ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 181 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Allard Excavation LLC | R3George J Igel & CO INC | R4Kanawha Stone Company Incorporated | R5Triton Construction INC | R6Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 931,325 CY | $6.25 | $8.25 | $9.00 | $8.00 | $10.00 | $12.00 | 23% |
| 302E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 19,377 CY | $190 | $193 | $198 | $198 | $208 | $230 | 15% |
| 442E10300 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 11,730 CY | $235 | $242 |
| Item | Quantity | R1Kokosing Construction Company INC | R2Allard Excavation LLC | R3George J Igel & CO INC | R4Kanawha Stone Company Incorporated | R5Triton Construction INC | R6Alan Stone CO INC |
|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $100,000 | $950,000 | $935,000 | $1,549,991 | $403,953 | $650,000 |
| 202E20010 HEADWALL REMOVED | 1 EACH | $350 | $256 | $550 | $457 | $500 | $470 |
| 202E23000 PAVEMENT REMOVED | 28,966 SY | $5.00 | $10.00 | $6.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $242 |
| $242 |
| $255 |
| $280 |
| 11% |
| 304E20000 AGGREGATE BASE | 21,687 CY | $95.00 | $92.00 | $102 | $121 | $105 | $100 | 8% |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 9,607 CY | $200 | $204 | $208 | $208 | $220 | $240 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $1,560,000 | $1,750,000 | $1,628,000 | $741,365 | $1,925,000 | $466,000 | 6% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 6,064 CY | $205 | $208 | $213 | $213 | $225 | $240 | 5% |
| 507E00400 STEEL PILES, MISC.: W36X262 | 2,323.4 FT | $380 | $307 | $340 | $315 | $400 | $570 | 4% |
| 832E30000 EROSION CONTROL | 800,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 204E30011 GRANULAR MATERIAL, TYPE B, AS PER PLAN | 8,317 CY | $85.00 | $91.00 | $100 | $119 | $120 | $70.00 | 3% |
| 605E13500 6" ROCK CUT UNDERDRAINS | 28,000 FT | $18.00 | $23.00 | $16.00 | $17.71 | $17.00 | $20.00 | 2% |
| 203E20000 EMBANKMENT | 507,036 CY | $0.95 | $3.00 | $2.25 | $1.59 | $2.00 | $2.00 | 2% |
| 255E11000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 1,997 SY | $225 | $273 | $171 | $338 | $235 | $260 | 2% |
| 524E94903 DRILLED SHAFTS, 48" DIAMETER ABOVE BEDROCK, AS PER | 1,493.9 FT | $260 | $165 | $140 | $410 | $300 | $300 | 2% |
| 524E94905 DRILLED SHAFTS, 48" DIAMETER, INTO BEDROCK, AS PER | 840 FT | $430 | $185 | $280 | $410 | $155 | $440 | 1% |
| 606E15050 GUARDRAIL, TYPE MGS | 20,925 FT | $16.78 | $16.78 | $16.78 | $16.78 | $16.78 | $20.00 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $334,000 | $350,000 | $815,000 | $573,372 | $200,000 | $810,000 | 1% |
| 616E10000 WATER | 4,300 MGAL | $70.00 | $1.00 | $38.00 | $65.99 | $20.00 | $35.00 | 1% |
| 611E07400 18" CONDUIT, TYPE B | 1,391 FT | $210 | $121 | $340 | $118 | $210 | $95.00 | 1% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 11,122 FT | $22.00 | $14.00 | $11.00 | $15.07 | $18.00 | $20.00 | 1% |
| $5.19 |
| $5.00 |
| $10.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 110 FT | $16.00 | $7.00 | $4.50 | $16.53 | $30.00 | $15.00 |
| 202E35101 PIPE REMOVED, 24" DIAMETER AND UNDER, AS PER PLAN | 565 FT | $12.00 | $7.00 | $4.00 | $24.59 | $50.00 | $15.00 |
| 202E38000 GUARDRAIL REMOVED | 19,827.5 FT | $1.80 | $2.00 | $1.80 | $1.90 | $3.00 | $2.50 |
