BEL-TR 428-00.30
BEL County · est $1.1M
Bid dateThursday, December 18—
BEL County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 49 more items below.
| Item | Quantity | R1Stanley Miller Construction Company | R2Alan Stone CO INC | R3Shelly & Sands INC | R4R C Construction Company And Son INC | % of bid |
|---|---|---|---|---|---|---|
| 511E32210 CLASS QC2 CONCRETE, SUPERSTRUCTURE, CONTINUOUS CON | 115 CY | $1,227 | $1,900 | $1,400 | $1,400 | 18% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 418 FT | $290 | $25.00 | $141 | $275 | 16% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $60,111 | $18,000 | $17,000 | $35,000 | 8% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 36,996 LB | $1.53 | $2.00 | $1.75 | $3.00 | 7% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 182 FT | $300 | $300 | $250 | $275 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $54,500 | $64,000 | $48,735 | $75,000 |
| Item | Quantity | R1Stanley Miller Construction Company | R2Alan Stone CO INC | R3Shelly & Sands INC | R4R C Construction Company And Son INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,000 | $5,200 | $12,000 | $15,000 |
| 202E38000 GUARDRAIL REMOVED | 30 FT | $11.00 | $35.00 | $9.00 | $10.00 |
| 203E10000 EXCAVATION | 216 CY | $39.50 | $45.00 | $30.00 | $25.00 |
| 204E10000 SUBGRADE COMPACTION | 838 SY | $1.00 | $6.50 | $6.00 | $2.00 |
| 204E13000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 62 CY | $653 | $860 | $1,575 | $1,200 | 5% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $31,900 | $72,000 | $100,000 | $25,000 | 4% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $28,944 | $37,000 | $36,000 | $50,000 | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 52 CY | $528 | $440 | $454 | $575 | 4% |
| 507E00361 STEEL PILES HP14X89, FURNISHED, AS PER PLAN | 290 FT | $70.00 | $80.00 | $63.00 | $120 | 3% |
| 304E20000 AGGREGATE BASE | 133 CY | $143 | $130 | $100 | $175 | 2% |
| 204E30041 GRANULAR MATERIAL, TYPE E, AS PER PLAN | 173 CY | $105 | $200 | $85.00 | $175 | 2% |
| 511E42510 CLASS QC1 CONCRETE, PIER CAP | 9 CY | $1,762 | $2,600 | $4,695 | $1,200 | 2% |
| 203E20000 EMBANKMENT | 211 CY | $72.00 | $15.00 | $25.00 | $25.00 | 2% |
| 503E21100 UNCLASSIFIED EXCAVATION | 125 CY | $118 | $50.00 | $220 | $100 | 2% |
| 606E35003 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, AS PER PLAN | 4 EACH | $3,278 | $3,300 | $2,750 | $3,000 | 2% |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 79 CY | $156 | $210 | $68.00 | $175 | 2% |
| 507E71200 SPECIAL - PILE ENCASEMENT | 116 FT | $94.00 | $150 | $175 | $275 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,670 | $15,000 | $2,500 | $50,000 | 1% |
| 45 CY |
| $29.00 |
| $90.00 |
| $32.00 |
| $50.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $125 | $290 | $275 | $200 |
| 606E15050 GUARDRAIL, TYPE MGS | 62.5 FT | $43.34 | $30.00 | $25.00 | $60.00 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 12.5 FT | $72.24 | $35.00 | $27.50 | $65.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 2 EACH | $2,195 | $2,100 | $1,750 | $2,000 |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 1 EACH | $1,670 | $1,500 | $1,250 | $1,500 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 1 EACH | $555 | $1,300 | $1,250 | $1,500 |
| 690E98400 SPECIAL - WORK INVOLVING ASBESTOS CONTAINING MATER | 1 LS | $500 | $240 | $240 | $50,000 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 4 SY | $81.00 | $740 | $185 | $400 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $180 | $150 | $10.00 |
| 659E00300 TOPSOIL | 107 CY | $69.00 | $20.00 | $49.00 | $10.00 |
| 659E10000 SEEDING AND MULCHING | 965 SY | $6.30 | $2.00 | $3.15 | $10.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 48 SY | $1.00 | $15.00 | $3.15 | $0.20 |
| 659E15000 INTER-SEEDING | 48 SY | $1.00 | $35.00 | $3.15 | $0.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.14 TON | $939 | $670 | $1,250 | $2,500 |
| 659E31000 LIME | 0.2 ACRE | $178 | $960 | $150 | $2,000 |
| 659E35000 WATER | 5 MGAL | $5.00 | $120 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 21 SY | $9.50 | $35.00 | $15.00 | $25.00 |
| 605E05200 4" UNCLASSIFIED PIPE UNDERDRAINS | 25 FT | $17.00 | $350 | $30.00 | $100 |
| 605E31100 AGGREGATE DRAINS | 50 FT | $34.00 | $35.00 | $20.00 | $50.00 |
| 611E00406 4" CONDUIT, TYPE F | 20 FT | $23.00 | $110 | $8.00 | $20.00 |
| 611E03400 10" CONDUIT, TYPE D | 28 FT | $67.00 | $110 | $52.00 | $35.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $328 | $730 | $500 | $350 |
| 408E10000 PRIME COAT | 32 GAL | $78.00 | $4.00 | $4.25 | $75.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 10 EACH | $14.50 | $15.00 | $12.00 | $25.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 128 FT | $24.50 | $20.00 | $17.50 | $25.00 |
| 630E80100 SIGN, FLAT SHEET | 45 SF | $35.50 | $30.00 | $25.00 | $75.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 5 EACH | $167 | $30.00 | $25.00 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $167 | $30.00 | $25.00 | $50.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 75 CY | $45.00 | $160 | $70.00 | $65.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $3,611 | $6,000 | $3,250 | $20,000 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 15 CY | $100 | $330 | $315 | $65.00 |
| 616E10000 WATER | 10 MGAL | $1.00 | $0.10 | $106 | $1.00 |
| 507E00201 STEEL PILES HP12X53, FURNISHED, AS PER PLAN | 240 FT | $41.60 | $55.00 | $38.00 | $95.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 102 SY | $62.00 | $30.00 | $48.00 | $65.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 35 SF | $2.00 | $2.00 | $4.00 | $45.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 31 SF | $3.00 | $2.50 | $4.50 | $55.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 58 FT | $37.00 | $10.00 | $52.00 | $65.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 53 CY | $160 | $130 | $157 | $175 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 178 FT | $16.00 | $40.00 | $15.50 | $75.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 83 FT | $16.00 | $20.00 | $5.00 | $25.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 48 FT | $35.00 | $25.00 | $5.00 | $25.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,225 | $8,000 | $5,185 | $45,000 |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $1,000 | $2,000 | $4,900 | $200 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E32210 CLASS QC2 CONCRETE, SUPERSTRUCTURE, CONTINUOUS CON | 115 CY | $1,227 | $141k | 16% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 418 FT | $290 | $121k | 14% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $60,111 | $60k | 7% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 36,996 LB | $1.53 | $57k | 6% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 182 FT | $300 | $55k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $54,500 | $55k | 6% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 62 CY | $653 | $40k | 5% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $31,900 | $32k | 4% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $28,944 | $29k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 52 CY | $528 | $27k | 3% |