HOL-/TUS-US 62/US 39-VAR
HOL County · est $5.4M
Bid dateThursday, October 9—
HOL County · est $5.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 27 more items below.
| Item | Quantity | R1Melway Paving CO INC | R2Karvo Companies INC | R3Shelly Company | % of bid |
|---|---|---|---|---|---|
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 8,886 CY | $205 | $250 | $260 | 37% |
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (6923 CY | $175 | $195 | $210 | 25% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (3 | 153,508 SY | $3.00 | $3.00 | $3.15 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $300,000 | $268,000 | $343,250 | 6% |
| 253E02000 PAVEMENT REPAIR | 575 CY | $380 | $335 | $325 | 4% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (1 | 70,138 SY | $3.00 | $2.00 | $2.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS |
| Item | Quantity | R1Melway Paving CO INC | R2Karvo Companies INC | R3Shelly Company |
|---|---|---|---|---|
| 202E23500 WEARING COURSE REMOVED | 2,313 SY | $5.40 | $14.00 | $8.00 |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 3 EACH | $110 | $1,500 | $1,900 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 575 FT | $16.00 | $15.00 | $10.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 4 EACH | $1,200 | $2,000 | $1,500 |
| 617E20001 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $100,000 |
| $400,000 |
| $200,000 |
| 2% |
| 874E21000 LONGITUDINAL JOINT PREPARATION | 7.48 MILE | $10,610 | $5,750 | $10,600 | 2% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 200 CY | $380 | $400 | $325 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 27,703 GAL | $2.50 | $2.50 | $3.00 | 1% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 853 CY | $70.00 | $72.00 | $100 | 1% |
| 646E10010 EDGE LINE, 6" | 19.04 MILE | $3,115 | $3,000 | $3,100 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 30.78 MILE | $1,205 | $1,200 | $1,025 | 1% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $650 | $725 | $550 | 1% |
| 621E00100 RPM | 876 EACH | $40.00 | $36.85 | $39.50 | 1% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 77 CF | $455 | $525 | $575 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 8,191 GAL | $4.10 | $5.00 | $5.00 | 1% |
| 646E10200 CENTER LINE | 10.26 MILE | $3,220 | $3,500 | $3,205 | 1% |
| 623E39600 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE | 35 EACH | $900 | $2,000 | $1,300 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 300 HOUR | $75.00 | $105 | $100 | 0% |
| 20,478 SY |
| $1.05 |
| $1.00 |
| $1.25 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 7.48 MILE | $1,400 | $929 | $930 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 752 EACH | $14.00 | $0.25 | $6.00 |
| 646E10300 CHANNELIZING LINE, 8" | 1,848 FT | $1.05 | $2.00 | $1.05 |
| 646E10400 STOP LINE | 383 FT | $12.05 | $12.50 | $12.00 |
| 646E10520 CROSSWALK LINE, 24" | 568 FT | $12.05 | $12.50 | $12.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 1,437 FT | $8.05 | $12.50 | $8.00 |
| 646E10800 ISLAND MARKING | 56 SF | $10.05 | $15.00 | $10.00 |
| 646E10900 HANDICAP SYMBOL MARKING | 1 EACH | $145 | $250 | $144 |
| 646E20100 SCHOOL SYMBOL MARKING, 72" | 1 EACH | $580 | $575 | $575 |
| 646E20110 SCHOOL SYMBOL MARKING, 96" | 2 EACH | $580 | $575 | $575 |
| 646E20200 PARKING LOT STALL MARKING | 65 FT | $4.80 | $3.00 | $4.75 |
| 646E20300 LANE ARROW | 26 EACH | $162 | $225 | $161 |
| 646E20370 TWO WAY LEFT TURN ARROW | 4 EACH | $223 | $325 | $222 |
| 646E20800 YIELD LINE | 48 FT | $12.05 | $12.00 | $12.00 |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 310 FT | $6.00 | $12.50 | $5.95 |
| 614E12460 WORK ZONE MARKING SIGN | 70 EACH | $85.00 | $80.00 | $85.00 |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 30.78 MILE | $380 | $400 | $650 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 1,848 FT | $2.00 | $0.50 | $2.25 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 383 FT | $3.00 | $3.00 | $9.35 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $20,000 | $34,416 | $25,000 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $2,500 | $3,000 | $3,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 8,886 CY | $205 | $1.82M | 36% |
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (6923 CY | $175 | $1.21M | 24% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (3 | 153,508 SY | $3 | $461k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $300,000 | $300k | 6% |
| 253E02000 PAVEMENT REPAIR | 575 CY | $380 | $219k | 4% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (1 | 70,138 SY | $3 | $210k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 2% |
| 874E21000 LONGITUDINAL JOINT PREPARATION | 7.48 MILE | $10,610 | $79k | 2% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 200 CY | $380 | $76k | 1% |
| 407E20000 NON-TRACKING TACK COAT | 27,703 GAL | $2.5 | $69k | 1% |