NOB-CEVSD Campus Connectivity
NOB County · est $2.3M
Bid dateThursday, December 18—
NOB County · est $2.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 74 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Stanley Miller Construction Company | R3Ruhlin Company | R4Alan Stone CO INC | R5Cast & Baker Corporation | % of bid |
|---|---|---|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 35,164 SF | $6.25 | $8.26 | $9.00 | $9.50 | $10.50 | 14% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 2,064 SY | $90.00 | $108 | $63.00 | $85.00 | $93.00 | 12% |
| 625E10481 LIGHT POLE, AESTHETIC, AS PER PLAN (16' TALL, TAPE | 33 EACH | $4,175 | $4,638 | $3,810 | $4,000 | $3,570 | 9% |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 1,578 SY | $80.00 | $89.00 | $78.00 | $90.00 | $111 | 8% |
| 611E05900 15" CONDUIT, TYPE B | 1,142 FT | $100 | $52.00 | $150 | $140 | $155 | 7% |
| 614E11000 MAINTAINING TRAFFIC |
| Item | Quantity | R1Shelly & Sands INC | R2Stanley Miller Construction Company | R3Ruhlin Company | R4Alan Stone CO INC | R5Cast & Baker Corporation |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,761 | $9,661 | $5,000 | $9,700 | $30,000 |
| 202E30200 STEPS REMOVED | 4 FT | $147 | $100 | $150 | $370 | $130 |
| 202E32000 CURB REMOVED | 1,168 FT | $6.50 | $4.00 | $7.00 | $15.00 | $8.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 466 FT | $25.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $100,000 |
| $76,488 |
| $27,275 |
| $32,000 |
| $141,700 |
| 6% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 3,850 FT | $24.70 | $33.00 | $24.50 | $30.00 | $47.00 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $84,000 | $87,946 | $92,250 | $67,000 | $100,000 | 5% |
| 832E30000 EROSION CONTROL | 60,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 33 EACH | $1,700 | $1,833 | $1,445 | $1,800 | $1,630 | 4% |
| 202E23000 PAVEMENT REMOVED | 2,144 SY | $22.50 | $19.00 | $39.50 | $20.00 | $24.00 | 3% |
| 611E04400 12" CONDUIT, TYPE B | 552 FT | $85.00 | $35.00 | $110 | $110 | $127 | 3% |
| 611E98180 CATCH BASIN, NO. 3A | 11 EACH | $4,200 | $2,593 | $5,475 | $3,600 | $3,650 | 3% |
| 625E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, SOLID-STATE (L | 33 EACH | $1,250 | $1,277 | $1,150 | $2,300 | $2,000 | 3% |
| 630E97700 SIGNING, MISC.: SOLAR-POWERED RECTANGULAR RAPID FL | 4 EACH | $9,670 | $9,666 | $6,750 | $10,000 | $9,240 | 2% |
| 202E30000 WALK REMOVED | 20,538 SF | $1.80 | $1.00 | $3.00 | $1.50 | $1.20 | 2% |
| 625E29001 TRENCH, AS PER PLAN | 2,901 FT | $12.00 | $13.20 | $9.00 | $9.50 | $8.40 | 2% |
| 659E00300 TOPSOIL | 449 CY | $75.00 | $50.00 | $76.00 | $40.00 | $80.00 | 2% |
| 625E23302 NO. 6 AWG 2400 VOLT DISTRIBUTION CABLE | 10,299 FT | $3.00 | $3.00 | $2.90 | $3.50 | $3.20 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $30,000 | $63,000 | $22,000 | $59,000 | $40,000 | 2% |
| $10.00 |
| $19.00 |
| $15.00 |
| $36.00 |
| 202E38000 GUARDRAIL REMOVED | 582 FT | $3.50 | $5.50 | $3.50 | $4.00 | $5.00 |
| 202E53100 MAILBOX REMOVED | 13 EACH | $257 | $50.00 | $100 | $40.00 | $80.00 |
| 202E58100 CATCH BASIN REMOVED | 10 EACH | $448 | $400 | $534 | $25.00 | $600 |
| 202E98100 REMOVAL MISC.: (RAILROAD TRACKS) | 1 EACH | $2,418 | $1,000 | $2,520 | $960 | $1,000 |
| 202E98200 REMOVAL MISC.:HANDRAIL | 114 FT | $5.50 | $8.30 | $6.00 | $35.00 | $9.00 |