| 202E47800 IMPACT ATTENUATOR REMOVED | 1 EACH | $150 | $186 | $150 | $150 | $500 | $160 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $1,700 | $390 | $200 | $1,077 | $1,500 | $470 |
| 202E75000 FENCE REMOVED | 924 FT | $5.00 | $2.00 | $6.50 | $4.05 | $4.00 | $5.00 |
| 203E35121 GRANULAR MATERIAL, TYPE C, AS PER PLAN | 470 CY | $116 | $109 | $110 | $112 | $120 | $120 |
| 203E65000 SPECIAL - SETTLEMENT PLATFORM | 3 EACH | $1,340 | $5,961 | $6,300 | $6,784 | $1,200 | $6,100 |
| 204E10000 SUBGRADE COMPACTION | 133,105 SY | $1.77 | $1.42 | $1.00 | $2.05 | $2.00 | $1.50 |
| 204E13000 EXCAVATION OF SUBGRADE | 8,317 CY | $6.25 | $8.00 | $21.75 | $3.62 | $10.00 | $20.00 |
| 204E45000 PROOF ROLLING | 45 HOUR | $250 | $268 | $120 | $256 | $250 | $1,000 |
| 208E10000 PRE-BLAST CONDITION SURVEY | 1 LS | $34,775 | $8,595 | $34,755 | $34,755 | $25,000 | $95,000 |
| 208E12000 BLASTING CONSULTANT | 1 LS | $5,000 | $5,500 | $5,500 | $5,500 | $10,000 | $60,000 |
| 208E13000 AIR BLAST AND NOISE CONTROL | 1 LS | $8,775 | $10,000 | $15,600 | $7,800 | $15,000 | $17,000 |
| 208E14000 VIBRATION CONTROL AND MONITORING | 1 LS | $8,775 | $10,000 | $15,600 | $7,800 | $30,000 | $15,000 |
| 208E16000 HYDROLOGIST | 1 LS | $15,300 | $45,000 | $27,300 | $46,500 | $90,000 | $150,000 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 132.5 STA | $85.00 | $64.00 | $280 | $89.88 | $80.00 | $150 |
| 209E70000 BORROW | 350.8 CY | $85.00 | $43.00 | $31.00 | $66.07 | $80.00 | $25.00 |
| 606E15400 MGS GUARDRAIL, TYPE 8 | 2,450 FT | $25.62 | $25.92 | $25.62 | $25.62 | $25.62 | $30.00 |
| 606E15550 GUARDRAIL, BARRIER DESIGN, TYPE MGS | 62.5 FT | $31.20 | $31.20 | $31.20 | $31.20 | $31.20 | $35.00 |
| 606E17050 RAISING TYPE MGS GUARDRAIL | 2,087.5 FT | $4.50 | $4.50 | $4.50 | $4.50 | $4.50 | $5.00 |
| 606E17500 POST END ANCHOR (OR CONCRETE BLOCK END ANCHOR) | 18 EACH | $1,280 | $1,280 | $1,280 | $1,280 | $1,280 | $1,500 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, (MASH 2016) | 6 EACH | $2,180 | $2,180 | $2,180 | $2,180 | $2,180 | $2,500 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 26 EACH | $1,000 | $1,000 | $1,000 | $1,000 | $1,000 | $1,100 |
| 606E27846 ANCHOR ASSEMBLY REBUILT, MGS TYPE B | 1 EACH | $760 | $760 | $760 | $760 | $760 | $870 |
| 606E27910 ANCHOR ASSEMBLY REBUILT, MGS TYPE T | 1 EACH | $450 | $450 | $450 | $450 | $450 | $510 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 3 EACH | $1,980 | $1,980 | $1,980 | $1,980 | $1,980 | $2,300 |
| 606E35012 MGS BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 1 | 2 EACH | $1,250 | $1,250 | $1,250 | $1,250 | $1,250 | $1,400 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $340 | $340 | $340 | $340 | $340 | $390 |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 1 EACH | $7,500 | $7,500 | $7,500 | $7,500 | $7,500 | $8,600 |
| 607E15000 FENCE, TYPE 47 | 853 FT | $15.16 | $15.16 | $15.16 | $15.16 | $15.16 | $15.00 |
| 623E40500 REFERENCE MONUMENT, TYPE A | 60 EACH | $480 | $789 | $760 | $784 | $700 | $1,200 |
| 601E25000 DUMPED ROCK FILL, TYPE A | 27 CY | $140 | $105 | $130 | $164 | $170 | $120 |
