ERI-SR 60-00.00
ERI County · est $1.2M
Bid dateThursday, February 27—
ERI County · est $1.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 31 more items below.
| Item | Quantity | R1Erie Blacktop INC | R2Kokosing Construction Company INC | R3Gerken Paving INC | % of bid |
|---|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 2,183 CY | $214 | $242 | $213 | 47% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)(Longitudinal) | 420 CY | $220 | $220 | $250 | 9% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(2.00?) | 52,595 SY | $1.55 | $1.60 | $2.40 | 8% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442) (TRANSVERSE) | 180 CY | $450 | $245 | $445 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $54,450 | $34,000 | 5% |
| 617E10100 COMPACTED AGGREGATE | 461 CY | $78.00 | $30.00 | $90.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS |
| Item | Quantity | R1Erie Blacktop INC | R2Kokosing Construction Company INC | R3Gerken Paving INC |
|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 187.5 FT | $2.10 | $2.00 | $2.00 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 2 EACH | $152 | $150 | $145 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 1 EACH | $99.75 | $150 | $95.00 |
| 202E42050 ANCHOR ASSEMBLY REMOVED, TYPE B | 7 EACH | $116 | $150 | $110 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 2 EACH | $78.75 | $250 | $75.00 |
| 203E20001 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $35,000 |
| $75,000 |
| $64,000 |
| 4% |
| 621E00100 RPM | 365 EACH | $43.60 | $34.00 | $41.50 | 2% |
| 408E10001 PRIME COAT, AS PER PLAN | 3,281 GAL | $4.80 | $4.00 | $5.50 | 2% |
| 253E02000 PAVEMENT REPAIR (FULL DEPTH FLEXIBLE) (LONGITUDINA | 42 CY | $300 | $345 | $350 | 1% |
| 253E02000 PAVEMENT REPAIR (FULL DEPTH FLEXIBLE) (TRANSVERSE) | 18 CY | $700 | $370 | $625 | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 5 EACH | $2,510 | $2,400 | $2,390 | 1% |
| 407E10000 TACK COAT (0.09 GAL/SY) | 4,774 GAL | $2.55 | $2.00 | $2.50 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $2,850 | $2,200 | $3,000 | 1% |
| 209E60500 LINEAR GRADING | 6.4 MILE | $1,750 | $3,700 | $2,100 | 1% |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $11,000 | $1,500 | $3,500 | 1% |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 14 EACH | $700 | $375 | $1,200 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 6.88 MILE | $1,260 | $1,190 | $1,100 | 1% |
| 623E39601 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE, AS PER P | 5 EACH | $1,600 | $1,100 | $2,750 | 1% |
| 606E15050 GUARDRAIL, TYPE MGS | 375 FT | $20.40 | $19.00 | $19.40 | 1% |
| 12 CY |
| $79.80 |
| $65.00 |
| $76.00 |
| 209E80000 GRADING MAILBOX APPROACHES | 69 EACH | $90.00 | $20.00 | $560 |
| 606E17000 RAISING TYPE 5 GUARDRAIL | 100 FT | $7.15 | $9.50 | $6.80 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 5 EACH | $1,386 | $1,100 | $1,320 |
| 606E27900 ANCHOR ASSEMBLY REBUILT, TYPE T | 2 EACH | $945 | $650 | $900 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 2 EACH | $2,610 | $2,275 | $2,485 |
| 614E13312 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 19 EACH | $12.60 | $11.00 | $12.00 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $190 | $450 | $550 |
| 832E30000 EROSION CONTROL | 500 EACH | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 1 EACH | $1,450 | $1,400 | $3,250 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3.00") | 381 SY | $3.30 | $10.00 | $2.90 |
| 254E01600 PATCHING PLANED SURFACE | 245 SY | $12.50 | $1.25 | $28.00 |
| 407E10000 TACK COAT (0.06 GAL/SY) | 24 GAL | $2.55 | $2.00 | $2.50 |
| 442E22301 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 17 CY | $250 | $600 | $465 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 365 EACH | $7.00 | $2.50 | $5.50 |
| 642E00104 EDGE LINE, 6", TYPE 1 (WHITE) | 6.4 MILE | $1,000 | $850 | $1,100 |
| 642E00300 CENTER LINE, TYPE 1 | 3.2 MILE | $1,210 | $990 | $1,100 |
| 644E00500 STOP LINE | 135 FT | $15.75 | $14.00 | $25.00 |
| 646E10010 EDGE LINE, 6" (WHITE) | 0.46 MILE | $10,500 | $5,800 | $7,550 |
| 646E10200 CENTER LINE (WHITE) | 0.23 MILE | $15,750 | $5,800 | $14,765 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 50 HOUR | $89.25 | $95.00 | $100 |
| 614E12460 WORK ZONE MARKING SIGN | 34 EACH | $94.50 | $94.50 | $125 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $285 | $100 | $550 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 270 FT | $3.15 | $6.00 | $3.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,250 | $4,350 | $5,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,850 | $3,000 | $15,815 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 2,183 CY | $214 | $467k | 43% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)(Longitudinal) | 420 CY | $220 | $92k | 9% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(2.00?) | 52,595 SY | $1.55 | $82k | 8% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442) (TRANSVERSE) | 180 CY | $450 | $81k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $50k | 5% |
| 617E10100 COMPACTED AGGREGATE | 461 CY | $78 | $36k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $35,000 | $35k | 3% |
| 621E00100 RPM | 365 EACH | $43.6 | $16k | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 3,281 GAL | $4.8 | $16k | 1% |
| 253E02000 PAVEMENT REPAIR (FULL DEPTH FLEXIBLE) (LONGITUDINA | 42 CY | $300 | $13k | 1% |