ALL-SR 117-03.47/04.64
ALL County · est $1.1M
Bid dateThursday, February 13—
ALL County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 70 more items below.
| Item | Quantity | R1Advanced Excavating & Demolition | R2LLC Sand Ridge Excavating | R3Fenson Contracting LLC | R4Crawford Construction Company INC | % of bid |
|---|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 376 CY | $275 | $292 | $267 | $300 | 17% |
| 611E94940 9' X 6' CONDUIT, TYPE A, 706.05 | 60 FT | $1,250 | $1,021 | $1,100 | $1,800 | 12% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 147 CY | $350 | $408 | $373 | $415 | 8% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 259 CY | $176 | $200 | $175 | $93.00 | 7% |
| 602E20000 CONCRETE MASONRY | 35.7 CY | $1,100 | $380 | $1,200 | $1,400 | 6% |
| 611E25000 66" CONDUIT, TYPE A, 706.02, 707.35, 707.85 OR 72" | 84 FT | $450 | $500 | $515 |
| Item | Quantity | R1Advanced Excavating & Demolition | R2LLC Sand Ridge Excavating | R3Fenson Contracting LLC | R4Crawford Construction Company INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $4,500 | $16,000 | $10,000 | $6,700 |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 83 FT | $90.00 | $100 | $60.00 | $63.00 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $550 | $400 | $645 | $925 |
| 202E98000 REMOVAL MISC.: LANDSCAPE BLOCKS | 1 LS | $500 | $400 | $300 | $860 |
| 202E98100 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $750 |
| 6% |
| 659E00300 TOPSOIL | 573 CY | $45.00 | $15.00 | $32.00 | $35.00 | 4% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 39 CY | $600 | $350 | $500 | $811 | 4% |
| 304E20000 AGGREGATE BASE | 368 CY | $63.00 | $56.31 | $58.00 | $120 | 4% |
| 203E10000 EXCAVATION | 905 CY | $25.00 | $8.00 | $52.00 | $35.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $17,325 | $20,000 | $67,312 | 3% |
| 253E02000 PAVEMENT REPAIR | 20 CY | $900 | $115 | $350 | $240 | 3% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 16 CY | $1,100 | $370 | $2,000 | $1,600 | 3% |
| 202E23000 PAVEMENT REMOVED | 1,382 SY | $12.00 | $30.00 | $10.75 | $15.00 | 3% |
| 611E02600 8" CONDUIT, TYPE F | 272 FT | $60.00 | $14.00 | $31.00 | $43.00 | 3% |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 1,308 FT | $12.00 | $15.00 | $24.00 | $12.00 | 3% |
| 832E30000 EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $10,000 | $12,000 | $12,330 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $35,000 | $22,000 | $14,200 | 2% |
| 611E04600 12" CONDUIT, TYPE C | 194 FT | $75.00 | $22.00 | $38.00 | $70.00 | 2% |
| 1 EACH |
| $300 |
| $700 |
| $300 |
| $370 |
| 202E98100 REMOVAL MISC.: WELCOME TO SPENCERVILLE MONUMENT | 1 EACH | $300 | $1,000 | $1,000 | $1,000 |
| 203E20000 EMBANKMENT | 607 CY | $20.00 | $15.00 | $10.00 | $30.00 |
| 204E10000 SUBGRADE COMPACTION | 1,794 SY | $2.25 | $2.00 | $3.00 | $2.50 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 1 EACH | $1,800 | $2,420 | $1,850 | $2,300 |
| 623E40000 MONUMENT ASSEMBLY REMOVED AND RESET | 1 EACH | $1,500 | $2,000 | $2,100 | $3,200 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 12 EACH | $350 | $3,850 | $237 | $350 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $2,750 | $1,000 | $2,750 | $1,500 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $2,750 | $1,000 | $2,750 | $1,500 |
| 690E50000 SPECIAL - MAILBOX SUPPORT | 2 EACH | $750 | $454 | $200 | $800 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 2 EACH | $800 | $675 | $325 | $480 |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 91 CY | $90.00 | $98.10 | $98.00 | $132 |
| 601E32111 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 28 CY | $87.00 | $98.10 | $105 | $147 |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 19 CY | $93.00 | $74.50 | $95.00 | $190 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $60.00 | $50.00 | $60.00 | $145 |
| 659E10000 SEEDING AND MULCHING | 5,158 SY | $1.60 | $5.00 | $3.50 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.7 TON | $850 | $532 | $893 | $620 |
| 659E31000 LIME | 0.12 ACRE | $35.00 | $80.00 | $36.00 | $93.00 |
| 659E35000 WATER | 28 MGAL | $1.00 | $7.00 | $1.00 | $0.30 |
| 670E00500 SLOPE EROSION PROTECTION | 1,142 SY | $2.30 | $3.00 | $2.25 | $3.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,425 | $863 | $2,600 | $2,900 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,120 | $6,383 | $3,000 | $2,400 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $9,650 | $13,024 | $9,650 | $3,000 |