| 601E26001 DUMPED ROCK FILL, TYPE B, AS PER PLAN | 3,056 CY | $11.00 | $104 | $115 | $129 | $140 | $65.00 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 892 CY | $140 | $115 | $120 | $136 | $125 | $75.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 1,382 CY | $145 | $115 | $120 | $131 | $160 | $70.00 |
| 659E00300 TOPSOIL | 8,983 CY | $9.00 | $20.00 | $7.00 | $30.07 | $25.00 | $15.00 |
| 659E10000 SEEDING AND MULCHING | 393,050 SY | $0.60 | $0.48 | $0.65 | $0.75 | $0.60 | $0.60 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 39,133 SY | $0.55 | $1.00 | $0.85 | $1.00 | $0.55 | $1.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 21,610 SY | $0.60 | $1.00 | $0.65 | $0.75 | $0.60 | $0.50 |
| 659E15000 INTER-SEEDING | 21,610 SY | $0.01 | $0.01 | $0.65 | $1.00 | $0.01 | $0.01 |
| 659E20000 COMMERCIAL FERTILIZER | 39 TON | $250 | $1,863 | $1,250 | $1,250 | $250 | $1,700 |
| 659E31000 LIME | 89.3 ACRE | $25.00 | $185 | $150 | $150 | $25.00 | $230 |
| 659E35000 WATER | 1,167 MGAL | $0.01 | $1.00 | $1.00 | $1.00 | $0.01 | $1.00 |
| 659E40000 MOWING | 3,168 MSF | $1.00 | $1.00 | $10.00 | $10.00 | $12.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 88,117 SY | $1.15 | $2.00 | $2.50 | $2.50 | $1.15 | $2.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $8,375 | $15,000 | $8,500 | $8,857 | $30,000 | $9,600 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $40,000 | $65,000 | $43,700 | $29,189 | $130,000 | $59,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $40,000 | $40,000 | $29,300 | $41,216 | $35,000 | $33,000 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 1,073 SY | $5.00 | $6.00 | $6.00 | $6.00 | $5.00 | $5.00 |
| 503E31100 ROCK EXCAVATION | 814 CY | $35.00 | $22.00 | $69.50 | $145 | $75.00 | $20.00 |
| 602E20000 CONCRETE MASONRY | 8.19 CY | $6,420 | $4,142 | $3,500 | $4,695 | $6,500 | $3,000 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 16,446 FT | $14.00 | $14.00 | $12.00 | $13.48 | $16.00 | $20.00 |
| 605E13402 6" UNCLASSIFIED PIPE UNDERDRAINS FOR SPRINGS | 1,200 FT | $30.00 | $30.00 | $15.75 | $19.53 | $30.00 | $20.00 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 13,058 FT | $9.00 | $13.00 | $9.00 | $11.37 | $12.00 | $15.00 |
| 605E32200 AGGREGATE DRAINS FOR SPRINGS | 200 FT | $16.00 | $46.00 | $22.75 | $48.29 | $30.00 | $25.00 |
| 611E00406 4" CONDUIT, TYPE F | 453 FT | $60.00 | $26.00 | $48.00 | $38.31 | $25.00 | $30.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 2,126 FT | $34.00 | $22.00 | $28.00 | $25.38 | $24.00 | $30.00 |
| 611E01500 6" CONDUIT, TYPE F | 10 FT | $67.00 | $16.00 | $65.00 | $80.18 | $30.00 | $60.00 |
| 611E04400 12" CONDUIT, TYPE B | 835 FT | $190 | $102 | $220 | $101 | $160 | $100 |
| 611E04600 12" CONDUIT, TYPE C | 1,000 FT | $145 | $65.00 | $75.00 | $93.19 | $160 | $100 |
| 611E07600 18" CONDUIT, TYPE C | 200 FT | $190 | $93.00 | $100 | $107 | $210 | $120 |
| 611E08900 21" CONDUIT, TYPE B | 628 FT | $270 | $137 | $270 | $135 | $240 | $130 |
| 611E97600 CONDUIT, MISC.: CLASS QC1 CONCRETE BACKFILL | 105 CY | $330 | $358 | $310 | $590 | $400 | $300 |
| 611E98230 CATCH BASIN, NO. 4 | 18 EACH | $9,930 | $5,148 | $5,500 | $7,373 | $9,500 | $5,600 |
| 611E98410 CATCH BASIN, NO. 8 | 2 EACH | $9,345 | $4,535 | $3,900 | $6,674 | $8,500 | $4,800 |
| 611E98505 CATCH BASIN, NO. 2-2C, AS PER PLAN | 13 EACH | $4,710 | $3,099 | $4,100 | $4,450 | $4,200 | $2,800 |
