| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Capitol Tunneling INC | R3Turn-key Tunneling INC | % of bid |
|---|---|---|---|---|---|
| 611E97400 CONDUIT, MISC.: 102" TUNNEL LINER PLATE STRUCTURE | 246 FT | $3,184 | $3,875 | $4,495 | 54% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $217,400 | $35,000 | $84,600 | 15% |
| 837E21000 BACKFILL FOR LINER PIPE | 246 FT | $461 | $475 | $300 | 8% |
| 611E96560 CONDUIT, WITH FIELD PAVING OF PIPE (102" TUNNEL LI | 246 FT | $251 | $250 | $655 | 4% |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $4,555 | $1,800 | $100 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $44,600 | $100,000 | $76,500 | 3% |
| 659E00300 TOPSOIL | 211 CY | $131 | $75.00 |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Capitol Tunneling INC | R3Turn-key Tunneling INC |
|---|---|---|---|---|
| 202E75000 FENCE REMOVED | 186 FT | $21.50 | $5.00 | $22.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $214 | $200 | $5.60 |
| 659E14000 REPAIR SEEDING AND MULCHING | 95 SY | $2.60 | $15.00 | $0.23 |
| 659E20000 COMMERCIAL FERTILIZER | 0.26 TON | $1,800 | $900 | $2,048 |
| 659E31000 LIME | 0.39 ACRE | $200 | $1,200 | $1,575 |
| 659E35000 WATER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $11.00 |
| 2% |
| 602E20000 CONCRETE MASONRY | 10.6 CY | $2,500 | $5,000 | $2,999 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,200 | $5,000 | $28,100 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,665 | $16,000 | $20,500 | 1% |
| 202E20010 HEADWALL REMOVED | 2 EACH | $7,140 | $3,300 | $2,210 | 1% |
| 203E20000 EMBANKMENT | 75 CY | $184 | $50.00 | $82.50 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $13,660 | $90,000 | $36,250 | 1% |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 53 CY | $240 | $285 | $243 | 1% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $979 | $600 | $54.50 | 1% |
| 614E12200 SPECIAL - WORK ZONE GUARDRAIL | 100 FT | $80.50 | $85.00 | $54.50 | 1% |
| 601E27000 DUMPED ROCK FILL, TYPE C | 27 CY | $219 | $160 | $216 | 0% |
| 203E10000 EXCAVATION | 50 CY | $102 | $25.00 | $55.00 | 0% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | 0% |
| 659E10000 SEEDING AND MULCHING | 1,905 SY | $2.60 | $5.00 | $5.60 | 0% |
| 10 MGAL |
| $1.00 |
| $100 |
| $1.00 |
| 304E20000 AGGREGATE BASE | 5 CY | $480 | $100 | $54.50 |
| 616E10000 WATER | 10 MGAL | $10.00 | $100 | $1.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,550 | $10,000 | $6,300 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E97400 CONDUIT, MISC.: 102" TUNNEL LINER PLATE STRUCTURE | 246 FT | $3,184 | $783k | 53% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $217,400 | $217k | 15% |
| 837E21000 BACKFILL FOR LINER PIPE | 246 FT | $461 | $113k | 8% |
| 611E96560 CONDUIT, WITH FIELD PAVING OF PIPE (102" TUNNEL LI | 246 FT | $251 | $62k | 4% |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $4,555 | $55k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $44,600 | $45k | 3% |
| 659E00300 TOPSOIL | 211 CY | $130.5 | $28k | 2% |
| 602E20000 CONCRETE MASONRY | 10.6 CY | $2,500 | $27k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,200 | $22k | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,665 | $16k | 1% |