LAW-SR 522-00.00
LAW County · est $0.7M
Bid dateThursday, July 31—
LAW County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1Shelly Company | R2Strawser Construction INC | % of bid |
|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 47,059 GAL | $3.00 | $3.50 | 22% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 127,186 SY | $1.03 | $1.45 | 20% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $72,000 | $82,400 | 11% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,000 SY | $60.50 | $80.00 | 9% |
| 886E11000 FOG SEAL | 19,078 GAL | $3.10 | $4.00 | 9% |
| 644E30030 REMOVAL OF PAVEMENT MARKING | 24.81 MILE | $1,275 | $1,350 | 5% |
| 621E00100 RPM | 756 EACH | $36.50 | $40.00 | 4% |
| 617E10100 COMPACTED AGGREGATE | 162 CY | $160 | $170 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $23,000 | $97,285 | 4% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 33.08 MILE | $580 | $615 | 3% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 16.54 MILE | $865 | $915 | 2% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 16.54 MILE | $745 | $45.00 | 2% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 740 EACH | $15.25 | $30.00 | 2% |
| 642E00300 CENTER LINE, TYPE 1 | 8.27 MILE | $1,232 | $1,300 | 2% |
| 209E60500 LINEAR GRADING | 1.66 MILE | $3,400 | $3,600 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $6,500 | 1% |
| 614E12460 WORK ZONE MARKING SIGN | 31 EACH | $88.00 | $148 | 0% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,500 | $2,000 | 0% |
| 646E10010 EDGE LINE, 6" | 0.04 MILE | $38,910 | $38,910 | 0% |
| 646E10200 CENTER LINE | 0.02 MILE | $59,650 | $59,650 | 0% |
| Item | Quantity | R1Shelly Company | R2Strawser Construction INC |
|---|---|---|---|
| 642E00500 STOP LINE, TYPE 1 | 19 FT | $8.50 | $9.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 19 FT | $15.00 | $16.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 19 FT | $5.00 | $5.25 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 47,059 GAL | $3 | $141k | 21% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 127,186 SY | $1.03 | $131k | 20% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $72,000 | $72k | 11% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,000 SY | $60.5 | $61k | 9% |
| 886E11000 FOG SEAL | 19,078 GAL | $3.1 | $59k | 9% |
| 644E30030 REMOVAL OF PAVEMENT MARKING | 24.81 MILE | $1,275 | $32k | 5% |
| 621E00100 RPM | 756 EACH | $36.5 | $28k | 4% |
| 617E10100 COMPACTED AGGREGATE | 162 CY | $160 | $26k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $23,000 | $23k | 4% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 33.08 MILE | $580 | $19k | 3% |