| 611E99575 MANHOLE, NO. 3, AS PER PLAN | 1 EACH | $7,485 | $4,993 | $11,000 | $6,171 | $6,500 | $4,200 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 11 EACH | $950 | $448 | $364 | $476 | $450 | $650 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 27,439 FT | $2.47 | $2.85 | $1.98 | $1.90 | $5.00 | $3.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 837 SY | $13.50 | $13.50 | $13.50 | $2.41 | $14.00 | $9.00 |
| 254E01010 PAVEMENT PLANING, PORTLAND CEMENT CONCRETE, 1.5" | 2,498 SY | $12.00 | $13.50 | $13.50 | $10.46 | $14.00 | $7.00 |
| 254E01010 PAVEMENT PLANING, PORTLAND CEMENT CONCRETE, VARIAB | 153 SY | $66.50 | $13.50 | $13.50 | $13.75 | $14.00 | $40.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 6,200 FT | $3.90 | $5.00 | $3.00 | $3.00 | $5.00 | $5.50 |
| 407E13900 TACK COAT, 702.13 | 12,544 GAL | $4.05 | $4.05 | $4.05 | $4.05 | $4.05 | $4.50 |
| 407E20000 NON-TRACKING TACK COAT | 20,192 GAL | $4.45 | $4.35 | $4.45 | $4.45 | $4.45 | $5.00 |
| 408E10000 PRIME COAT | 2,790 GAL | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.50 |
| 441E70800 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (662.6 CY | $341 | $345 | $345 | $345 | $362 | $390 |
| 442E00100 ANTI-SEGREGATION EQUIPMENT | 16,187 CY | $7.00 | $7.00 | $7.00 | $7.00 | $8.00 | $8.00 |
| 617E10100 COMPACTED AGGREGATE | 364 CY | $135 | $135 | $135 | $87.12 | $145 | $120 |
| 618E40600 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 23.2 MILE | $880 | $635 | $1,150 | $1,320 | $635 | $1,500 |
| 625E00450 CONNECTION, FUSED PULL APART | 4 EACH | $226 | $140 | $115 | $140 | $140 | $180 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 4 EACH | $220 | $140 | $115 | $140 | $140 | $180 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 10 EACH | $192 | $140 | $115 | $140 | $140 | $180 |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 3 EACH | $3,960 | $3,550 | $2,900 | $3,550 | $3,550 | $4,500 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 1,605 FT | $4.60 | $3.50 | $3.80 | $3.50 | $3.50 | $4.50 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 744 FT | $2.60 | $2.50 | $1.75 | $2.50 | $2.50 | $3.00 |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 144 FT | $39.00 | $33.00 | $12.00 | $33.00 | $33.00 | $40.00 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 3" | 371 FT | $143 | $52.00 | $50.00 | $52.00 | $52.00 | $65.00 |
| 625E25910 CONDUIT CLEANED AND CABLES REMOVED | 149 FT | $6.10 | $1.00 | $1.00 | $1.00 | $1.00 | $1.50 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 4 EACH | $530 | $775 | $575 | $775 | $775 | $980 |
| 625E29002 TRENCH, 24" DEEP | 104 FT | $26.00 | $10.00 | $14.00 | $10.00 | $10.00 | $15.00 |
| 625E30700 PULL BOX, 725.08, 18" | 4 EACH | $1,820 | $1,450 | $1,150 | $1,450 | $1,450 | $1,800 |
| 625E32000 GROUND ROD | 4 EACH | $350 | $325 | $276 | $325 | $325 | $410 |
| 625E34001 POWER SERVICE, AS PER PLAN | 2 EACH | $18,800 | $7,700 | $8,925 | $7,700 | $7,700 | $9,800 |
| 625E35010 REMOVE AND REERECT EXISTING LIGHT POLE | 4 EACH | $3,110 | $1,400 | $1,375 | $1,400 | $1,400 | $1,800 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 104 FT | $8.50 | $1.00 | $3.00 | $1.00 | $1.00 | $1.50 |
| 625E75510 POWER SERVICE REMOVED | 2 EACH | $1,650 | $500 | $650 | $500 | $500 | $630 |
