TRU-US 62-04.56
TRU County · est $4.4M
Bid dateThursday, December 18—
TRU County · est $4.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 102 more items below.
| Item | Quantity | R1Kirila Contractors INC | R2Shelly & Sands INC | R3Shelly Company | R4Karvo Companies INC | % of bid |
|---|---|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 8,542 CY | $236 | $220 | $245 | $270 | 58% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1.5") | 171,822 SY | $1.50 | $1.20 | $1.80 | $1.80 | 7% |
| 255E12000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 900 SY | $263 | $275 | $270 | $241 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $136,186 | $278,796 | $380,000 | $240,000 | 4% |
| 441E00100 ANTI-SEGREGATION EQUIPMENT | 5,845 CY | $15.35 | $10.00 | $6.00 | $7.85 | 3% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) (LONGITUDINAL) | 1,800 SY | $48.25 | $50.00 | $50.00 | $37.00 |
| Item | Quantity | R1Kirila Contractors INC | R2Shelly & Sands INC | R3Shelly Company | R4Karvo Companies INC |
|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 2 EACH | $250 | $500 | $700 | $500 |
| 202E23000 PAVEMENT REMOVED | 1,040 SY | $15.00 | $7.50 | $26.50 | $25.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 197 FT | $15.00 | $3.00 | $28.00 | $27.00 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $300 | $250 | $1,500 | $700 |
| 202E60010 MONUMENT ASSEMBLY REMOVED | 1 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 2% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449)(T=8") | 404 CY | $205 | $200 | $220 | $230 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN (T=1" AVG.) | 547 CY | $139 | $90.00 | $120 | $131 | 2% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 8 EACH | $8,950 | $8,950 | $8,950 | $8,600 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 18,615 GAL | $3.50 | $3.05 | $2.50 | $2.35 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $53,836 | $100,000 | $100,000 | $300,000 | 2% |
| 807E12010 WET REFLECTIVE EPOXY PAVEMENT MARKING, EDGE LINE, | 13.2 MILE | $3,250 | $3,250 | $3,250 | $3,250 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $3,500 | $3,500 | $3,500 | $2,200 | 1% |
| 621E00101 RPM, AS PER PLAN (WHITE/RED) | 884 EACH | $38.50 | $38.50 | $38.50 | $39.00 | 1% |
| 442E22400 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 126 CY | $270 | $300 | $325 | $340 | 1% |
| 255E19100 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 106 SY | $317 | $300 | $350 | $350 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,644 FT | $20.00 | $29.50 | $20.00 | $37.00 | 1% |
| 209E60200 LINEAR GRADING | 469 STA | $70.00 | $65.00 | $70.00 | $30.00 | 1% |
| 611E04400 12" CONDUIT, TYPE B | 432 FT | $71.00 | $65.00 | $145 | $115 | 1% |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE | 643 SY | $46.00 | $45.75 | $45.75 | $45.75 | 1% |
| $350 |
| $500 |
| $1,000 |
| $95.00 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 421 FT | $25.00 | $5.00 | $50.00 | $30.00 |
| 202E98100 REMOVAL MISC.:BARRIER REFLECTOR | 24 EACH | $5.00 | $5.00 | $5.00 | $5.00 |
| 203E10000 EXCAVATION | 740 CY | $18.00 | $26.00 | $48.00 | $41.00 |
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 117 CY | $25.00 | $26.00 | $28.00 | $85.00 |
| 203E20000 EMBANKMENT | 126 CY | $20.00 | $65.00 | $75.00 | $35.00 |
| 204E10000 SUBGRADE COMPACTION | 1,973 SY | $1.50 | $3.00 | $1.25 | $2.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $200 | $100 | $135 | $350 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 1 EACH | $1,500 | $750 | $3,250 | $1,200 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $750 | $3,000 | $10,000 | $1,200 |
| 831E00101 LONGITUDINAL CHANNELIZING DEVICE, AS PER PLAN, NEW | 38 FT | $150 | $150 | $150 | $150 |
| 831E00101 LONGITUDINAL CHANNELIZING DEVICE, AS PER PLAN, REU | 38 FT | $42.50 | $42.50 | $42.50 | $42.50 |
| 831E00500 REMOVAL OF LONGITUDINAL CHANNELIZING DEVICE | 38 FT | $15.00 | $15.00 | $15.00 | $15.00 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 12 SY | $200 | $200 | $220 | $375 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 2 CY | $250 | $125 | $1,200 | $870 |