| 203E10000 EXCAVATION | 202 CY | $37.50 | $110 | $55.00 | $30.00 | $150 |
| 203E20000 EMBANKMENT | 174 CY | $32.50 | $90.00 | $72.00 | $8.50 | $50.00 |
| 204E10000 SUBGRADE COMPACTION | 1,558 SY | $7.50 | $1.00 | $3.75 | $10.00 | $9.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $276 | $180 | $333 | $280 | $260 |
| 607E35000 FENCE REMOVED AND REBUILT | 120 FT | $91.50 | $87.20 | $85.00 | $100 | $90.00 |
| 607E98000 FENCE, MISC.:WOOD FENCE | 65 FT | $6.50 | $103 | $60.00 | $120 | $63.00 |
| 608E40000 CONCRETE STEPS, TYPE A | 4 FT | $456 | $200 | $470 | $560 | $320 |
| 608E52000 CURB RAMP | 557 SF | $48.00 | $34.00 | $21.00 | $25.00 | $34.00 |
| 608E53020 DETECTABLE WARNING | 170 SF | $31.50 | $50.00 | $30.00 | $25.00 | $36.00 |
| 690E98000 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 13 EACH | $269 | $430 | $250 | $300 | $250 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 1 CY | $1,085 | $400 | $1,500 | $2,300 | $500 |
| 659E10000 SEEDING AND MULCHING | 4,041 SY | $1.50 | $3.20 | $1.20 | $2.00 | $1.30 |
| 659E14000 REPAIR SEEDING AND MULCHING | 203 SY | $1.00 | $1.00 | $1.20 | $6.50 | $1.30 |
| 659E15000 INTER-SEEDING | 203 SY | $1.00 | $1.00 | $1.20 | $2.00 | $1.30 |
| 659E20000 COMMERCIAL FERTILIZER | 0.57 TON | $850 | $800 | $1,250 | $660 | $1,300 |
| 659E31000 LIME | 0.84 ACRE | $173 | $150 | $1,250 | $950 | $1,300 |
| 659E35000 WATER | 37 MGAL | $1.00 | $1.00 | $1.00 | $120 | $1.00 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $13,352 | $12,000 | $11,613 | $14,000 | $13,000 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $3,116 | $3,333 | $2,500 | $3,400 | $3,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $13,796 | $4,070 | $7,350 | $18,000 | $11,000 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 0.67 CY | $4,021 | $1,899 | $10,000 | $3,100 | $3,300 |
| 602E20000 CONCRETE MASONRY | 0.1 CY | $9,234 | $9,000 | $14,000 | $9,400 | $14,000 |
| 611E00900 6" CONDUIT, TYPE B | 106 FT | $22.50 | $39.00 | $94.50 | $25.00 | $90.00 |
| 611E10400 24" CONDUIT, TYPE B | 51 FT | $150 | $89.00 | $197 | $140 | $170 |
| 611E98150 CATCH BASIN, NO. 3 | 3 EACH | $4,993 | $3,886 | $6,160 | $4,600 | $4,750 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $4,270 | $3,000 | $4,285 | $3,800 | $2,900 |
| 611E98504 CATCH BASIN, NO. 2-2C | 1 EACH | $6,317 | $2,500 | $4,720 | $2,600 | $2,900 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 3 EACH | $1,123 | $1,100 | $1,350 | $720 | $600 |
| 611E99574 MANHOLE, NO. 3 | 4 EACH | $5,741 | $4,800 | $7,915 | $6,200 | $3,800 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $923 | $1,800 | $1,450 | $670 | $600 |
| 895E10010 MANUFACTURED WATER QUALITY STRUCTURE, TYPE 1 | 1 EACH | $19,405 | $27,448 | $65,350 | $14,000 | $32,000 |
| 304E20000 AGGREGATE BASE | 144 CY | $186 | $135 | $244 | $160 | $236 |
| 407E10000 TACK COAT | 54.04 GAL | $3.50 | $5.00 | $3.00 | $5.00 | $4.20 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 37 CY | $695 | $955 | $190 | $720 | $950 |
| 609E18000 COMBINATION CURB AND GUTTER, TYPE 3 | 150 FT | $81.50 | $58.00 | $47.50 | $35.00 | $58.00 |
| 609E33200 CURB, TYPE 10-B | 119 FT | $41.50 | $40.00 | $78.50 | $25.00 | $55.00 |
| 625E00450 CONNECTION, FUSED PULL APART | 66 EACH | $120 | $122 | $192 | $160 | $142 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 6 EACH | $160 | $166 | $182 | $150 | $131 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 1,716 FT | $2.50 | $2.75 | $2.00 | $3.00 | $2.60 |