| 625E75522 LUMINAIRE SUPPORT FOUNDATION REMOVED | 3 EACH | $750 | $650 | $500 | $650 | $650 | $820 |
| 625E75551 DISTRIBUTION CABLE REMOVED, AS PER PLAN | 480 FT | $4.80 | $1.50 | $1.00 | $1.50 | $1.50 | $2.00 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL (PS-1 AT US 33 & | 1 EACH | $630 | $2,350 | $4,000 | $2,350 | $2,350 | $3,000 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL (PS-1 AT US 33 & | 1 EACH | $630 | $2,350 | $4,000 | $2,350 | $2,350 | $3,000 |
| 625E98000 LIGHTING, MISC.: REUSE AND REHABILITATION OF EXIST | 1 EACH | $2,700 | $1,250 | $250 | $1,250 | $1,250 | $1,600 |
| 625E98000 LIGHTING, MISC.: REUSE AND REHABILITATION OF EXIST | 3 EACH | $990 | $1,250 | $250 | $1,250 | $1,250 | $1,600 |
| 621E00100 RPM | 895 EACH | $36.00 | $36.00 | $35.00 | $36.00 | $36.00 | $36.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 485 EACH | $28.00 | $31.00 | $31.00 | $31.00 | $6.00 | $31.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, (1WAY) | 259 EACH | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, (BIDIRECTIONAL) | 39 EACH | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 | $10.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 156 FT | $8.30 | $8.30 | $8.30 | $8.30 | $8.30 | $9.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 867 FT | $10.20 | $10.20 | $10.20 | $10.20 | $10.20 | $10.00 |
| 630E04101 GROUND MOUNTED SUPPORT, NO. 4 POST, AS PER PLAN | 88 FT | $14.20 | $14.20 | $14.20 | $14.20 | $14.20 | $15.00 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 143.7 FT | $22.60 | $22.60 | $22.60 | $22.60 | $22.60 | $25.00 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 71.5 FT | $23.00 | $23.00 | $23.00 | $23.00 | $23.00 | $25.00 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 366.7 FT | $27.60 | $27.60 | $27.60 | $27.60 | $27.60 | $30.00 |
| 630E08000 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W12X30 | 235.6 FT | $56.00 | $56.00 | $56.00 | $56.00 | $56.00 | $65.00 |
| 630E08600 SIGN POST REFLECTOR (RED) | 17 EACH | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 | $25.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 34 EACH | $650 | $650 | $650 | $650 | $650 | $740 |
| 630E80100 SIGN, FLAT SHEET | 553.5 SF | $13.60 | $13.60 | $13.60 | $13.60 | $13.60 | $15.00 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 1,650 SF | $19.50 | $19.50 | $19.50 | $19.50 | $19.50 | $20.00 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 42 EACH | $1,480 | $1,480 | $1,480 | $1,480 | $1,480 | $1,700 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 30 EACH | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 | $15.00 |
| 630E85000 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE | 70 EACH | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 | $25.00 |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 10 EACH | $115 | $115 | $115 | $115 | $115 | $130 |
| 630E86006 REMOVAL OF GROUND MOUNTED POST SUPPORT AND STORAGE | 116 EACH | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 | $65.00 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 24 EACH | $250 | $250 | $250 | $250 | $250 | $290 |
| 644E00500 STOP LINE | 111 FT | $8.50 | $8.50 | $8.50 | $8.50 | $8.50 | $9.50 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 777 FT | $8.50 | $8.50 | $8.50 | $8.50 | $8.50 | $9.50 |