| 659E00300 TOPSOIL | 177 CY | $60.00 | $75.00 | $72.00 | $65.00 |
| 659E10000 SEEDING AND MULCHING | 1,591 SY | $4.00 | $5.00 | $1.30 | $1.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.22 TON | $885 | $910 | $1,500 | $800 |
| 659E31000 LIME | 0.33 ACRE | $161 | $607 | $1.00 | $180 |
| 659E35000 WATER | 9 MGAL | $1.00 | $2.00 | $60.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 338 SY | $1.50 | $3.00 | $4.00 | $1.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $2,500 | $2,500 | $2,500 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,420 | $12,840 | $5,350 | $9,630 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $1,075 | $1,140 | $1,100 | $1,074 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1.14 CY | $4,450 | $350 | $5,250 | $4,950 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 20 FT | $25.00 | $20.00 | $28.00 | $35.00 |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 1,174 FT | $15.00 | $32.00 | $26.50 | $24.50 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 68 FT | $28.00 | $30.00 | $40.00 | $39.00 |
| 611E00511 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS, AS PER | 30 FT | $32.00 | $30.00 | $90.00 | $90.00 |
| 611E01501 6" CONDUIT, TYPE F, AS PER PLAN, 704.42 | 90 FT | $32.00 | $32.00 | $30.00 | $31.00 |
| 611E05900 15" CONDUIT, TYPE B | 220 FT | $110 | $75.00 | $155 | $120 |
| 611E05900 15" CONDUIT, TYPE B, 706.02 | 11 FT | $174 | $175 | $300 | $268 |
| 611E07400 18" CONDUIT, TYPE B | 71 FT | $98.00 | $100 | $160 | $130 |
| 611E98180 CATCH BASIN, NO. 3A | 3 EACH | $3,650 | $5,200 | $4,300 | $5,200 |
| 611E98300 CATCH BASIN, NO. 5 | 3 EACH | $4,375 | $4,900 | $5,250 | $4,000 |
| 611E98370 CATCH BASIN, NO. 6 | 1 EACH | $4,525 | $4,500 | $4,800 | $3,600 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $2,075 | $3,500 | $3,800 | $3,200 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $1,000 | $1,500 | $600 | $160 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 1,459 FT | $2.75 | $4.00 | $2.50 | $2.50 |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (T | 31,356 SY | $0.75 | $1.20 | $1.85 | $1.65 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 4,291 FT | $3.00 | $3.00 | $2.50 | $2.50 |
| 304E20000 AGGREGATE BASE | 334 CY | $72.00 | $65.00 | $100 | $93.00 |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 117 CY | $85.00 | $75.00 | $55.00 | $65.00 |
| 408E10001 PRIME COAT, AS PER PLAN @ 0.40 GAL/SY | 7,867 GAL | $3.25 | $3.50 | $5.00 | $4.70 |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 115 SY | $85.00 | $83.00 | $135 | $130 |
| 609E26000 CURB, TYPE 6 | 528 FT | $40.00 | $28.00 | $36.00 | $45.00 |
| 618E40600 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 14 MILE | $1,200 | $975 | $975 | $975 |
| 621E00100 RPM | 160 EACH | $42.60 | $42.60 | $42.60 | $39.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 519 EACH | $5.00 | $5.00 | $7.00 | $5.50 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (ONE WAY) | 40 EACH | $17.25 | $17.25 | $17.25 | $17.25 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (ONE WAY) | 90 EACH | $30.00 | $30.00 | $30.00 | $30.00 |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 132 FT | $16.50 | $16.50 | $16.50 | $16.50 |
| 630E08600 SIGN POST REFLECTOR (RED) | 1 EACH | $45.00 | $45.00 | $45.00 | $45.00 |
| 630E08600 SIGN POST REFLECTOR (WHITE) | 6 EACH | $45.00 | $45.00 | $45.00 | $45.00 |
| 630E08600 SIGN POST REFLECTOR (YELLOW) | 2 EACH | $45.00 | $45.00 | $45.00 | $45.00 |
| 630E80100 SIGN, FLAT SHEET | 35 SF | $20.00 | $20.00 | $20.00 | $20.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 3 EACH | $25.00 | $25.00 | $25.00 | $25.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 4 EACH | $125 | $125 | $125 | $125 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $15.00 | $15.00 | $15.00 | $15.00 |
| 646E10010 EDGE LINE, 6" | 4.52 MILE | $2,900 | $2,900 | $2,900 | $2,900 |
| 646E10110 LANE LINE, 6" | 2.34 MILE | $1,500 | $1,500 | $1,500 | $1,500 |
