PIC-SR 762-11.18
PIC County · est $3.0M
Bid dateThursday, February 13—
PIC County · est $3.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 45 more items below.
| Item | Quantity | R1Shelly Company | R2Strawser Paving CO INC | R3Kokosing Construction Company INC | R4Axis Civil Construction LLC | R5Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|---|
| 253E02001 PAVEMENT REPAIR, AS PER PLAN, 13.75" | 5,087 CY | $180 | $185 | $205 | $225 | $215 | 51% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 3,106 CY | $57.00 | $68.00 | $50.00 | $75.00 | $63.00 | 10% |
| 204E13000 EXCAVATION OF SUBGRADE | 3,106 CY | $38.00 | $46.00 | $23.00 | $18.00 | $56.90 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $75,000 | $100,000 | $108,000 | $100,000 | $100,000 | 4% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 3,334 FT | $21.00 | $18.00 | $22.00 | $20.50 | $27.00 | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 3,487.5 FT |
| Item | Quantity | R1Shelly Company | R2Strawser Paving CO INC | R3Kokosing Construction Company INC | R4Axis Civil Construction LLC | R5Shelly & Sands INC |
|---|---|---|---|---|---|---|
| 202E38001 GUARDRAIL REMOVED, AS PER PLAN | 3,168 FT | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 202E42011 ANCHOR ASSEMBLY REMOVED, TYPE E, AS PER PLAN | 4 EACH | $175 | $135 | $135 | $175 | $175 |
| 202E47001 BRIDGE TERMINAL ASSEMBLY REMOVED, AS PER PLAN | 4 EACH | $125 | $60.00 | $60.00 | $125 | $125 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $18.50 |
| $17.60 |
| $17.60 |
| $18.50 |
| $18.50 |
| 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $49,250 | $100,000 | $86,179 | $50,000 | $155,742 | 3% |
| 605E14000 6" BASE PIPE UNDERDRAINS | 3,232 FT | $15.00 | $12.00 | $19.00 | $15.00 | $35.00 | 3% |
| 251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 479 SY | $78.50 | $80.00 | $150 | $145 | $95.00 | 2% |
| 202E34900 PIPE REMOVED, 6" BASE PIPE UNDERDRAIN | 3,283 FT | $9.35 | $6.50 | $9.00 | $1.80 | $10.50 | 2% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 145 CY | $203 | $300 | $255 | $355 | $225 | 2% |
| 252E01500 FULL DEPTH PAVEMENT SAWING, 13.75" | 17,490 FT | $1.50 | $1.25 | $1.59 | $1.60 | $0.25 | 1% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 8 EACH | $3,000 | $2,750 | $2,750 | $2,200 | $3,500 | 1% |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $19,500 | $33,320 | $10,080 | $27,000 | $13,500 | 1% |
| 304E20000 AGGREGATE BASE | 232 CY | $76.00 | $115 | $170 | $280 | $165 | 1% |
| 659E00300 TOPSOIL | 144 CY | $120 | $70.00 | $30.00 | $110 | $125 | 1% |
| 204E51000 GEOGRID | 9,346 SY | $1.75 | $5.00 | $1.50 | $2.00 | $2.50 | 1% |
| 611E06100 15" CONDUIT, TYPE C | 184 FT | $85.50 | $120 | $135 | $80.00 | $145 | 1% |
| 203E10000 EXCAVATION | 253 CY | $61.00 | $19.00 | $76.00 | $28.00 | $85.00 | 1% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN, 13.75 | 741 SY | $19.75 | $29.00 | $37.00 | $16.00 | $55.00 | 1% |
| 203E20000 EMBANKMENT | 216 CY | $47.50 | $48.00 | $21.00 | $21.00 | $82.50 |
| 204E10000 SUBGRADE COMPACTION | 1,391 SY | $2.85 | $3.50 | $4.75 | $2.00 | $5.00 |
| 209E60201 LINEAR GRADING, AS PER PLAN | 34.6 STA | $75.00 | $75.00 | $94.00 | $75.00 | $85.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 4 EACH | $2,400 | $2,380 | $2,380 | $2,400 | $2,400 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,400 | $2,450 | $2,450 | $2,400 | $2,400 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 113 SY | $85.00 | $74.00 | $96.00 | $70.00 | $65.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 6 CY | $350 | $380 | $300 | $155 | $600 |
| 659E10000 SEEDING AND MULCHING | 1,317 SY | $3.50 | $2.60 | $3.50 | $2.60 | $3.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 65 SY | $6.00 | $2.60 | $6.00 | $2.60 | $6.00 |