| 644E00900 ISLAND MARKING | 904 SF | $2.50 | $2.50 | $2.50 | $2.50 | $2.50 | $3.00 |
| 644E01300 LANE ARROW | 12 EACH | $105 | $105 | $105 | $105 | $105 | $120 |
| 645E00118 EDGE LINE, 6", TYPE A4 | 0.22 MILE | $58,350 | $58,350 | $58,350 | $58,350 | $58,350 | $67,000 |
| 645E00220 LANE LINE, 6", TYPE A4 | 0.12 MILE | $30,225 | $30,225 | $30,225 | $30,225 | $30,225 | $35,000 |
| 646E50100 REMOVAL OF PAVEMENT MARKING (TRANSVERSE LINE) | 3,267 FT | $4.22 | $4.72 | $4.72 | $4.70 | $5.00 | $5.50 |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 10.58 MILE | $2,003 | $5,700 | $5,700 | $5,700 | $5,700 | $6,500 |
| 807E14010 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, EDG | 24.84 MILE | $5,150 | $5,150 | $5,150 | $5,150 | $5,150 | $5,900 |
| 807E14110 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, LAN | 11.82 MILE | $2,390 | $2,390 | $2,390 | $2,390 | $2,390 | $2,700 |
| 807E14310 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, CHA | 6,553 FT | $2.75 | $2.75 | $2.75 | $2.75 | $2.75 | $3.00 |
| 807E14410 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, DOT | 1,378 FT | $1.10 | $1.40 | $1.10 | $1.10 | $1.10 | $1.50 |
| 850E10010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $2,617 | $2,617 | $2,617 | $2,617 | $2,617 | $3,000 |
| 850E10110 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1.35 | $1.35 | $1.35 | $1.35 | $1.35 | $1.50 |
| 850E10130 GROOVING FOR 12" RECESSED PAVEMENT MARKING | — | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.50 |
| 410E10000 TRAFFIC COMPACTED SURFACE, TYPE A | 100 CY | $216 | $151 | $116 | $118 | $200 | $140 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 175 HOUR | $120 | $112 | $100 | $93.06 | $70.00 | $110 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $8,920 | $2,200 | $2,575 | $5,000 | $2,500 | $3,500 |
| 614E12420 DETOUR SIGNING (PINE GROVE RD) | 1 LS | $6,500 | $3,500 | $3,500 | $3,500 | $3,500 | $4,000 |
| 614E12420 DETOUR SIGNING (MORNING STAR RD) | 1 LS | $5,400 | $2,950 | $2,950 | $2,950 | $2,950 | $3,400 |
| 614E12460 WORK ZONE MARKING SIGN | 26 EACH | $85.00 | $85.00 | $85.00 | $85.00 | $85.00 | $95.00 |
| 614E12600 REPLACEMENT DRUM | 200 EACH | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 | $90.00 |
| 614E12756 WORK ZONE CROSSOVER LIGHTING SYSTEM | 1 EACH | $40,000 | $48,750 | $72,500 | $48,750 | $48,750 | $62,000 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 150 CY | $250 | $250 | $298 | $135 | $400 | $350 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, (1WAY) | 165 EACH | $18.00 | $18.00 | $11.00 | $18.00 | $18.00 | $20.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, (BIDIRECTIONAL) | 211 EACH | $20.25 | $20.25 | $14.25 | $20.25 | $20.25 | $25.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 165 EACH | $22.50 | $22.50 | $15.25 | $22.50 | $22.50 | $25.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 211 EACH | $26.50 | $26.50 | $18.75 | $26.50 | $26.50 | $30.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 24 SNMT | $1,500 | $1,500 | $1,500 | $1,500 | $1,500 | $1,700 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 4.1 MILE | $975 | $975 | $975 | $975 | $975 | $1,100 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 28.61 MILE | $825 | $825 | $825 | $825 | $825 | $940 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 4,514 FT | $0.65 | $0.65 | $0.65 | $0.65 | $0.65 | $0.70 |