| 625E25400 CONDUIT, 2", 725.04 | 84 FT | $29.00 | $32.00 | $26.00 | $30.00 | $25.20 |
| 625E25402 CONDUIT, 2", 725.05 | 2,791 FT | $7.25 | $8.00 | $5.50 | $9.50 | $8.40 |
| 625E25502 CONDUIT, 3", 725.05 | 26 FT | $24.00 | $26.50 | $10.60 | $15.00 | $13.00 |
| 625E25909 CONDUIT, JACKED OR DRILLED, 725.052, AS PER PLAN ( | 133 FT | $93.00 | $103 | $45.00 | $110 | $100 |
| 625E30510 PULL BOX, 725.06, SIZE 4 | 8 EACH | $700 | $750 | $1,090 | $1,300 | $1,155 |
| 625E32000 GROUND ROD | 35 EACH | $200 | $205 | $250 | $360 | $315 |
| 625E34001 POWER SERVICE, AS PER PLAN | 3 EACH | $4,000 | $4,111 | $9,950 | $8,500 | $7,560 |
| 625E36011 UNDERGROUND WARNING/MARKING TAPE, AS PER PLAN | 2,901 FT | $2.00 | $1.50 | $2.00 | $2.00 | $1.80 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 150 FT | $26.50 | $22.00 | $23.26 | $25.00 | $26.00 |
| 630E04101 GROUND MOUNTED SUPPORT, NO. 4 POST, AS PER PLAN | 41 FT | $32.50 | $27.00 | $32.51 | $35.00 | $32.00 |
| 630E08600 SIGN POST REFLECTOR | 11 EACH | $59.00 | $55.00 | $82.76 | $65.00 | $58.00 |
| 630E80100 SIGN, FLAT SHEET | 83 SF | $34.50 | $33.00 | $27.13 | $40.00 | $34.00 |
| 630E85000 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE | 18 EACH | $53.50 | $33.00 | $16.56 | $150 | $53.00 |
| 630E85600 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND REERECTIO | 2 EACH | $80.50 | $272 | $82.77 | $320 | $79.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 14 EACH | $27.00 | $27.00 | $22.08 | $35.00 | $26.00 |
| 644E00300 CENTER LINE | 0.37 MILE | $12,856 | $13,294 | $8,425 | $14,000 | $12,600 |
| 644E00500 STOP LINE | 67 FT | $9.50 | $10.00 | $12.65 | $10.00 | $9.50 |
| 644E00620 CROSSWALK LINE, 12" | 552 FT | $5.00 | $4.83 | $6.90 | $5.00 | $4.60 |
| 644E00630 CROSSWALK LINE, 24" | 169 FT | $10.00 | $10.00 | $8.85 | $10.00 | $9.50 |
| 644E20800 YIELD LINE | 28 FT | $15.00 | $15.50 | $10.00 | $15.00 | $15.00 |
| 631E93250 SCHOOL SPEED LIMIT SIGN ASSEMBLY, MISC.:REMOVAL | 2 EACH | $806 | $833 | $420 | $890 | $800 |
| 631E93241 SCHOOL SPEED LIMIT SIGN ASSEMBLY, SOLAR-POWERED, A | 2 EACH | $11,175 | $4,722 | $5,935 | $12,000 | $11,000 |
| 632E64020 PEDESTAL FOUNDATION | 4 EACH | $2,257 | $888 | $777 | $2,500 | $2,200 |
| 632E64950 TEST HOLE PERFORMED | 4 EACH | $1,182 | $205 | $315 | $1,300 | $1,100 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 222 CY | $93.00 | $150 | $85.00 | $130 | $120 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $13,893 | $23,500 | $10,050 | $20,000 | $15,600 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 35,164 SF | $6.25 | $220k | 11% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 2,064 SY | $90 | $186k | 9% |
| 625E10481 LIGHT POLE, AESTHETIC, AS PER PLAN (16' TALL, TAPE | 33 EACH | $4,175 | $138k | 7% |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 1,578 SY | $80 | $126k | 6% |
| 611E05900 15" CONDUIT, TYPE B | 1,142 FT | $100 | $114k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $100,000 | $100k | 5% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 3,850 FT | $24.7 | $95k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $84,000 | $84k | 4% |
| 832E30000 EROSION CONTROL | 60,000 EACH | $1 | $60k | 3% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 33 EACH | $1,700 | $56k | 3% |