| 659E15000 INTER-SEEDING | 65 SY | $5.00 | $2.60 | $5.00 | $2.60 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.18 TON | $750 | $1,250 | $750 | $1,250 | $750 |
| 659E31000 LIME | 0.27 ACRE | $10.00 | $150 | $10.00 | $150 | $10.00 |
| 659E35000 WATER | 7 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.9 CY | $2,825 | $4,200 | $4,000 | $3,200 | $4,500 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 20 FT | $33.25 | $12.00 | $20.00 | $35.00 | $65.00 |
| 611E01500 6" CONDUIT, TYPE F | 40 FT | $20.00 | $12.00 | $55.00 | $28.00 | $50.00 |
| 611E98150 CATCH BASIN, NO. 3 | 1 EACH | $3,685 | $4,800 | $6,000 | $5,000 | $4,750 |
| 611E98180 CATCH BASIN, NO. 3A | 2 EACH | $2,985 | $3,800 | $4,500 | $4,600 | $4,000 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 4 EACH | $320 | $150 | $600 | $375 | $650 |
| 251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 8 SY | $800 | $185 | $850 | $252 | $95.00 |
| 407E20000 NON-TRACKING TACK COAT | 138 GAL | $3.90 | $4.40 | $2.80 | $5.00 | $3.50 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 35 CY | $295 | $575 | $550 | $495 | $235 |
| 621E00100 RPM | 84 EACH | $65.00 | $62.00 | $65.00 | $65.00 | $65.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 84 EACH | $4.50 | $1.00 | $1.00 | $5.00 | $15.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, 2-WAY | 57 EACH | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 644E00104 EDGE LINE, 6" | 1.78 MILE | $4,791 | $4,791 | $4,791 | $4,791 | $4,200 |
| 644E00300 CENTER LINE | 1.83 MILE | $5,350 | $5,350 | $5,350 | $5,350 | $5,400 |
| 644E00400 CHANNELIZING LINE, 8" | 100 FT | $2.90 | $2.90 | $2.90 | $2.90 | $2.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 948 FT | $7.30 | $7.30 | $7.30 | $7.30 | $7.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING, CENTER LINE | 8,232 FT | $0.35 | $0.35 | $0.35 | $0.35 | $0.55 |
| 644E30000 REMOVAL OF PAVEMENT MARKING, TRANSVERSE LINE | 294 FT | $5.00 | $5.00 | $5.00 | $5.00 | $2.00 |
| 644E30030 REMOVAL OF PAVEMENT MARKING, EDGE LINE | 2.59 MILE | $1,848 | $1,848 | $1,848 | $1,848 | $2,600 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 72 HOUR | $80.00 | $82.00 | $75.00 | $85.00 | $110 |
| 614E12460 WORK ZONE MARKING SIGN | 12 EACH | $100 | $85.00 | $125 | $200 | $100 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $1,500 | $900 | $900 | $750 | $1,500 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.83 MILE | $1,050 | $1,705 | $1,705 | $1,705 | $1,705 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 6.96 MILE | $1,075 | $900 | $900 | $900 | $1,300 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 100 FT | $5.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 168 FT | $6.00 | $5.00 | $5.00 | $5.00 | $8.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,000 | $15,000 | $9,000 | $13,000 | $10,389 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $9,500 | $13,200 | $6,000 | $3,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 253E02001 PAVEMENT REPAIR, AS PER PLAN, 13.75" | 5,087 CY | $180.25 | $917k | 47% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 3,106 CY | $57 | $177k | 9% |
| 204E13000 EXCAVATION OF SUBGRADE | 3,106 CY | $38 | $118k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $75,000 | $75k | 4% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 3,334 FT | $21 | $70k | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 3,487.5 FT | $18.5 | $65k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $49,250 | $49k | 3% |
| 605E14000 6" BASE PIPE UNDERDRAINS | 3,232 FT | $15 | $48k | 2% |
| 251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 479 SY | $78.5 | $38k | 2% |
| 202E34900 PIPE REMOVED, 6" BASE PIPE UNDERDRAIN | 3,283 FT | $9.35 | $31k | 2% |