| 614E24612 WORK ZONE DOTTED LINE, CLASS III, 6", 642 PAINT | 3,134 FT | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 614E25620 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS III, 642 | 2,058 FT | $4.50 | $4.50 | $4.50 | $4.50 | $4.50 | $5.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 48 FT | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 | $15.00 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 24 EACH | $160 | $160 | $160 | $160 | $160 | $180 |
| 614E31670 WORK ZONE WORD ON PAVEMENT, 96", CLASS III, 642 PA | 8 EACH | $270 | $270 | $270 | $270 | $270 | $310 |
| 615E10001 ROADS FOR MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $10,000 | $32,000 | $80,100 | $17,315 | $150,000 | $120,000 |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 2,261 SY | $51.00 | $83.00 | $65.00 | $86.67 | $85.00 | $65.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 9,168 FT | $21.00 | $33.00 | $21.50 | $27.72 | $75.00 | $22.00 |
| 642E30000 REMOVAL OF PAVEMENT MARKING (TRANSVERSE) | 1,004 FT | $4.22 | $4.72 | $4.72 | $4.70 | $5.00 | $5.50 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 12 EACH | $48.03 | $52.00 | $52.00 | $52.00 | $52.00 | $60.00 |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 4.02 MILE | $2,003 | $3,300 | $3,300 | $3,300 | $3,300 | $3,800 |
| 831E00500 REMOVAL OF LONGITUDINAL CHANNELIZING DEVICE | 369 FT | $4.00 | $6.00 | $9.00 | $0.52 | $7.00 | $4.50 |
| 614E20110 WORK ZONE LANE LINE, CLASS I, 6", 642 PAINT | 23.64 MILE | $675 | $675 | $675 | $714 | $675 | $770 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 11.82 MILE | $525 | $525 | $525 | $555 | $525 | $600 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 49.68 MILE | $1,245 | $1,245 | $1,245 | $1,317 | $1,245 | $1,400 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $135,900 | $198,703 | $125,000 | $167,190 | $160,000 | $200,000 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $5,000 | $40,000 | $7,500 | $42,041 | $25,000 | $18,000 |
| 111E10100 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN "A" | 1 LS | $8,000 | $8,072 | $6,500 | $23,280 | $25,000 | $30,000 |
| 619E16020 FIELD OFFICE, TYPE C | 43 MNTH | $2,800 | $2,500 | $3,320 | $6,222 | $3,000 | $2,200 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $220,000 | $300,000 | $236,000 | $388,000 | $300,000 | $450,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E10000 EXCAVATION | 931,325 CY | $6.25 | $5.82M | 19% |
| 302E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 19,377 CY | $190 | $3.68M | 12% |
| 442E10300 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 11,730 CY | $235 | $2.76M | 9% |
| 304E20000 AGGREGATE BASE | 21,687 CY | $95 | $2.06M | 7% |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 9,607 CY | $200 | $1.92M | 6% |
| 624E10000 MOBILIZATION | 1 LS | $1,560,000 | $1.56M | 5% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 6,064 CY | $205 | $1.24M | 4% |
| 507E00400 STEEL PILES, MISC.: W36X262 | 2,323.4 FT | $380 | $883k | 3% |
| 832E30000 EROSION CONTROL | 800,000 EACH | $1 | $800k | 3% |
| 204E30011 GRANULAR MATERIAL, TYPE B, AS PER PLAN | 8,317 CY | $85 | $707k | 2% |