| 605E31100 AGGREGATE DRAINS | 127 FT | $25.00 | $8.00 | $17.00 | $26.00 |
| 611E01100 6" CONDUIT, TYPE C | 51 FT | $30.00 | $16.90 | $31.00 | $35.00 |
| 611E01500 6" CONDUIT, TYPE F | 10 FT | $50.00 | $12.75 | $32.00 | $35.00 |
| 611E02500 8" CONDUIT, TYPE E | 10 FT | $60.00 | $15.00 | $39.00 | $43.00 |
| 611E03300 10" CONDUIT, TYPE C | 20 FT | $50.00 | $19.00 | $35.00 | $58.00 |
| 611E03700 10" CONDUIT, TYPE F | 137 FT | $60.00 | $15.00 | $33.00 | $58.00 |
| 611E04400 12" CONDUIT, TYPE B | 10 FT | $86.00 | $25.00 | $70.00 | $200 |
| 611E05200 12" CONDUIT, TYPE F | 111 FT | $75.00 | $21.00 | $38.00 | $74.00 |
| 611E07400 18" CONDUIT, TYPE B | 62 FT | $90.00 | $36.00 | $48.00 | $140 |
| 611E07600 18" CONDUIT, TYPE C | 160 FT | $75.00 | $27.00 | $41.00 | $120 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $2,000 | $1,375 | $2,200 | $3,400 |
| 611E98471 CATCH BASIN, NO. 2-2B, AS PER PLAN | 1 EACH | $2,500 | $1,484 | $2,500 | $3,400 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $3,000 | $2,573 | $4,900 | $6,500 |
| 611E99575 MANHOLE, NO. 3, AS PER PLAN | 1 EACH | $3,500 | $3,030 | $5,600 | $6,500 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 586 SY | $18.00 | $19.55 | $19.15 | $20.00 |
| 301E56100 ASPHALT CONCRETE BASE, PG64-22, (449), (DRIVEWAYS) | 7 CY | $350 | $292 | $267 | $720 |
| 407E20000 NON-TRACKING TACK COAT | 304 GAL | $3.00 | $5.75 | $5.25 | $11.60 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $450 | $408 | $373 | $412 |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 28 SY | $125 | $63.58 | $190 | $330 |
| 621E00100 RPM | 6 EACH | $850 | $776 | $650 | $772 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 6 EACH | $65.00 | $15.00 | $10.00 | $62.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 82 FT | $25.00 | $16.10 | $14.70 | $29.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $15.00 | $23.00 | $21.00 | $185 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 8 EACH | $65.00 | $86.25 | $78.78 | $87.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $20.00 | $23.00 | $21.00 | $24.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.15 MILE | $5,000 | $5,750 | $5,250 | $27,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.1 MILE | $10,000 | $11,500 | $10,500 | $31,500 |
| 407E20000 NON-TRACKING TACK COAT | 20 GAL | $3.00 | $11.50 | $10.50 | $11.60 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 10 CY | $400 | $552 | $504 | $560 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $1,000 | $3,450 | $1,050 | $1,750 |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 0.1 MILE | $9,000 | $10,350 | $9,450 | $10.00 |
| 616E10000 WATER | 10 MGAL | $1.00 | $7.00 | $10.00 | $6.00 |
| 617E10100 COMPACTED AGGREGATE | 50 CY | $69.00 | $56.51 | $52.00 | $103 |
| 202E11000 STRUCTURE REMOVED | 1 LS | $13,500 | $30,000 | $15,000 | $9,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $12,000 | $20,000 | $20,000 | $10,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $13,500 | $20,000 | $20,125 | $20,000 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 4,984 LB | $2.75 | $0.81 | $2.55 | $2.70 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 50 SY | $30.00 | $33.00 | $92.00 | $58.00 |
| 512E33000 TYPE 2 WATERPROOFING | 184 SY | $30.00 | $20.00 | $25.00 | $40.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 40 SF | $25.00 | $4.00 | $8.25 | $17.00 |
| 518E21230 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 1 LS | $7,000 | $4,100 | $5,500 | $5,100 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $15,000 | $20,000 | $7,000 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $1,500 | $15,000 | $3,950 | $1,550 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 376 CY | $275 | $103k | 12% |
| 611E94940 9' X 6' CONDUIT, TYPE A, 706.05 | 60 FT | $1,250 | $75k | 9% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 147 CY | $350 | $51k | 6% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 259 CY | $176 | $46k | 5% |
| 602E20000 CONCRETE MASONRY | 35.7 CY | $1,100 | $39k | 4% |
| 611E25000 66" CONDUIT, TYPE A, 706.02, 707.35, 707.85 OR 72" | 84 FT | $450 | $38k | 4% |
| 659E00300 TOPSOIL | 573 CY | $45 | $26k | 3% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 39 CY | $600 | $23k | 3% |
| 304E20000 AGGREGATE BASE | 368 CY | $63 | $23k | 3% |
| 203E10000 EXCAVATION | 905 CY | $25 | $23k | 3% |