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 250 FT | $23.50 | $21.80 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 4 EACH | $2,575 | $2,420 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 4 EACH | $1,445 | $1,040 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25 INCH) | 469 SY | $1.85 | $2.41 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (TAPER 3.0" TO | 302 SY | $1.85 | $2.41 |
| 254E01600 PATCHING PLANED SURFACE | 552 SY | $9.75 | $18.00 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 6.64 MILE | $1,090 | $1,050 |
| 621E00100 RPM | 450 EACH | $43.60 | $41.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 450 EACH | $5.50 | $5.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 6 EACH | $11.55 | $12.50 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 13.32 MILE | $840 | $850 |
| 642E00300 CENTER LINE, TYPE 1 | 6.66 MILE | $840 | $600 |
| 644E00500 STOP LINE | 217 FT | $7.35 | $8.00 |
| 644E00620 CROSSWALK LINE, 12" | 52 FT | $4.20 | $4.00 |
| 644E01000 RAILROAD SYMBOL MARKING | 2 EACH | $630 | $700 |
| 644E01410 WORD ON PAVEMENT, 96" | 2 EACH | $265 | $200 |
| 644E01620 BIKE CROSSING SYMBOL | 2 EACH | $158 | $500 |
| 644E40000 SPEED MEASUREMENT MARKING | 5 EACH | $675 | $30.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 18 CY | $255 | $225 |
| 410E13000 TRAFFIC COMPACTED SURFACE, TYPE C | 110 CY | $120 | $145 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 75 HOUR | $89.25 | $110 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,875 | $12,000 |
| 614E12460 WORK ZONE MARKING SIGN | 29 EACH | $105 | $125 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $325 | $500 |
| 614E18000 MAINTAINING TRAFFIC, MISC.: TEMPORARY MAILBOXES | 26 EACH | $142 | $120 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $998 | $1,350 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 19.98 MILE | $840 | $600 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 117 FT | $3.15 | $3.00 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 102 FT | $27.35 | $26.04 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 100 FT | $110 | $118 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $4,500 | $5,400 |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $2,700 | $4,250 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,500 | $9,460 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 253E02001 PAVEMENT REPAIR, AS PER PLAN (LONGITUDINAL) | 6,252 CY | $148 | $925k | 21% |
| 442E20171 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 5,352 CY | $170 | $910k | 20% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 3,842 CY | $206 | $791k | 18% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE | 13,239 SY | $21.75 | $288k | 6% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 1,210 CY | $195 | $236k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $220,000 | $220k | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3.0 INCH) | 109,556 SY | $1.85 | $203k | 5% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN (TRANSVERSE) | 400 CY | $400 | $160k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $120,000 | $120k | 3% |
| 605E31101 AGGREGATE DRAINS, AS PER PLAN | 11,600 FT | $5.5 | $64k | 1% |