| 646E10200 CENTER LINE | 0.22 MILE | $3,750 | $3,750 | $3,750 | $3,750 |
| 646E10310 CHANNELIZING LINE, 12" | 4,598 FT | $1.85 | $1.85 | $1.85 | $1.85 |
| 646E10400 STOP LINE | 509 FT | $10.00 | $10.00 | $10.00 | $10.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 1,055 FT | $10.00 | $10.00 | $10.00 | $10.00 |
| 646E10620 CHEVRON MARKING | 534 FT | $10.00 | $10.00 | $10.00 | $10.00 |
| 646E10800 ISLAND MARKING | 523 SF | $7.50 | $7.50 | $7.50 | $7.50 |
| 646E20300 LANE ARROW | 54 EACH | $135 | $135 | $135 | $135 |
| 646E20504 DOTTED LINE, 6" | 1,390 FT | $1.50 | $1.50 | $1.50 | $1.50 |
| 807E12110 WET REFLECTIVE EPOXY PAVEMENT MARKING, LANE LINE, | 6.6 MILE | $1,625 | $1,625 | $1,625 | $1,625 |
| 807E12200 WET REFLECTIVE EPOXY PAVEMENT MARKING, CENTER LINE | 0.29 MILE | $4,000 | $4,000 | $4,000 | $4,000 |
| 807E12310 WET REFLECTIVE EPOXY PAVEMENT MARKING, CHANNELIZIN | 4,150 FT | $2.25 | $2.25 | $2.25 | $2.25 |
| 807E12410 WET REFLECTIVE EPOXY PAVEMENT MARKING, DOTTED LINE | 3,030 FT | $1.25 | $1.25 | $1.25 | $1.25 |
| 850E10010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1,100 | $1,100 | $1,100 | $1,100 |
| 850E10110 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1.00 | $1.00 | $1.00 | $1.00 |
| 850E10130 GROOVING FOR 12" RECESSED PAVEMENT MARKING | — | $2.00 | $2.00 | $2.00 | $2.00 |
| 850E20010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $2,500 | $2,500 | $2,500 | $2,500 |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 2 EACH | $9,250 | $9,250 | $9,250 | $9,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $75.00 | $95.00 | $120 | $110 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,320 | $2,320 | $2,750 | $1,739 |
| 614E12420 DETOUR SIGNING | 1 LS | $3,250 | $3,250 | $3,250 | $3,250 |
| 614E12460 WORK ZONE MARKING SIGN | 12 EACH | $85.00 | $85.00 | $85.00 | $85.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 35 EACH | $22.50 | $22.50 | $22.50 | $22.50 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 16 SNMT | $900 | $850 | $850 | $850 |
| 614E20010 WORK ZONE LANE LINE, CLASS I, 6" | 8.94 MILE | $750 | $750 | $500 | $750 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 8.94 MILE | $750 | $750 | $500 | $750 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.51 MILE | $1,100 | $1,100 | $2,000 | $1,100 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.51 MILE | $1,100 | $1,100 | $2,000 | $1,100 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 1.28 MILE | $2,250 | $2,250 | $1,000 | $2,250 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 17.72 MILE | $500 | $500 | $650 | $500 |
| 614E23010 WORK ZONE CHANNELIZING LINE, CLASS I, 12" | 9,795 FT | $1.25 | $1.25 | $0.75 | $1.25 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 8,748 FT | $1.25 | $1.25 | $0.75 | $1.25 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 2,407 FT | $1.00 | $1.00 | $0.75 | $1.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 509 FT | $3.50 | $3.50 | $4.00 | $3.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 509 FT | $3.50 | $3.50 | $3.50 | $3.50 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $17,578 | $15,000 | $20,000 | $65,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $13,670 | $33,000 | $20,000 | $2,300 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 8,542 CY | $236 | $2.02M | 49% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1.5") | 171,822 SY | $1.5 | $258k | 6% |
| 255E12000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 900 SY | $263 | $237k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $136,186 | $136k | 3% |
| 441E00100 ANTI-SEGREGATION EQUIPMENT | 5,845 CY | $15.35 | $90k | 2% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) (LONGITUDINAL) | 1,800 SY | $48.25 | $87k | 2% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449)(T=8") | 404 CY | $205 | $83k | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN (T=1" AVG.) | 547 CY | $139 | $76k | 2% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 8 EACH | $8,950 | $72k | 2% |
| 407E20000 NON-TRACKING TACK COAT | 18,615 GAL | $3.5 | $65k | 2% |